BLD-Final | 3/14/2003 | 3/21/2003 | 3/21/2003 | A | PASS |
Dave Hannah
|
|
|
follow up to 5 day notice pass ok for c.c 3/21/2003 9:45:11 AM
|
DOC - Permit Finaled | 3/21/2003 | 3/21/2003 | 3/21/2003 | A | PASS |
Dave Hannah
|
|
|
Finaled by inspector at 3/21/2003 9:45:29 AM
|
BLD-Aging Inspection | 3/11/2003 | 3/12/2003 | 3/12/2003 | A | FAIL |
Jim Storey
|
|
|
waiting for follow up from dave mortsen job super.no action form phone call earler in week. 5 day notice posted on site no one around. p paine will recieve 5 day notice for on file copy. clone insp for 25 day notice insp. 3/14/2003 10:03:05 AM
|
BLD-Aging Inspection | 3/11/2003 | 3/11/2003 | 3/11/2003 | | PART |
Jim Storey
|
|
|
dave with mortsen said he would have the job super call me to follow up with insp and provide aproved plan. 3/11/2003 5:04:53 PM
|
BLD-Framing/Rough-in | 1/29/2002 | 1/29/2002 | 1/29/2002 | A | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 01/29/2002 at 07:03:49. Contact: ###-####. ok to insulate---fire damper needed in 1-hr fire wall prior to passing at final. 1/29/2002 8:52:18 AM
|
BLD-Energy code compliance | 1/29/2002 | 1/29/2002 | 1/29/2002 | P | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 01/29/2002 at 07:04:54. Contact: ###-####. Insulation verified in building BUT per Table 5-A of 97 UBC opening IS NOT allowed (even with damper) on a S-2-type with in 5 feet even if protected. 1/29/2002 1:49:30 PM
|
BLD-Framing/Rough-in | 1/22/2002 | 1/25/2002 | 1/25/2002 | P | FAIL |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 01/22/2002 at 14:55:55. Contact: ###-####. 30"' X 30" supply air cannot be in 1-Hour opening unless smoke and fire damper is installed with an equi. fire rating. Relocation outside the 1-Hr wall is also an option. 1/25/2002 2:26:41 PM
|
BLD-Wall cover | 12/12/2001 | 12/12/2001 | 12/12/2001 | P | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 12/12/2001 at 10:23:06. Contact: ###-####. shear 12/12/2001 3:00:54 PM
|
BLD-Foundation | 11/26/2001 | 11/26/2001 | 11/26/2001 | P | PART |
Steven Webb
|
|
|
JACK ###-#### house wip--garage not ready 11/26/2001 2:34:50 PM
|
BLD-Footing | 11/20/2001 | 11/20/2001 | 11/20/2001 | P | PASS |
Steven Webb
|
|
|
Engineering recieved from Keith Jones--footing per his engineering. 11/20/2001 1:16:30 PM
|
BLD-Footing | 11/8/2001 | 11/9/2001 | 11/9/2001 | A | FAIL |
Steven Webb
|
|
|
###-#### JACK Electrical conduit which run through footing are not per as the approved plans indicate. Contractor to re-locate conduit which agrees with plans or modifiy plans to eliminate conduit positioned in footings. Do not pour. 11/9/2001 11:38:39 AM
|
BLD-Footing | 11/6/2001 | 11/7/2001 | 11/7/2001 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 11/06/2001 at 19:25:01. Contact: ###-####. Contractor to conference with electrical inspector -- will call for re-inspection. 11/7/2001 11:12:50 AM
|
BLD-Footing | 11/2/2001 | 11/5/2001 | 11/5/2001 | A | DONE |
Steven Webb
|
|
|
###-#### JACK Conference not footing--reviewed approved plans ok to modify to concrete as long as a min. of 12" footer and 6" stem wall is obtained. 11/5/2001 10:53:10 AM
|
(F) Reprint permit | | | 10/26/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/25/2001 | | DONE |
|
|
|
|
Plan assigned to (PEP) | 9/20/2001 | | 10/24/2001 | | PASS |
Perry Paine
|
|
|
10/24/2001 13:42:22 PEP - activity updated through activity BLDA022 from case BLD01-02562.
|
Plan resubmittals received | | | 10/24/2001 | | DONE |
|
|
|
Received two copies of revised sheets SP, A1 and A2. One copy of cover letter and two copies of struc. calculations. Routed to Perry Paine. kmm
|
Print Pending Permit.LaserJet4 | | | 10/24/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/24/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/24/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/24/2001 | | DONE |
|
|
|
|
Telephone call | | | 10/24/2001 | | DONE |
|
|
|
permit ready
|
Plan Review Report | | | 10/16/2001 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 10/16/2001 | | |
|
|
|
faxed plan review report to architect @ ###-####
|
Routing - FIRE | 10/16/2001 | | 10/16/2001 | | PASS |
|
|
|
approved without written comment
|
Routing - PLANNING | 9/20/2001 | | 10/16/2001 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 9/20/2001 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 9/20/2001 | | 9/20/2001 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/20/2001 | | DONE |
|
|
|
|
First Notice | 9/19/2001 | 9/19/2001 | 9/19/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 9/19/2001 | | DONE |
|
|
|
<$25,000
|
Application received | | | 9/19/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/19/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/16/2001 | | | | |
|
|
|
|