Case Summary (BLD) | | | 12/6/2013 | | DONE |
|
|
|
|
Permanent Occupancy | | 10/14/2002 | 10/14/2002 | | DONE |
|
|
|
|
BLD-Final | 10/11/2002 | 10/14/2002 | 10/14/2002 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
ok for perm. occ. 10/14/2002 10:42:30 AM
|
Permanent occupancy | | | 10/14/2002 | | DONE |
|
|
|
Perm. Occ. cert. #9399 issued 10-14-02 to Gem State Gymnastics.
|
FIRE-Final Inspection | 10/11/2002 | 10/11/2002 | 10/11/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled
|
FIRE-Final Inspection | 10/10/2002 | 10/10/2002 | 10/10/2002 | A | FAIL |
Troy Cobbley
|
|
|
provide panic hardware per the building review notes on the main exit door from the day care
|
BLD-Final | 9/23/2002 | 9/25/2002 | 9/25/2002 | A | NR |
Russ Owen
|
|
|
Cathy has the card. This is not ready as I can see fire/life/safety has not approved ? no contact number. 9/25/2002 9:40:13 AM
|
FIRE-Final Inspection | 9/23/2002 | 9/24/2002 | 9/24/2002 | P | FAIL |
Troy Cobbley
|
|
|
no approved plans on site. I did not inspect project 9/24/2002 3:16:30 PM
|
Telephone call | | | 9/23/2002 | | DONE |
|
|
|
Talked w/Harvey (owner) @ ###-#### & he will get in touch w/Alarmco re: fire insp.
|
Telephone call | | | 8/9/2002 | | DONE |
|
|
|
Called & gave a heads up re: status of temp. occ.
|
Telephone call | | | 8/8/2002 | | DONE |
|
|
|
Called contractor & left msg. re: status of temp. occ.
|
Fee Review-notes | 9/20/2001 | 9/20/2001 | 6/19/2002 | | DONE |
|
|
|
|
Temporary occupancy | | | 6/14/2002 | | DONE |
|
|
|
Temp. Occ. Cert. #4827 issued 6-14-02 to Gem State Gymnastics.
|
BLD-Conference | 6/13/2002 | 6/13/2002 | 6/13/2002 | | DONE |
|
|
|
Conference - ok for temp. occ. - Carl
|
BLD-Final | 6/12/2002 | 6/13/2002 | 6/13/2002 | A | PART |
Carl Dependahl
|
|
|
TEMP OCC ###-####- BUTCH ...ok for t/o; fire alarms on temp...struct c/n ok. 6/13/2002 11:41:27 AM
|
FIRE-Final Inspection | 6/11/2002 | 6/12/2002 | 6/12/2002 | A | PART |
Troy Cobbley
|
|
|
I signed a temp for the fire alarm and fire life safety per Dave Millers ok 6/12/2002 10:49:35 AM
|
BLD-Final | 6/11/2002 | 6/12/2002 | 6/12/2002 | A | FAIL |
Jim Sly
|
|
|
###-#### butch call 1st please C/N Need Occ request card. 6/12/2002 11:22:12 AM
|
Print Occupancy Form | | | 6/12/2002 | | DONE |
|
|
|
|
BLD-Final | 4/23/2002 | 4/23/2002 | 4/23/2002 | P | NR |
Dave Hannah
|
|
|
fn insp butch ###-####
|
BLD-Framing/Rough-in | 4/23/2002 | 4/23/2002 | 4/23/2002 | P | PART |
Dave Hannah
|
|
|
Added by Inspector: 425 On 4/23/2002 1:45:49 PM 1hr wall second floor up to bottom of roof ok ceiling grid ok to place tiles
|
BLD-Framing/Rough-in | 4/11/2002 | 4/11/2002 | 4/11/2002 | P | PART |
Carl Dependahl
|
|
|
###-#### call butch first before you go., 2hr wall & clg assy ok; add gyp at top of 1hr sep. wall ( 2nd fl.) remove plastic exhaust duct ( Cl 0 or 1 req'd) return handrails 4/11/2002 5:45:39 PM
|
BLD-Framing/Rough-in | 3/27/2002 | 3/28/2002 | 3/28/2002 | A | CANC |
Jim Sly
|
|
|
###-#### BURT Picked up by 340. 3/28/2002 11:36:05 AM
|
Issue PAID IN FULL permit | | | 2/12/2002 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 9/28/2001 | | 1/29/2002 | | PASS |
Mike Otto
|
|
|
1/29/2002 14:24:17 MLO - activity updated through activity BLDA022 from case BLD01-02575.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/29/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/29/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/29/2002 | | DONE |
|
|
|
|
Telephone call | | | 1/29/2002 | | DONE |
|
|
|
left mess that permit is ready
|
Routing - FIRE | 1/25/2002 | | 1/28/2002 | | PASS |
|
|
|
daycare moved to first floor
|
Routing - PLAN CHECK | 1/16/2002 | | 1/25/2002 | | PASS |
|
|
|
|
Plan resubmittals received | | | 1/24/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets A4-1 with cover letter and submittal information of 2-hour shaftwall/stairwell partition systems. routed to mike otto.
|
Plan resubmittals received | | | 1/15/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets A0-1, A1-1, A2-0, A2-1, A2-2, A2-3, A4-1, with structural calculations and cover letter. Routed to Mike Otto.
|
Routing - FIRE | 10/4/2001 | | 10/8/2001 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 10/4/2001 | | FAIL |
|
|
|
UBC corrections
|
Routing - PLAN CHECK | 10/2/2001 | | 10/4/2001 | | FAIL |
|
|
|
corrections faxed and mailed to architect
|
Routing - PUBLIC WORKS | 9/28/2001 | | 10/1/2001 | | PASS |
|
|
|
|
Plan resubmittals received | | | 10/1/2001 | | DONE |
|
|
|
Received two copies of reivsed sheet A2-1 and CDH department application form. Routed to Mike O. KMM
|
Plans ACCEPTED BY PLAN TECH | | | 9/25/2001 | | DONE |
|
|
|
plans signed off by CDH. No code data on cover sheet. KMM
|
Plans ACCEPTED BY PLAN TECH | | | 9/20/2001 | | HOLD |
|
|
|
needs to be approved by cdh. Plans in hold box. KMM
|
Application received | | | 9/20/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/20/2001 | | |
|
|
|
|