Permit NumberBLD01-02584
StatusFinaled
Name BIG 5 SPORTING GOODS (RACKING)
Site Address 101 N MILWAUKEE ST Unit: #101
Project NameRACKING * SPACE 101
Customer Number 
ePlanReviewNo
Description
(Big 5 Sporting Goods - RACKING)(Space #101) To install steel storage racking/shelving exceeding 8' in height in a 14,195 sq. ft. building per approved plans on file. Work to include steel storage racks/shelving installation per UBC Chapter 22, Division X, and fire sprinkler work. This is a Scope of Work Permit. LETTER OF COMPLETION TO BE ISSUED WHEN DONE. NOTE: This building is fully fire sprinklered for area increase. (PC#0763-01) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes9/21/20019/21/20013/22/2004 DONE
Expired/Cancelled  8/18/2003 DONE
FIRE-Final Inspection1/28/20021/28/20021/28/2002PPASS
DetailsTroy Cobbley
Added by Inspector: 430 On 1/28/2002 3:13:05 PM Fire life/safety finaled. Owner remove excess stock from top of racks
FIRE-Final Inspection1/18/20021/18/20021/18/2002PFAIL
DetailsTroy Cobbley
Added by Inspector: 430 On 1/18/2002 2:09:44 PM The maximum storage height of 10' has been exceeded. Notified store manager that product will need to be taken off of top shelf. I told manager I will be back next week to re-inspect
BLD-Aging Inspection1/16/20021/16/20021/16/2002 PART
DetailsRuss Owen
waiting for fire/life safety. 1/17/2002 2:29:40 PM
BLD-Final11/7/200111/7/200111/7/2001PPASS
DetailsRuss Owen
###-#### DAVE. ok perm oc. 11/8/2001 10:21:14 AM
BLD-Final11/2/200111/5/200111/5/2001APART
DetailsRuss Owen
fn insp dave fox-- ###-#### . needs fire insp and post loads. 11/5/2001 11:03:30 AM
Case Summary (BLD)  10/18/2001  
BLD-Framing/Rough-in10/9/200110/10/200110/10/2001APART
DetailsJim Sly
late am ###-#### Called in wrong permit.......OK to cover 1 side framed walls. 10/10/2001 11:20:55 AM
Issue PAID IN FULL permit  10/5/2001 DONE
Routing - PLAN CHECK10/4/2001 10/4/2001 PASS
Permit and plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  10/4/2001 PASS
Inspection Record Card- Bld  10/4/2001 DONE
Print Occupancy Form  10/4/2001 DONE
Telephone call  10/4/2001 DONE
left mess for terry lane that permit is ready
Plan assigned to (JCB)9/24/2001 10/4/2001 PASS
DetailsJason Blais
10/4/2001 13:30:40 JCB - activity updated through activity BLDA022 from case BLD01-02584.
Routing - PLAN CHECK10/1/2001 10/2/2001 PEND
Will issue racking permit when tenant improvement permit is ready to be issued.
Routing - FIRE9/27/200110/1/200110/1/2001 PASS
DetailsBill Alexander
Plan Review Completed(1st rev)  10/1/2001 DONE
Routing - PLAN CHECK9/24/2001 9/27/2001 PEND
Plan review report sent and faxed to rack professional. No response required. When approved by Fire Dept. permit can be issued. Plans routed to Fire Dept.
Plan routing begun/TENANTS  9/24/2001 DONE
Plans ACCEPTED BY PLAN TECH  9/24/2001 DONE
Received Certificate of Value  9/21/2001 DONE
Recd Pcfee & Taken To Pln CK  9/21/2001 DONE
Application received  9/21/2001