BLD-Final | 5/9/2002 | 5/10/2002 | 5/10/2002 | A | PASS |
Steven Webb
|
|
|
fn steve- ###-#### C. of C. #22398 issued. 5/10/2002 10:55:35 AM
|
DOC - Permit Finaled | 5/10/2002 | 5/10/2002 | 5/10/2002 | A | PASS |
Steven Webb
|
|
|
Finaled by inspector at 5/10/2002 10:55:41 AM
|
BLD-Conference | 4/2/2002 | 4/3/2002 | 4/3/2002 | P | DONE |
Steven Webb
|
|
|
###-#### steve larrondo
|
BLD-Energy code compliance | 2/5/2002 | 2/6/2002 | 2/6/2002 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 02/05/2002 at 12:47:58. Contact: ###-####. ok to cover c/n items complete 2/6/2002 1:18:42 PM
|
BLD-Framing/Rough-in | 1/24/2002 | 1/25/2002 | 1/25/2002 | P | FAIL |
Tom Arcoraci
|
|
|
###-#### cn posted ok to insulate 1/25/2002 3:05:43 PM
|
Inspection Record Card- Bld | | | 1/24/2002 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 1/14/2002 | 1/14/2002 | 1/14/2002 | P | PASS |
Steven Webb
|
|
|
Holdown inspection not framing--ok to cover holdowns. 1/14/2002 1:18:31 PM
|
BLD-Foundation | 12/10/2001 | 12/11/2001 | 12/11/2001 | A | PART |
Dave Hannah
|
|
|
DONNY ###-#### ok to pour all but garage front they need to make ftg continuous along with stim wall 12/11/2001 9:47:19 AM
|
BLD-Footing | 12/7/2001 | 12/10/2001 | 12/10/2001 | P | DONE |
Dave Hannah
|
|
|
###-#### DONNY done friday by steve 12/10/2001 2:27:18 PM
|
BLD-Footing | 12/7/2001 | 12/7/2001 | 12/7/2001 | P | PASS |
Steven Webb
|
|
|
Scheduled by Inspector: 420 On 12/7/2001 3:39:34 PM
|
Plan assigned to (PEP) | 9/27/2001 | | 9/28/2001 | | PASS |
Perry Paine
|
|
|
9/28/2001 09:56:34 PEP - activity updated through activity BLDA022 from case BLD01-02635.
|
Inspector's copy Bld permit | | | 9/28/2001 | | DONE |
|
|
|
|
Plan Review Report | | | 9/28/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/28/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/28/2001 | | DONE |
|
|
|
|
Telephone call | | | 9/28/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/28/2001 | | DONE |
|
|
|
|
Application received | | | 9/27/2001 | | |
|
|
|
|