Fee Review-notes | 10/1/2001 | 10/1/2001 | 5/23/2002 | | DONE |
|
|
|
|
Letter of compliance | | | 3/15/2002 | | DONE |
|
|
|
Letter of Compliance #22309 issued 3-15-02.
|
BLD-Final | 3/13/2002 | 3/14/2002 | 3/14/2002 | A | PASS |
Tom Arcoraci
|
|
|
###-#### PETE CALL 1ST ok for perm 3/14/2002 9:48:58 AM
|
BLD-Final | 3/8/2002 | 3/11/2002 | 3/11/2002 | A | NR |
Tom Arcoraci
|
|
|
###-#### PETE
|
FIRE-Final Inspection | 3/11/2002 | 3/11/2002 | 3/11/2002 | P | PASS |
Troy Cobbley
|
|
|
Fire life/safety finaled 3/11/2002 3:13:27 PM
|
BLD-Framing/Rough-in | 2/15/2002 | 2/15/2002 | 2/15/2002 | P | PASS |
Tom Arcoraci
|
|
|
fr insp -pete ###-#### pending spec insp 2/15/2002 1:27:51 PM
|
BLD-Footing | 12/20/2001 | 12/21/2001 | 12/21/2001 | P | PART |
Dave Hannah
|
|
|
###-#### call to meet there mti is inspecting epoxy and testing concrete they will also check rebar 12/21/2001 1:31:57 PM
|
Issue PAID IN FULL permit | | | 12/7/2001 | | DONE |
|
|
|
|
Telephone call | | | 12/5/2001 | | DONE |
|
|
|
talked to eric peterson to verify plans are still here.will let the g.c.know
|
Plan assigned to (M_P) | 10/2/2001 | | 10/18/2001 | | PASS |
Mike Phillips
|
|
|
10/18/2001 09:11:24 M_P - activity updated through activity BLDA022 from case BLD01-02671.
|
Routing - PLAN CHECK | 10/10/2001 | | 10/18/2001 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/18/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/18/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/18/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/18/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/18/2001 | | DONE |
|
|
|
|
Telephone call | | | 10/18/2001 | | DONE |
|
|
|
permit ready and need ACHD
|
Plan resubmittals received | | | 10/16/2001 | | DONE |
|
|
|
received one set of soils/geotechnical report. Sent to Mike Phillips.
|
Routing - FIRE | 10/5/2001 | | 10/10/2001 | | PASS |
Bill Alexander
|
|
|
No fire review notes attached.
|
Plan Review Completed(1st rev) | | | 10/10/2001 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/5/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 10/3/2001 | | 10/5/2001 | | FAIL |
|
|
|
Plan review completed, called and spoke with Keith Jones about soil bearing pressures over 1,500 pounds. Waiting for reply prior to issuing permit.
|
Routing - PLANNING | 10/2/2001 | | 10/3/2001 | | PASS |
|
|
|
Approved per DRH01-00187.
|
Plans ACCEPTED BY PLAN TECH | | | 10/2/2001 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 10/2/2001 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 10/2/2001 | | 10/2/2001 | | PASS |
|
|
|
|
Application received | | | 10/1/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/1/2001 | | DONE |
|
|
|
|