Fee Review-notes | 7/11/2003 | 7/11/2003 | 7/11/2003 | | DONE |
|
|
|
Additional value from subcontractors.
|
Fee Review-notes | 10/1/2001 | 10/1/2001 | 1/14/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 12/27/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8970 issued 12-27-01 to the Athletic Training Center.
|
BLD-Final | 12/24/2001 | 12/26/2001 | 12/26/2001 | A | PASS |
Tom Arcoraci
|
|
|
###-#### ok for perm occ 12/26/2001 9:04:15 AM
|
Permanent Occupancy | | 12/26/2001 | 12/26/2001 | | DONE |
|
|
|
|
BLD-Final | 12/20/2001 | 12/21/2001 | 12/21/2001 | A | NR |
Russ Owen
|
|
|
###-#### Still needs plumbing finaled. 12/21/2001 10:51:47 AM
|
BLD-Final | 12/19/2001 | 12/20/2001 | 12/20/2001 | A | NR |
Russ Owen
|
|
|
###-#### GREG. plumbing inspection has failed. 12/20/2001 10:21:10 AM
|
BLD-Final | 12/5/2001 | 12/5/2001 | 12/5/2001 | P | PART |
Tom Arcoraci
|
|
|
###-#### GREG ok for temp occneeds plumbing perm 12/5/2001 3:38:34 PM
|
FIRE-Final Inspection | 12/4/2001 | 12/4/2001 | 12/4/2001 | P | PASS |
Troy Cobbley
|
|
|
Fire sprinkler system finaled today. Correction are made 12/4/2001 4:49:32 PM
|
Routing - PLANNING | 12/4/2001 | 12/4/2001 | 12/4/2001 | | PASS |
|
|
|
Approved as per CUP01-00149.
|
FIRE-Final Inspection | 12/3/2001 | 12/3/2001 | 12/3/2001 | P | PASS |
Troy Cobbley
|
|
|
Fire life/safety finaled 12/4/2001 11:27:50 AM
|
BLD-Framing/Rough-in | 11/21/2001 | 11/21/2001 | 11/21/2001 | P | PASS |
Tom Arcoraci
|
|
|
###-#### GREG CEILING GRID
|
BLD-Framing/Rough-in | 11/1/2001 | 11/1/2001 | 11/1/2001 | P | PART |
Tom Arcoraci
|
|
|
###-#### ok to cover bath 11/1/2001 1:00:47 PM
|
BLD-Foundation | 10/26/2001 | 10/26/2001 | 10/26/2001 | P | PART |
Russ Owen
|
|
|
###-#### GREG Footing ok'd by 316. wall steel all inplace.. 10/26/2001 3:55:59 PM
|
BLD-Foundation | 10/24/2001 | 10/25/2001 | 10/25/2001 | A | PART |
Russ Owen
|
|
|
found rebar-gregg- ###-#### . Footing for the concrete wall has been poure w-o insp , only can verify width and verticals , left c/n not to pour wall w-o insp. This is an 8 foot high wall approx 10 long. 10/25/2001 11:23:37 AM
|
BLD-Framing/Rough-in | 10/24/2001 | 10/24/2001 | 10/24/2001 | P | PASS |
Jim Sly
|
|
|
###-#### greg
|
Plan assigned to (M_P) | 10/11/2001 | | 10/22/2001 | | PASS |
Mike Phillips
|
|
|
10/22/2001 11:25:12 M_P - activity updated through activity BLDA022 from case BLD01-02675.
|
Routing - PLAN CHECK | 10/19/2001 | | 10/22/2001 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/22/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/22/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/22/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/22/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/22/2001 | | DONE |
|
|
|
|
Telephone call | | | 10/22/2001 | | DONE |
|
|
|
permit ready
|
Issue PAID IN FULL permit | | | 10/22/2001 | | DONE |
|
|
|
|
Routing - FIRE | 10/17/2001 | 10/19/2001 | 10/19/2001 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 10/19/2001 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/17/2001 | | DONE |
|
|
|
received two sets of plumbing plans P0.0, P1.0, P1.1, P2.0 with a transmittal. Routed to Mike Phillips.
|
Routing - PUBLIC WORKS | 10/12/2001 | | 10/17/2001 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/11/2001 | | 10/12/2001 | | PEND |
|
|
|
Waiting for others to approve prior to issuing permit.
|
Additional plans submitted | | | 10/10/2001 | | DONE |
|
|
|
Received three copies of mech. sheets M0.0, M1.0, M1.1. Put two copies with plans and one in hold box. KMM
|
Plans ACCEPTED BY PLAN TECH | | | 10/2/2001 | | DONE |
|
|
|
State plumb./mech. design build. Left message with Wes Steele about we no not design build. KMM
|
Application received | | | 10/1/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/1/2001 | | |
|
|
|
|