Fee Review-notes | 10/3/2001 | 10/3/2001 | 3/22/2004 | | DONE |
|
|
|
|
BLD-Final | 5/13/2003 | 5/15/2003 | 5/15/2003 | A | PASS |
Jim Sly
|
|
|
bill; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
Letter of compliance | | | 5/15/2003 | | DONE |
|
|
|
Letter of Compliance #22937 issued 5-15-03.
|
FIRE-Final Inspection | 5/13/2003 | 5/14/2003 | 5/14/2003 | A | PASS |
Troy Cobbley
|
|
|
Fire sprinkler and fire alarm passed 5/14/2003 8:49:34 AM
|
FIRE-Final Inspection | 5/7/2003 | 5/9/2003 | 5/9/2003 | A | FAIL |
Troy Cobbley
|
|
|
bill; Phone #: ###-#### Corrections needed for the fire alarm system. See attached FIR01-00613 5/9/2003 11:23:43 AM 5/9/2003 11:24:10 AM
|
BLD-Framing/Rough-in | 1/2/2002 | 1/2/2002 | 1/2/2002 | P | PASS |
Dave Hannah
|
|
|
###-#### ok to cover 1/2/2002 3:21:17 PM
|
Plan assigned to (DRS) | 10/3/2001 | 10/3/2001 | 11/2/2001 | | PASS |
Dan Stuart
|
|
|
11/2/2001 10:52:26 MYS - activity updated through activity BLDA022 from case BLD01-02696.
|
Routing - PLAN CHECK | 10/31/2001 | | 11/2/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/2/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/2/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/2/2001 | | DONE |
|
|
|
|
Telephone call | | | 11/2/2001 | | DONE |
|
|
|
permit ready
|
Issue PAID IN FULL permit | | | 11/2/2001 | | DONE |
|
|
|
|
Routing - FIRE | 10/30/2001 | | 10/31/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 10/29/2001 | | 10/30/2001 | | PASS |
|
|
|
approved per DRH01-00202
|
Routing - PLANNING Land Div | 10/29/2001 | | 10/29/2001 | | PASS |
|
|
|
n/a - tenant improvement w/out expansion. Routed to Planning Dept.
|
Routing - PLAN CHECK | 10/26/2001 | 10/26/2001 | 10/26/2001 | | PEND |
|
|
|
Routing to other agencies for review.
|
Received Certificate of Value | | | 10/26/2001 | | DONE |
|
|
|
Received revised cert. of value. Routed to Dan S. kmm
|
Routing - PLAN CHECK | 10/3/2001 | 10/4/2001 | 10/3/2001 | | FAIL |
|
|
|
Concerns on building area with new canopy additions; approval by zoning; engineering for the roof system and snow load analysis for drifting as new truss' will cause snow to collect on roof. Requested engineering design and either upgrade of construction type to III-N or letter to Building Official Tim Hogland for approval of proposal to allow building to be classified as V-N unlimited area with full sprinkler system and 60 feet on three sides and 54 feet on the West side. My recommendation was to require the III-N compliance as this appears to be the original construction requirement for the mall to make it meet code's. The first floor is about 500 sq. feet over area for a V-N, fully sprinklered with three yards for area increase. The new canopys, 10 +/- feet deep, would add approximately 5,500 sq. ft. to the floor area based on the distance from the building to the centerline of the new columns and posts to bring the total over area to approx. 6,000 sq. ft.. I also need to have Tempra Wilson state that the zoning approval has been given as it was not recorded as part of the Keystone Bank DRH01-00034.
|
Application received | | | 10/3/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/3/2001 | | DONE |
|
|
|
|