BLD-Final | 2/27/2002 | 2/28/2002 | 2/28/2002 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 02/27/2002 at 17:30:29. Contact: ###-####.
|
DOC - Permit Finaled | 2/28/2002 | 2/28/2002 | 2/28/2002 | P | PASS |
Tom Arcoraci
|
|
|
Finaled by inspector at 2/28/2002 4:25:49 PM
|
BLD-Final | 2/26/2002 | 2/27/2002 | 2/27/2002 | P | FAIL |
Russ Owen
|
|
|
ERIC ###-#### c/n posted. 2/27/2002 12:42:06 PM
|
BLD-Concrete | 2/20/2002 | 2/20/2002 | 2/20/2002 | A | FAIL |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 2/20/2002 9:26:24 AM left c/notice called builder no return call as of yet c/n requires driveway to be 3 ft from prop line 2/20/2002 9:28:54 AM
|
BLD-Conference | 2/20/2002 | 2/20/2002 | 2/20/2002 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 2/20/2002 10:52:56 AM owner returned call and is now aware of 3 ft driveway set back from prop line
|
BLD-Framing/Rough-in | 1/10/2002 | 1/10/2002 | 1/10/2002 | P | PASS |
Jim Storey
|
|
|
###-#### JOE c/n justified with engineering. made ok for cover. 1/14/2002 9:34:14 AM
|
BLD-Framing/Rough-in | 1/4/2002 | 1/7/2002 | 1/7/2002 | A | FAIL |
Steven Webb
|
|
|
fr insp- mikki-- ###-#### items on prior c/n not completed. 1/7/2002 8:55:25 AM
|
BLD-Framing/Rough-in | 1/3/2002 | 1/4/2002 | 1/4/2002 | A | PART |
Jim Storey
|
|
|
###-#### roof trusses at loft lower landing bearing wall need truss engineering and load path for floor sys. support. 1/4/2002 10:37:58 AM
|
BLD-Framing/Rough-in | 11/8/2001 | 11/9/2001 | 11/9/2001 | A | CANC |
Dave Hannah
|
|
|
###-#### TIM
|
BLD-Foundation | 11/9/2001 | 11/9/2001 | 11/9/2001 | A | PART |
Dave Hannah
|
|
|
Added by Inspector: 425 On 11/9/2001 10:01:05 AM work in progress
|
BLD-Footing | 11/5/2001 | 11/6/2001 | 11/6/2001 | A | PART |
Dave Hannah
|
|
|
###-#### TIM work in progress 11/6/2001 11:08:49 AM
|
Issue PAID IN FULL permit | | | 11/5/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/16/2001 | | 10/25/2001 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 10/24/2001 | | 10/25/2001 | | PASS |
Steve Munroe
|
|
|
10/25/2001 06:38:22 SAM - activity updated through activity BLDA022 from case BLD01-02770.
|
Print Pending Permit.LaserJet4 | | | 10/25/2001 | | |
|
|
|
|
Plan Review Report | | | 10/25/2001 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/25/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/25/2001 | | DONE |
|
|
|
|
Telephone call | | | 10/25/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Pending Assignment by DJO | 10/16/2001 | | 10/24/2001 | | DONE |
Dan Overy
|
|
|
10/24/2001 11:09:27 SAM - activity updated through activity BLDA183 from case BLD01-02770.
|
Routing - PLANNING | 10/16/2001 | | 10/16/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 10/16/2001 | | 10/16/2001 | | PASS |
|
|
|
|
Application received | | | 10/16/2001 | | |
|
|
|
|