Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD01-02771
StatusFinaled
Name DEBRHA J CARNAHAN LAW OFFICE
Site Address 101 S CAPITOL BLVD
Project NameUS BANK-4TH FLR
Customer Number 
ePlanReviewNo
Description
(DEBRHA J CARNAHAN LAW OFFICE)(US BANK-SUITE 400) To remodel a 1,687 sq.ft. office space for new tenant per approved plans on file. Work to include construction of new rated doors into rated main corridor, new rated wall surrounding entry doors, new interior office partitions and miscellaneous finish. NOTE: This building is fully fire sprinklered. (P.C.#0806-01) mys
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  7/2/2013 DONE
Fee Review-notes10/16/200110/16/20011/14/2002 DONE
BLD-Final12/26/200112/26/200112/26/2001PPASS
DetailsCarl Dependahl
###-####, firesafing installed 12/26/2001 1:49:27 PM
Permanent Occupancy 12/26/200112/26/2001 DONE
Details
Permanent occupancy  12/26/2001 DONE
Perm. Occ. Cert. #8969 issued 12-26-01 to Debrha J. Carnahan Law Ofc. on the 4th floor of the U.S. Bank Bldg.
FIRE-Final Inspection12/24/200112/24/200112/24/2001PPASS
DetailsTroy Cobbley
Added by Inspector: 430 On 12/24/2001 12:22:41 PM Fire life/safety finaled
BLD-Framing/Rough-in12/20/200112/21/200112/21/2001APART
DetailsCarl Dependahl
above ceiling insp dave ###-####...add firesafing at window areasper plan note 14.
chk at final 12/21/2001 2:39:52 PM
FIRE-Final Inspection12/21/200112/21/200112/21/2001PFAIL
DetailsRick Jackson
Scheduled by Inspector: 409 On 12/21/2001 2:03:31 PM need lobby door hardware and closure; alarms tested okay; 12/21/2001 2:08:01 PM
FIRE-Sprinkler Rough-in12/5/200112/5/200112/5/2001AFAIL
DetailsRick Jackson
Added by Inspector: 409 On 12/5/2001 9:50:52 AM not approved for cover; more than one head per drop in same fire area
BLD-Framing/Rough-in12/3/200112/3/200112/3/2001PPART
DetailsJim Storey
###-#### CHRIS wall framing covered with out insp. corridor west wing wall and ceilling not complet gyp. need reinsp/ primary steel protection needs repaced. 12/3/2001 3:41:49 PM
Issue PAID IN FULL permit  11/15/2001 DONE
Plan assigned to (MYS)10/19/2001 11/14/2001 PASS
DetailsMarlene Southard
11/14/2001 11:00:19 MYS - activity updated through activity BLDA022 from case BLD01-02771.
Routing - FIRE11/9/2001 11/14/2001 PASS
Plan Review Completed(1st rev)  11/14/2001 PASS
Routing - PLAN CHECK11/14/2001 11/14/2001 PASS
PLANS/APPL TAKEN TO FRONT DESK  11/14/2001 DONE
Print Occupancy Form  11/14/2001 DONE
Inspection Record Card- Bld  11/14/2001 DONE
Telephone call  11/14/2001 DONE
permit ready
Routing - PLAN CHECK10/29/2001 11/9/2001 PEND
Approved pending Fire review and approval. Copy of plan review faxed to architect.
Routing - PUBLIC WORKS10/26/2001 10/29/2001 PASS
Routing - PLANNING Land Div10/19/2001 10/26/2001 PASS
n/a - tenant improvement w/out expansion. Routed to Public Works.
Recd Pcfee & Taken To Pln CK  10/16/2001  
Plans ACCEPTED BY PLAN TECH  10/16/2001  
Application received  10/16/2001