Case Summary (BLD) | | | 11/4/2005 | | |
|
|
|
|
Fee Review-notes | 7/11/2003 | 7/11/2003 | 7/11/2003 | | DONE |
|
|
|
Additional value from subcontractors.
|
Fee Review-notes | 10/16/2001 | 10/16/2001 | 12/16/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 4/29/2002 | | DONE |
|
|
|
occ #9117 issued 4/29/02 to Alcohol Tobacco & Firearms.
|
Permanent Occupancy | | 4/25/2002 | 4/25/2002 | | DONE |
|
|
|
|
BLD-Final | 4/24/2002 | 4/25/2002 | 4/25/2002 | A | PASS |
Carl Dependahl
|
|
|
###-####
|
BLD-Final | 2/20/2002 | 2/21/2002 | 2/21/2002 | A | PART |
Carl Dependahl
|
|
|
fn- mike ###-#### ; ok for t/o, complete int finish, etc. 2/25/2002 1:33:53 PM
|
FIRE-Final Inspection | 2/15/2002 | 2/20/2002 | 2/20/2002 | A | PASS |
Rick Jackson
|
|
|
MIKE ###-####
|
FIRE-Final Inspection | 2/15/2002 | 2/19/2002 | 2/19/2002 | A | NR |
Rick Jackson
|
|
|
MIKE ###-#### rescheduled for 2/20/02 2/19/2002 9:24:18 AM
|
BLD-Framing/Rough-in | 1/28/2002 | 1/29/2002 | 1/29/2002 | P | PART |
Carl Dependahl
|
|
|
###-#### MIKE "tunnel" const ok, seal misc penetrations at corridor (plbg) addkickers at int walls & spacers for grid clg...ok to tile as noted. 1/29/2002 3:35:01 PM
|
BLD-Framing/Rough-in | 12/19/2001 | 12/20/2001 | 12/20/2001 | A | PART |
Carl Dependahl
|
|
|
###-####
|
BLD-Framing/Rough-in | 12/7/2001 | 12/10/2001 | 12/10/2001 | A | FAIL |
Carl Dependahl
|
|
|
###-####; need arch's clarification and struct framing details 12/10/2001 12:15:23 PM for tunnel, ok to 1 12/10/2001 12:15:43 PM
|
Issue PAID IN FULL permit | | | 12/7/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/5/2001 | | 12/6/2001 | | PASS |
Ron Hill
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/6/2001 | | PASS |
Ron Hill
|
|
|
|
Print Occupancy Form | | | 12/6/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/6/2001 | | DONE |
|
|
|
|
Telephone call | | | 12/6/2001 | | DONE |
|
|
|
permit ready
|
Plan assigned to (R_H) | 10/19/2001 | | 12/6/2001 | | PASS |
|
|
|
12/6/2001 16:16:36 RMH - activity updated through activity BLDA022 from case BLD01-02775.
|
Routing - PLAN CHECK | 11/16/2001 | | 12/5/2001 | | |
|
|
|
|
Routing - PUBLIC WORKS | 12/5/2001 | | 12/5/2001 | | PASS |
|
|
|
|
Plan Review Report | | | 11/19/2001 | | DONE |
|
|
|
|
Routing - FIRE | 11/14/2001 | | 11/16/2001 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/9/2001 | | 11/14/2001 | | PEND |
Ron Hill
|
|
|
Passed in building department review, Received resubmittals showing change in door hardware. Plans pending fire department review and approvals
|
Plan Review Completed(1st rev) | | | 11/9/2001 | | FAIL |
|
|
|
|
Routing - FIRE | 11/5/2001 | | 11/9/2001 | | FAIL |
|
|
|
I-3 NOT ALLOWED
|
Routing - PLAN CHECK | 10/30/2001 | | 11/5/2001 | | FAIL |
Ron Hill
|
|
|
|
Plan Review Report | | | 11/2/2001 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 10/26/2001 | | 10/30/2001 | | FAIL |
|
|
|
Environmental waiting for additional information from eng. Louise Waldorf. kmm
|
Routing - PLANNING Land Div | 10/19/2001 | | 10/26/2001 | | PASS |
|
|
|
n/a - tenant improvement w/out expansion. Routed to Public Works.
|
Plans ACCEPTED BY PLAN TECH | | | 10/17/2001 | | DONE |
|
|
|
|
Application received | | | 10/16/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/16/2001 | | |
|
|
|
|