BLD-Final | 3/29/2002 | 3/29/2002 | 3/29/2002 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/29/2002 at 08:25:10. Contact: ###-####.
|
DOC - Permit Finaled | 3/29/2002 | 3/29/2002 | 3/29/2002 | P | PASS |
Russ Owen
|
|
|
Finaled by inspector at 3/29/2002 5:04:30 PM
|
BLD-Energy code compliance | 2/15/2002 | 2/15/2002 | 2/15/2002 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 02/15/2002 at 08:13:32. Contact: ###-####.ok to cover 2/15/2002 2:52:57 PM
|
BLD-Other | 2/13/2002 | 2/14/2002 | 2/14/2002 | A | DONE |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 02/13/2002 at 14:46:54. Contact: ###-####.
|
BLD-Energy code compliance | 2/13/2002 | 2/14/2002 | 2/14/2002 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 02/13/2002 at 14:47:34. Contact: ###-####. seal package ok to insulate 2/14/2002 10:32:01 AM
|
BLD-Framing/Rough-in | 2/13/2002 | 2/13/2002 | 2/13/2002 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 02/13/2002 at 07:40:16. Contact: ###-####.c/n on site 2/13/2002 3:46:42 PM
|
BLD-Other | 2/7/2002 | 2/7/2002 | 2/7/2002 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/07/2002 at 09:58:48. Contact: ###-####.
ext. shear ok 2/7/2002 2:52:15 PM
|
BLD-Framing/Rough-in | 2/5/2002 | 2/6/2002 | 2/6/2002 | A | NR |
Tony Young
|
|
|
shear 2/5/2002 3:34:49 PM
|
BLD-Other | 2/6/2002 | 2/6/2002 | 2/6/2002 | P | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/06/2002 at 08:17:42. Contact: ###-####.
shear not nailed per plan 2/6/2002 1:59:47 PM
|
BLD-Other | 2/5/2002 | 2/5/2002 | 2/5/2002 | P | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/05/2002 at 08:47:32. Contact: ###-####.
|
BLD-Foundation | 12/14/2001 | 12/14/2001 | 12/14/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/14/2001 at 07:23:38. Contact: ###-####.wip 12/14/2001 9:49:45 AM
|
BLD-Footing | 12/10/2001 | 12/11/2001 | 12/11/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/10/2001 at 15:07:11. Contact: ###-####.
wip, ok after thaw 12/11/2001 9:49:38 AM
|
Issue PAID IN FULL permit | | | 12/10/2001 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/26/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/26/2001 | | DONE |
|
|
|
|
Telephone call | | | 11/26/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Routing - PLAN CHECK | 11/2/2001 | | 11/23/2001 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 11/8/2001 | | 11/23/2001 | | PASS |
Steve Munroe
|
|
|
11/23/2001 10:36:25 SAM - activity updated through activity BLDA022 from case BLD01-02902.
|
Print Pending Permit.LaserJet4 | | | 11/23/2001 | | |
|
|
|
|
Plan Review Report | | | 11/23/2001 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/23/2001 | | DONE |
|
|
|
|
Pending Assignment by DJO | 10/31/2001 | | 11/8/2001 | | DONE |
Dan Overy
|
|
|
11/8/2001 16:22:12 SAM - activity updated through activity BLDA183 from case BLD01-02902.
|
Routing - PLANNING | 10/31/2001 | | 11/2/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 11/2/2001 | | 11/2/2001 | | PASS |
|
|
|
|
Application received | | | 10/31/2001 | | |
|
|
|
|