Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD01-02910
StatusFinaled
Name 300 MAIN (SITE MODIFICATIONS)
Site Address 300 W MAIN ST
Project Name300 MAIN
Customer Number 
ePlanReviewNo
Description
(300 MAIN)(EXTERIOR SITE MODIFICATIONS) New exterior site modifications for existing building per approved plans on file. Work to include new exterior stairs with handrails, new landings at existing exterior doors, new flat and sloped walks, new patio, new guardrail at one location, landscaping and irrigation. Planning approval done under DRH01-00197. This is a Scope of Work Permit. LETTER OF COMPLETION TO BE ISSUED WHEN DONE. NOTE: This building is NOT fire sprinklered. (PC#0841-01) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes11/2/200111/2/20013/22/2004 DONE
BLD-Aging Inspection7/24/20037/24/20037/24/2003 DONE
DetailsCarl Dependahl
work done, bldg completed & FINALLED! 7/24/2003 8:12:09 AM
DOC - Permit Finaled7/24/20037/24/20037/24/2003APASS
DetailsCarl Dependahl
Finaled by inspector at 7/24/2003 8:12:11 AM
DOC - Permit Finaled7/24/20037/24/20037/24/2003APASS
DetailsCarl Dependahl
Finaled by inspector at 7/24/2003 9:42:16 AM
BLD-Final5/9/20025/10/20025/10/2002APART
DetailsCarl Dependahl
dave ###-####--complete ext work...t/o ok (l/c only) 5/10/2002 4:53:55 PM
BLD-Conference5/10/20025/9/20025/10/2002APASS
DetailsWm. Michael Meloy
Scheduled by Inspector: WMM On 5/10/2002 9:32:04 AM
BLD-Conference5/3/20025/3/20025/3/2002PPART
DetailsCarl Dependahl
add extensions (23" ) at handrails...install guards, rails as shown on approved plans
BLD-Concrete1/15/20021/16/20021/16/2002APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 01/15/2002 at 17:22:03. Contact: ###-####. west side stairs, ramp ok 1/16/2002 10:52:17 AM
BLD-Other1/16/20021/16/20021/16/2002PPART
DetailsCarl Dependahl
STEPS AUDIE ###-#### CELL # ###-####...work appears ok, need verify to plan 1/16/2002 3:42:23 PM
BLD-Footing1/1/20021/2/20021/2/2002APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 01/01/2002 at 10:25:26. Contact: ###-####.front at west side walls ok. 1/2/2002 10:51:31 AM
BLD-Footing12/26/200112/27/200112/27/2001PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/26/2001 at 13:34:25. Contact: ###-####. west ft at stairs ok for cover. 12/27/2001 2:51:17 PM
Issue PAID IN FULL permit  12/21/2001 DONE
Print Occupancy Form  12/5/2001 DONE
Inspection Record Card- Bld  12/5/2001 DONE
Telephone call  12/5/2001 DONE
permit ready
Plan Review Completed(1st rev)  12/4/2001 PASS
Routing - PLAN CHECK12/4/2001 12/4/2001 PASS
Plans and permit approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  12/4/2001 PASS
Plan assigned to (JCB)11/13/2001 12/4/2001 PASS
DetailsJason Blais
12/4/2001 13:42:59 JCB - activity updated through activity BLDA022 from case BLD01-02910.
Routing - FIRE11/30/2001 12/4/2001 PASS
approved as drawn
Routing - PLAN CHECK11/16/2001 11/30/2001 PEND
Plan review report sent and faxed to architect. No response required. When approved by Fire Dept. permit can be issued. Plans routed to Fire Dept.
Routing - PLANNING11/15/2001 11/16/2001 PASS
Sarah Schafer.
Routing - PUBLIC WORKS11/13/2001 11/15/2001 PASS
Brian Murphy.
Plans ACCEPTED BY PLAN TECH  11/2/2001 DONE
Application received  11/2/2001  
Recd Pcfee & Taken To Pln CK  11/2/2001