BLD-Final | 8/15/2003 | 8/15/2003 | 8/15/2003 | P | PASS |
Dave Hannah
|
|
|
per our conversation
|
DOC - Permit Finaled | 8/15/2003 | 8/15/2003 | 8/15/2003 | P | PASS |
Dave Hannah
|
|
|
Finaled by inspector at 8/15/2003 5:04:27 PM
|
Letter of compliance | | | 8/15/2003 | | DONE |
|
|
|
Letter of Compliance #22985 issued 8-15-03 by Barbara.
|
BLD-Final | 8/13/2003 | 8/14/2003 | 8/14/2003 | P | FAIL |
Dave Hannah
|
|
|
dwight; Phone #: ###-#### Internet Inspection Request from: Darla Downs every thing ok but needs a plumbing final ok for c.c after plumbing in finaled 8/14/2003 3:06:53 PM
|
BLD-Grading Inspection | 7/23/2003 | 7/23/2003 | 7/23/2003 | | PASS |
Rita DeYoung
|
|
|
FINAL GRADING AND DRAINAGE APPROVED
|
BLD-Conference | 7/14/2003 | 7/14/2003 | 7/14/2003 | P | PASS |
Carl Dependahl
|
|
|
per carl dwight cell ###-####...wip, ok to continue 7/14/2003 1:15:25 PM
|
BLD-Conference | 12/18/2002 | 12/18/2002 | 12/18/2002 | P | PASS |
Dave Hannah
|
|
|
JUST NEEDS EXTENDED ok to extend work in progress 12/18/2002 4:37:48 PM
|
PostCard Mailed | | | 12/6/2002 | | SENT |
|
|
|
PostCard has been mailed requesting inspection.
|
BLD-Energy code compliance | 6/5/2002 | 6/6/2002 | 6/6/2002 | A | PASS |
Tony Young
|
|
|
###-#### dwight
|
BLD-Energy code compliance | 6/3/2002 | 6/4/2002 | 6/4/2002 | P | NR |
Dave Hannah
|
|
|
###-#### DWIGHT
|
BLD-Framing/Rough-in | 5/16/2002 | 5/17/2002 | 5/17/2002 | A | CANC |
Tony Young
|
|
|
dwight ###-####
|
BLD-Framing/Rough-in | 5/17/2002 | 5/17/2002 | 5/17/2002 | P | FAIL |
Tony Young
|
|
|
dwight ###-####/// c/n posted
need struct. eng. to sign off on shear/ componets,////// covered w/out inspection
ok to insulate after engineer approves,, other corrections on list 5/17/2002 4:34:43 PM
|
BLD-Foundation | 1/17/2002 | 1/18/2002 | 1/18/2002 | P | PART |
Steven Webb
|
|
|
###-#### wip--Per revised eng. plans--No city approved plans on site--discussed with builder--eng. plans exceed code on basement wall--Eng. plans by Pinnacle Eng. 1/18/2002 2:48:00 PM
|
BLD-Grading Inspection | 1/9/2002 | 1/9/2002 | 1/9/2002 | | PASS |
Rita DeYoung
|
|
|
Geotechnical engineer has approved the foundation subgrade. Small soft spot along northeast end must be scraped before footing is poured.
|
BLD-Footing | 1/9/2002 | 1/9/2002 | 1/9/2002 | P | PASS |
Tom Arcoraci
|
|
|
###-####
|
Issue PAID IN FULL permit | | | 12/3/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/27/2001 | | DONE |
|
|
|
|
Telephone call | | | 11/27/2001 | | DONE |
|
|
|
|
Plan assigned to (DJO) | 11/26/2001 | 11/26/2001 | 11/26/2001 | | PASS |
Dan Overy
|
|
|
11/26/2001 15:02:54 DJO - activity updated through activity BLDA022 from case BLD01-02919.
|
Plan Review Report | | | 11/26/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/26/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/26/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 11/26/2001 | | |
|
|
|
|
Routing - PLANNING | 11/16/2001 | | 11/20/2001 | | PASS |
|
|
|
|
Routing - FIRE | 11/20/2001 | | 11/20/2001 | | COND |
|
|
|
Fire sprinklers per UFPA 13D and a Class A roof are required for this house on Lot 76 of Morningside Heights subdivision.
|
Routing - PUBLIC WORKS GRADING | 11/15/2001 | 11/15/2001 | 11/15/2001 | | PASS |
Rita DeYoung
|
|
|
Grading plan approved with conditions of approval in letter from Boise Public Works attached to plan.
|
Routing - PUBLIC WORKS | 11/15/2001 | | 11/15/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 11/5/2001 | | 11/8/2001 | | FAIL |
Rita DeYoung
|
|
|
Grading plan needs revision. Wrote letter to engineer.
|
Application received | | | 11/5/2001 | | |
|
|
|
|
Extend Permit 180 days | | 8/13/2003 | | | |
|
|
|
ok to extend permit per david hannah ... i put this permit back to issue mode for the final ///dld 8-13-03
|
Pending Assignment by DJO | 11/5/2001 | | | | |
Dan Overy
|
|
|
|
Routing - PLAN CHECK | 11/20/2001 | | | | |
|
|
|
|