DOC - Permit Finaled | 6/26/2002 | 6/26/2002 | 6/26/2002 | P | PASS |
Jim Sly
|
|
|
Finaled by inspector at 6/26/2002 2:20:16 AM
|
BLD-Final | 6/24/2002 | 6/25/2002 | 6/25/2002 | P | PASS |
Jim Sly
|
|
|
fn -dan- ###-#### C/C issued. 6/26/2002 2:20:09 AM
|
BLD-Framing/Rough-in | 2/14/2002 | 2/15/2002 | 2/15/2002 | P | PASS |
Jim Sly
|
|
|
DAN ###-####
|
BLD-Energy code compliance | 2/14/2002 | 2/15/2002 | 2/15/2002 | P | PASS |
Jim Sly
|
|
|
DAN ###-####
|
BLD-Framing/Rough-in | 2/12/2002 | 2/13/2002 | 2/13/2002 | A | FAIL |
Jim Sly
|
|
|
###-#### DAN C/N posted. 2/13/2002 1:19:46 PM
|
BLD-Framing/Rough-in | 1/21/2002 | 1/22/2002 | 1/22/2002 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 01/21/2002 at 09:36:38. Contact: . Shear OK. 1/22/2002 12:10:18 PM
|
BLD-Foundation | 12/20/2001 | 12/21/2001 | 12/21/2001 | A | PART |
Jim Sly
|
|
|
###-####\\plans are in elec box 941- 711\\plans are in elec box 12/21/2001 9:45:29 AM Footing OK. 12/21/2001 9:45:45 AM
|
Issue PAID IN FULL permit | | | 12/17/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/20/2001 | | DONE |
|
|
|
|
Telephone call | | | 11/20/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Pending Assignment by DJO | 11/7/2001 | | 11/19/2001 | | DONE |
Dan Overy
|
|
|
11/19/2001 09:37:51 SAM - activity updated through activity BLDA183 from case BLD01-02950.
|
Routing - PLAN CHECK | 11/8/2001 | | 11/19/2001 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 11/19/2001 | | 11/19/2001 | | PASS |
Steve Munroe
|
|
|
11/19/2001 15:20:23 SAM - activity updated through activity BLDA022 from case BLD01-02950.
|
Print Pending Permit.LaserJet4 | | | 11/19/2001 | | |
|
|
|
|
Plan Review Report | | | 11/19/2001 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/19/2001 | | DONE |
|
|
|
|
Routing - PLANNING | 11/7/2001 | | 11/8/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 11/8/2001 | | 11/8/2001 | | PASS |
|
|
|
|
Application received | | | 11/7/2001 | | |
|
|
|
|