BLD-Final | 8/6/2002 | 8/8/2002 | 8/8/2002 | A | PASS |
Tony Young
|
|
|
terry; Phone #: ###-####
NOTE: THE DOWNSTAIRS IS NOT FINISHED AND SHOULD BE INSPECTED BEFORE COVER TO ENSURE DRAFT/FIREBLOCKS ARE IN 8/8/2002 11:29:16 AM
|
DOC - Permit Finaled | 8/8/2002 | 8/8/2002 | 8/8/2002 | A | PASS |
Tony Young
|
|
|
Finaled by inspector at 8/8/2002 11:24:55 AM
|
BLD-Grading Inspection | 8/2/2002 | 8/2/2002 | 8/2/2002 | | BOND |
Rita DeYoung
|
|
|
Rough grading is complete. Fine grading and revegetation have not been completed. For this the engineer recommended a $1300.00 bond. Upon receipt of this bond the grading and drainage is conditionally approved.
|
BLD-Framing/Rough-in | 5/22/2002 | 5/22/2002 | 5/22/2002 | P | PASS |
Tony Young
|
|
|
re-insp for f/p- terry- ###-####-also shear
|
BLD-Conference | 5/17/2002 | 5/20/2002 | 5/20/2002 | A | CANC |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 5/16/2002 | 5/17/2002 | 5/17/2002 | P | PASS |
Tony Young
|
|
|
terry ###-#### fr -re-insp
|
BLD-Energy code compliance | 5/16/2002 | 5/17/2002 | 5/17/2002 | A | PASS |
Tony Young
|
|
|
terry -###-####
|
CHANGE STATUS TO (ISS) | | | 5/16/2002 | | |
|
|
|
|
BLD-Framing/Rough-in | 5/14/2002 | 5/15/2002 | 5/15/2002 | P | FAIL |
Jim Sly
|
|
|
###-#### TERRY C/N on site 5/15/2002 4:38:15 PM
|
BLD-Framing/Rough-in | 4/22/2002 | 4/23/2002 | 4/23/2002 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 04/22/2002 at 16:37:11. Contact: ###-####.
ext. shear nailing ok except need fix from sruct. engineer on hd by front door and 4x material on shearwall #4 4/23/2002 3:57:33 PM
|
BLD-Conference | 4/23/2002 | 4/23/2002 | 4/23/2002 | P | PART |
Tony Young
|
|
|
conference on winder stairs 4/23/2002 11:30:15 AM
w/ G.SLANE, stairs as they are do not meet code now, need to at frame inspection 4/23/2002 4:42:19 PM
|
BLD-Foundation | 2/12/2002 | 2/12/2002 | 2/12/2002 | P | PART |
Tony Young
|
|
|
###-####
|
BLD-Footing | 2/6/2002 | 2/7/2002 | 2/7/2002 | A | PART |
Tony Young
|
|
|
CLINT ###-#### FT
|
BLD-Footing | 2/6/2002 | 2/6/2002 | 2/6/2002 | P | NR |
Tony Young
|
|
|
###-####
|
Issue PAID IN FULL permit | | | 12/12/2001 | | DONE |
|
|
|
|
Telephone call | | | 12/3/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Plan assigned to (DJO) | 11/29/2001 | 11/29/2001 | 11/30/2001 | | PASS |
Dan Overy
|
|
|
11/30/2001 08:09:20 DJO - activity updated through activity BLDA022 from case BLD01-03009.
|
Case Summary (BLD) | | | 11/30/2001 | | DONE |
|
|
|
|
Plan Review Report | | | 11/30/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/30/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/30/2001 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 11/29/2001 | | |
|
|
|
started review thursday morning 11/29/01
|
Plans ACCEPTED BY PLAN CHECK | | | 11/29/2001 | | |
|
|
|
|
Routing - FIRE | 11/21/2001 | | 11/26/2001 | | DONE |
|
|
|
There is no FD requirement for fire sprinklers for this lot 27, Block 1.
|
Routing - PUBLIC WORKS | 11/19/2001 | | 11/21/2001 | | |
|
|
|
|
Routing - PLANNING | 11/19/2001 | | 11/21/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 11/16/2001 | | 11/16/2001 | | PASS |
Rita DeYoung
|
|
|
APPROVED AS CATEGORY 3 WITH CONDITONS OF APPROVAL IN LETTER ATTACHED TO PLANS
|
Application received | | | 11/16/2001 | | |
|
|
|
|
Pending Assignment by DJO | 11/16/2001 | | | | |
Dan Overy
|
|
|
|
Routing - PLAN CHECK | 11/26/2001 | | | | |
|
|
|
|