Fee Review-notes | 7/14/2003 | 7/14/2003 | 7/14/2003 | | DONE |
|
|
|
Additional values from subcontractors.
|
Permanent occupancy | | | 5/15/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9133 issued 5-15-02 to Idacorp Financial.
|
BLD-Final | 5/9/2002 | 5/9/2002 | 5/9/2002 | A | PASS |
Jim Storey
|
|
|
|
Permanent Occupancy | | 5/9/2002 | 5/9/2002 | | DONE |
|
|
|
|
BLD-Final | 5/8/2002 | 5/8/2002 | 5/8/2002 | P | FAIL |
Jim Storey
|
|
|
1. (Glass labels) Each light shall bear the manufacturer's label designating the type and thickness of glass. When approved by the building official, labels may be omitted, provided an affidavit is furnished by the glazing contractor certifying that each light is glazed in accordance with approved plans and specifications. (1997 UBC 2402)
|
BLD-Final | 5/1/2002 | 5/1/2002 | 5/1/2002 | P | FAIL |
Carl Dependahl
|
|
|
###-#### TIM complete glazing, misc. finish; ok for t/o. 5/1/2002 5:13:45 PM
|
FIRE-Final Inspection | 4/29/2002 | 4/29/2002 | 4/29/2002 | P | PASS |
Rick Jackson
|
|
|
tim ###-#### -fire fn
|
BLD-Framing/Rough-in | 4/23/2002 | 4/23/2002 | 4/23/2002 | P | PART |
Carl Dependahl
|
|
|
ceiling grid- jim ###-####...grid ok 4/23/2002 4:47:25 PM
|
Issue PAID IN FULL permit | | | 2/6/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/14/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/14/2002 | | DONE |
|
|
|
|
Telephone call | | | 1/14/2002 | | DONE |
|
|
|
permit ready
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2002 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 12/7/2001 | | 1/11/2002 | | PASS |
|
|
|
Reviewed resubmitted drawings. Drawings approved.
|
Plan assigned to (CJW) | 11/21/2001 | | 1/11/2002 | | PASS |
Carl Westfall
|
|
|
1/11/2002 13:37:49 CJW - activity updated through activity BLDA022 from case BLD01-03024.
|
Plan resubmittals received | | | 1/9/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets A0.0, A1.0, A2.0, A3.0, to include cover letter. Routed to Carl Westfall.
|
Routing - FIRE | 12/5/2001 | 12/7/2001 | 12/7/2001 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 12/7/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/29/2001 | | 12/4/2001 | | PASS |
|
|
|
UBC plan review started December 3, 2001 and finished the next day. The drawings were approved with conditions. See the conditions list.
|
Routing - PUBLIC WORKS | 11/27/2001 | | 11/29/2001 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 11/21/2001 | | 11/27/2001 | | PASS |
|
|
|
N/A - tenant improvement w/out expansion. **If they expand, they will have to prove legal land division and may need a density reduction record of survey. Routed to Public Works. (blc)
|
First Notice | 11/19/2001 | 11/19/2001 | 11/19/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/19/2001 | | DONE |
|
|
|
1. General Notes on A2.0 state "All Plumbing is Design build".
2. General Notes on A2.0 state "All HVAC is Design Build".
3. General Notes on A2.0 state "All Electrical is Design build".
|
Application received | | | 11/19/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/19/2001 | | DONE |
|
|
|
|