Permit Information
Permit NumberBLD01-03024
StatusFinaled
Name IDACORP FINANCIAL
Site Address 205 N 10TH ST Unit: 510
Project NameEMPIRE BLDG-5TH FLR
Customer Number 
ePlanReviewNo
Description
(IDACORP FINANCIAL) This building is fire sprinklered under the provisions of the 1994 UCBC because it is too tall and too big. To construct a 2,200 square foot office tenant space on the 5th floor of the Empire Building (Southeast corner). Work is to include interior nonbearing walls, furred down ceilings, suspended ceilings, glass block walls, interior doors and windows, and interior finishes all per approved drawings and plan review conditions on file. Fire sprinkler heads shall be located per NFPA 13-1999 as regulated by the Fire Department. PC01-0870 **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes7/14/20037/14/20037/14/2003 DONE
Additional values from subcontractors.
Permanent occupancy  5/15/2002 DONE
Perm. Occ. Cert. #9133 issued 5-15-02 to Idacorp Financial.
BLD-Final5/9/20025/9/20025/9/2002APASS
DetailsJim Storey
Permanent Occupancy 5/9/20025/9/2002 DONE
Details
BLD-Final5/8/20025/8/20025/8/2002PFAIL
DetailsJim Storey
1. (Glass labels) Each light shall bear the manufacturer's label designating the type and thickness of glass. When approved by the building official, labels may be omitted, provided an affidavit is furnished by the glazing contractor certifying that each light is glazed in accordance with approved plans and specifications. (1997 UBC 2402)
BLD-Final5/1/20025/1/20025/1/2002PFAIL
DetailsCarl Dependahl
###-#### TIM complete glazing, misc. finish; ok for t/o. 5/1/2002 5:13:45 PM
FIRE-Final Inspection4/29/20024/29/20024/29/2002PPASS
DetailsRick Jackson
tim ###-#### -fire fn
BLD-Framing/Rough-in4/23/20024/23/20024/23/2002PPART
DetailsCarl Dependahl
ceiling grid- jim ###-####...grid ok 4/23/2002 4:47:25 PM
Issue PAID IN FULL permit  2/6/2002 DONE
Print Occupancy Form  1/14/2002 DONE
Inspection Record Card- Bld  1/14/2002 DONE
Telephone call  1/14/2002 DONE
permit ready
PLANS/APPL TAKEN TO FRONT DESK  1/11/2002 PASS
Routing - PLAN CHECK12/7/2001 1/11/2002 PASS
Reviewed resubmitted drawings. Drawings approved.
Plan assigned to (CJW)11/21/2001 1/11/2002 PASS
DetailsCarl Westfall
1/11/2002 13:37:49 CJW - activity updated through activity BLDA022 from case BLD01-03024.
Plan resubmittals received  1/9/2002 DONE
Received two sets of resubmittal sheets A0.0, A1.0, A2.0, A3.0, to include cover letter. Routed to Carl Westfall.
Routing - FIRE12/5/200112/7/200112/7/2001 PASS
DetailsBill Alexander
Plan Review Completed(1st rev)  12/7/2001 DONE
Routing - PLAN CHECK11/29/2001 12/4/2001 PASS
UBC plan review started December 3, 2001 and finished the next day. The drawings were approved with conditions. See the conditions list.
Routing - PUBLIC WORKS11/27/2001 11/29/2001 PASS
Routing - PLANNING Land Div11/21/2001 11/27/2001 PASS
N/A - tenant improvement w/out expansion. **If they expand, they will have to prove legal land division and may need a density reduction record of survey. Routed to Public Works. (blc)
First Notice11/19/200111/19/200111/19/2001 DONE
Plans ACCEPTED BY PLAN TECH  11/19/2001 DONE
1. General Notes on A2.0 state "All Plumbing is Design build".
2. General Notes on A2.0 state "All HVAC is Design Build".
3. General Notes on A2.0 state "All Electrical is Design build".
Application received  11/19/2001  
Recd Pcfee & Taken To Pln CK  11/19/2001 DONE