BLD-Aging Inspection | 2/12/2004 | 2/12/2004 | 2/12/2004 | | DONE |
Dave Hannah
|
|
|
|
DOC - Permit Expired | 2/12/2004 | 2/12/2004 | 2/12/2004 | A | PASS |
Dave Hannah
|
|
|
Expired by inspector at 2/12/2004 7:36:40 AM
|
BLD-Aging Inspection | 11/19/2003 | 11/19/2003 | 11/19/2003 | | DONE |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 7/25/2003 | 7/25/2003 | 7/25/2003 | | DONE |
Carl Dependahl
|
|
|
called, ph# not in service....previously finalled 7/28/2003 10:21:24 AM
|
BLD-Final | 4/25/2002 | 4/25/2002 | 4/25/2002 | P | PASS |
Carl Dependahl
|
|
|
tim ###-#### fn ok for c/o 4/25/2002 4:35:16 PM
|
FIRE-Final Inspection | 4/25/2002 | 4/25/2002 | 4/25/2002 | P | PASS |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 4/25/2002 12:02:16 PM
|
Permanent Occupancy | | 4/25/2002 | 4/25/2002 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 4/11/2002 | 4/12/2002 | 4/12/2002 | A | PART |
Tom Arcoraci
|
|
|
###-#### TIM grid insp needs spacer bars 4/12/2002 9:10:11 AM
|
BLD-Framing/Rough-in | 3/4/2002 | 3/4/2002 | 3/4/2002 | P | PART |
Carl Dependahl
|
|
|
wall cover insp tim ###-#### walls ok 3/4/2002 3:59:14 PM
|
Issue PAID IN FULL permit | | | 2/6/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/14/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/14/2002 | | DONE |
|
|
|
|
Telephone call | | | 1/14/2002 | | DONE |
|
|
|
permit ready
|
Routing - PLAN CHECK | 12/7/2001 | | 1/11/2002 | | PASS |
|
|
|
Reviewed resubmitted drawings. Drawings approved.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2002 | | PASS |
|
|
|
|
Plan assigned to (CJW) | 11/21/2001 | | 1/11/2002 | | PASS |
Carl Westfall
|
|
|
1/11/2002 13:38:34 CJW - activity updated through activity BLDA022 from case BLD01-03025.
|
Plan resubmittals received | | | 1/9/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets A0.0, A1.0, A2.0, A3.0, to include cover letter. Routed to Carl Westfall.
|
Routing - FIRE | 12/5/2001 | 12/7/2001 | 12/7/2001 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 12/7/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/29/2001 | | 12/5/2001 | | |
|
|
|
Failed first UBC review. UBC plan review started December 4, 2001 and finished the next day. A plan revision from the architect was required. See the conditions list.
|
Routing - PUBLIC WORKS | 11/27/2001 | | 11/29/2001 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 11/21/2001 | | 11/27/2001 | | PASS |
|
|
|
N/A - tenant improvement w/out expansion. **If they expand, they will have to prove legal land division and may need a density reduction record of survey. Routed to Public Works. (blc)
|
Application received | | | 11/19/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/19/2001 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/19/2001 | | DONE |
|
|
|
1. General Notes on A2.0 state "All Plumbing is Design build".
2. General Notes on A2.0 state "All HVAC is Design Build".
3. General Notes on A2.0 state "All Electrical is Design build".
|
Fee Review-notes | 11/19/2001 | 11/19/2001 | | | |
|
|
|
|