Fee Review-notes | 7/14/2003 | 7/14/2003 | 7/14/2003 | | DONE |
|
|
|
|
Permanent Occupancy | | 2/20/2002 | 2/20/2002 | | DONE |
|
|
|
|
BLD-Final | 2/19/2002 | 2/20/2002 | 2/20/2002 | P | PASS |
Tom Arcoraci
|
|
|
fn occ--###-####- jerald ok for perm occ 2/20/2002 1:25:25 PM
|
Permanent occupancy | | | 2/20/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9033 issued 2-20-02 to The Dish in the Harbormaster Bldg.
|
FIRE-Final Inspection | 2/8/2002 | 2/11/2002 | 2/11/2002 | A | PASS |
Troy Cobbley
|
|
|
Hood tested OK. FIre alarm finaled 2/11/2002 1:31:05 PM
|
Issue PAID IN FULL permit | | | 1/28/2002 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 11/30/2001 | | 1/10/2002 | | PASS |
|
|
|
1/10/2002 10:43:34 RMH - activity updated through activity BLDA022 from case BLD01-03088.
|
Routing - PLAN CHECK | 1/2/2002 | | 1/10/2002 | | PASS |
Ron Hill
|
|
|
|
Print Occupancy Form | | | 1/10/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/10/2002 | | DONE |
|
|
|
|
Telephone call | | | 1/10/2002 | | DONE |
|
|
|
permit ready
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/10/2002 | | PASS |
Ron Hill
|
|
|
|
Plan resubmittals received | | | 1/10/2002 | | DONE |
|
|
|
Received one additional resubmittal "HOOD" sheet as requested by Ron Hill. Routed to Ron Hill
|
Plan Review Report | | | 1/9/2002 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/9/2002 | | DONE |
|
|
|
|
Plan resubmittals received | | | 1/8/2002 | | DONE |
|
|
|
Received two copies of resubmittal sheet HOOD with cover letter. Routed to Ron Hill.
|
Routing - FIRE | 12/13/2001 | 3/17/2001 | 12/17/2001 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 12/17/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/4/2001 | | 12/13/2001 | | FAIL |
Ron Hill
|
|
|
Failed in plan check, faxed requirements to the engineer, routed plans to fire department, 12-13-01
|
Plan Review Report | | | 12/13/2001 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 12/13/2001 | | FAIL |
Ron Hill
|
|
|
Faxed requirements to Richard Kartchner, 12-13-01, Routed plans to fire department for review.
|
Routing - PUBLIC WORKS | 11/30/2001 | | 12/3/2001 | | PASS |
|
|
|
|
Routing - PLUMBING | 12/3/2001 | | 12/3/2001 | | PASS |
|
|
|
if changes ars made to the existing plumbing, plans may need to be submitted.
|
First Notice | 11/28/2001 | 11/28/2001 | 11/28/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/28/2001 | | DONE |
|
|
|
1. Drawings are NTS except Detail C.
2. Building Code Data not listed.
3. Site Plan and Key Plan not shown.
11/27/01-Plans signed by Bob Jue, CDH.
|
Application received | | | 11/28/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/28/2001 | | DONE |
|
|
|
|
Routing - PLANNING | 12/21/2001 | | 1/2/2001 | | PASS |
|
|
|
Approved per building permit plans.
|