Description
(ZOO BOISE - KITCHEN / BREAKROOM REMODEL) This building is NOT fire sprinklered. To remodel an 880 square foot area within an existing 1,434 square foot building. The employee breakroom and animal meal preparation kitchen are being modified. Work is to include interior nonbearing walls, a toilet/shower room accessible to the disabled, an exterior wall infill at an existing opening, millwork, and finishes. Selective non-structural demolition is covered under this permit. PC01-0925 **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection1/16/20041/16/20041/16/2004 DONE
DetailsDave Hannah
DOC - Permit Expired1/16/20041/16/20041/16/2004PPASS
DetailsDave Hannah
Expired by inspector at 1/16/2004 7:24:25 AM
Fee Review-notes12/13/200112/13/20013/21/2003 DONE
Letter of compliance  12/17/2002 DONE
Letter of Compliance #22786 issued 12-17-02.
BLD-Final12/12/200212/13/200212/13/2002PPASS
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 12/12/2002 at 08:41:31. Contact: ###-####. ok 12/13/2002 3:48:34 PM
FIRE-Final Inspection12/11/200212/11/200212/11/2002PPASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 12/11/2002 at 08:51:39. Contact: ###-####. as of today the ELE and PLM inspections weren't final 12/11/2002 4:09:22 PM
BLD-Other11/25/200211/26/200211/26/2002ANR
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 11/25/2002 at 09:51:29. Contact: ###-####...needs fire for final...call to office. 11/26/2002 9:38:24 AM
Inspection Record Card- Bld  10/28/2002 DONE
Print Occupancy Form  10/28/2002 DONE
FIRE-Final Inspection5/21/20025/22/20025/22/2002AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 05/21/2002 at 08:50:25. Contact: ###-####. no approved plans on site 5/22/2002 9:48:40 AM
BLD-Final5/21/20025/22/20025/22/2002PNR
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 05/21/2002 at 08:51:11. Contact: ###-####. needs fire final 5/22/2002 1:48:47 PM
BLD-Framing/Rough-in2/28/20022/28/20022/28/2002PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 02/28/2002 at 08:19:16. Contact: ###-####. walls ok to cover
2/28/2002 4:57:51 PM
BLD-Framing/Rough-in2/26/20022/27/20022/27/2002ANR
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 02/26/2002 at 12:31:42. Contact: ###-####... 2/27/2002 4:28:16 PM unable to contact, left msg. 2/27/2002 4:39:30 PM
BLD-Framing/Rough-in2/27/20022/27/20022/27/2002PNR
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 2/27/2002 11:55:36 AM recall insp. 2/27/2002 4:39:55 PM
Issue PAID IN FULL permit  2/6/2002 DONE
Plan assigned to (CJW)12/20/2001 1/30/2002 PASS
DetailsCarl Westfall
1/30/2002 08:20:59 CJW - activity updated through activity BLDA022 from case BLD01-03198.
Routing - PLAN CHECK1/7/2002 1/30/2002 PASS
Drawings approved, with conditions, after resubmittal review.
PLANS/APPL TAKEN TO FRONT DESK  1/30/2002 PASS
Inspection Record Card- Bld  1/30/2002 DONE
Print Occupancy Form  1/30/2002 DONE
Telephone call  1/30/2002 DONE
permit ready
Plan resubmittals received  1/29/2002 DONE
Received two sets of resubmittal sheets A0.01, A2.01, P0.0, P0.1, P1.0, P1.1, M0.0, M0.1, M1.0 with ADA Fixture Cutsheets. Routed to Carl Westfall.
Routing - FIRE1/4/2002 1/7/2002 PASS
APPROVED AS DRAWN
Plan Review Completed(1st rev)  1/7/2002  
Failed first UBC review.
Routing - PLAN CHECK12/26/2001 1/4/2002  
Failed first UBC review. UBC plan review started January 3, 2002 and finished the next day. The architect was required to resubmit drawings. See the conditions list. A report was sent to the architect.
Routing - PLUMBING12/21/2001 12/26/2001 PASS
pipe water heater t&p drain to exterior, vent new floor drains, provide a floor sink, exposed in the tor kick, for food prep sink.
Routing - PUBLIC WORKS12/20/2001 12/21/2001 PASS
Plans ACCEPTED BY PLAN TECH  12/14/2001 DONE
Application received  12/13/2001  
Recd Pcfee & Taken To Pln CK  12/13/2001 DONE