BLD-Final | 5/24/2002 | 5/28/2002 | 5/28/2002 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 05/24/2002 at 13:28:52. Contact: ###-####.
|
DOC - Permit Finaled | 5/28/2002 | 5/28/2002 | 5/28/2002 | A | PASS |
Russ Owen
|
|
|
Finaled by inspector at 5/28/2002 11:17:00 AM
|
DOC - Permit Finaled | 5/28/2002 | 5/28/2002 | 5/28/2002 | A | PASS |
Russ Owen
|
|
|
Finaled by inspector at 5/28/2002 11:18:24 AM
|
BLD-Energy code compliance | 3/7/2002 | 3/8/2002 | 3/8/2002 | A | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 03/07/2002 at 15:18:30. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/5/2002 | 3/6/2002 | 3/6/2002 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 03/05/2002 at 11:43:17. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/6/2002 | 3/6/2002 | 3/6/2002 | P | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 03/06/2002 at 10:08:38. Contact: ###-####. cn posted 3/6/2002 1:48:50 PM
|
BLD-Framing/Rough-in | 2/26/2002 | 2/27/2002 | 2/27/2002 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 02/26/2002 at 18:20:52. Contact: ###-####. ok to side 2/27/2002 11:18:45 AM
|
BLD-Framing/Rough-in | 2/25/2002 | 2/26/2002 | 2/26/2002 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/25/2002 at 15:35:38. Contact: ###-####. shear panels, recall when right. 2/26/2002 4:31:18 PM
|
BLD-Foundation | 1/22/2002 | 1/22/2002 | 1/22/2002 | P | PART |
Steven Webb
|
|
|
###-#### wip--60% ready--corner of garage footing to be pinned where cracked during stripping of footing boards. 1/22/2002 1:13:18 PM
|
BLD-Footing | 1/17/2002 | 1/18/2002 | 1/18/2002 | A | PART |
Steven Webb
|
|
|
###-#### wip- 1/18/2002 9:02:17 AM
|
BLD-Footing | 1/16/2002 | 1/17/2002 | 1/17/2002 | A | NR |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 01/16/2002 at 18:42:18. Contact: ###-####. No form board up--no one on site. 1/17/2002 9:17:24 AM
|
BLD-Footing | 1/16/2002 | 1/16/2002 | 1/16/2002 | P | CANC |
Jim Storey
|
|
|
MARK ###-#### exavation still in progess. 1/16/2002 3:45:37 PM
|
Inspection Record Card- Bld | | | 1/16/2002 | | DONE |
|
|
|
|
Telephone call | | | 1/16/2002 | | DONE |
|
|
|
left mess that permit is ready
|
Issue PAID IN FULL permit | | | 1/16/2002 | | DONE |
|
|
|
|
Plan assigned to (PEP) | 1/8/2002 | | 1/15/2002 | | PASS |
Perry Paine
|
|
|
1/15/2002 15:15:21 PEP - activity updated through activity BLDA022 from case BLD01-03280.
|
Inspector's copy Bld permit | | | 1/15/2002 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/15/2002 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 1/8/2002 | | DONE |
|
|
|
called builder mark at ###-#### told him that the pool house was required to meet section '97 UBC 2320.4.1 for lateral desighn
|
Pending Assignment by DJO | 12/31/2001 | | 1/8/2002 | | DONE |
Dan Overy
|
|
|
1/8/2002 07:58:56 PEP - activity updated through activity BLDA176 from case BLD01-03280.
|
Routing - PUBLIC WORKS | 12/31/2001 | | 1/2/2002 | | PASS |
|
|
|
|
Routing - PLANNING | 12/31/2001 | | 12/31/2001 | | PASS |
|
|
|
|
Application received | | | 12/31/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 1/2/2002 | | | | |
|
|
|
|