Fee Review-notes | 7/15/2003 | 7/15/2003 | 7/15/2003 | | DONE |
|
|
|
Additional values from subcontractors.
|
Fee Review-notes | 1/3/2002 | 1/3/2002 | 4/9/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 4/4/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9095 issued 4-4-02 to At. Al's Reg. Medical Center.
|
Permanent Occupancy | | 4/3/2002 | 4/3/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/3/2002 | 4/3/2002 | 4/3/2002 | P | PASS |
Troy Cobbley
|
|
|
Fire life/safety finaled. Contractor removed manual flushbolts and key hardware on double doors as I waited. Fire extinguishers, exit lights and emergency lights OK 4/3/2002 11:53:56 AM
|
BLD-Final | 4/3/2002 | 4/3/2002 | 4/3/2002 | P | PASS |
Tom Arcoraci
|
|
|
###-#### mike ok for perm occ 4/3/2002 3:03:10 PM
|
BLD-Framing/Rough-in | 3/15/2002 | 3/18/2002 | 3/18/2002 | A | PASS |
Tom Arcoraci
|
|
|
wall insp -mike- ###-#### ok to cover drop in basement 3/18/2002 9:31:21 AM
|
BLD-Footing | 3/15/2002 | 3/18/2002 | 3/18/2002 | A | NR |
Tom Arcoraci
|
|
|
mike --###-#### ft needs permit 3/18/2002 9:31:40 AM
|
BLD-Framing/Rough-in | 2/28/2002 | 3/1/2002 | 3/1/2002 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 407 On 2/28/2002 6:20:47 PM ok to side 3/1/2002 8:52:53 AM grid ok 3/1/2002 9:40:54 AM
|
BLD-Framing/Rough-in | 2/28/2002 | 2/28/2002 | 2/28/2002 | P | CANC |
Russ Owen
|
|
|
###-####
|
BLD-Framing/Rough-in | 2/12/2002 | 2/13/2002 | 2/13/2002 | P | PASS |
Tom Arcoraci
|
|
|
###-#### MIKE
|
Inspection Record Card- Bld | | | 2/12/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/12/2002 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/12/2002 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 1/7/2002 | | 2/11/2002 | | PASS |
Dan Stuart
|
|
|
2/11/2002 12:55:32 DRS - activity updated through activity BLDA022 from case BLD02-00017.
|
Routing - FIRE | 2/6/2002 | | 2/11/2002 | | PASS |
|
|
|
approved without written comment
|
Plan Review Completed(1st rev) | | | 2/11/2002 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 2/11/2002 | | 2/11/2002 | | PASS |
|
|
|
Approved as noted and attached plan review comments & clarification on accessibility from architect dated 2/5/02.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/11/2002 | | PASS |
|
|
|
To permit desk to issue.
|
Routing - PLAN CHECK | 1/8/2002 | | 2/5/2002 | | PEND |
|
|
|
Approved as noted on plans & attached plan review comments. Routing to fire code analyst for review.
|
Routing - PUBLIC WORKS | 1/7/2002 | | 1/8/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/3/2002 | | DONE |
|
|
|
1. Mechanical, Plumbing, and Electrical to be "design-built" per General Notes on Sheet A-2.
|
Application received | | | 1/3/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/3/2002 | | |
|
|
|
|