Permit Information
Permit NumberBLD02-00046
StatusFinaled
Name TAHOE CONSTRUCTION
Site Address 3417 S SHORTLEAF AVE
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a three bedroom, two and half bathroom 1906 sq. ft. two story single family dwelling (1390 sq. ft. first floor/516 sq. ft. second floor) with a attached 555 sq. ft. two car garage and a 43 sq. ft. covered back porch. Per approved plans, engineering and requirement list. This is a solar and shade restricted lot. CUP98-0116 per Roger Jones with Planning and Zoning. PC#006 (SAM)
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/24/20024/25/20024/25/2002AFAIL
DetailsSteven Webb
Scheduled by a contractor via Hello! on 04/24/2002 at 15:00:16. Contact: ###-####. c /n--Need protection post in front of furnace and seal attic access in garage. 4/25/2002 9:18:22 AM
BLD-Final4/25/20024/25/20024/25/2002PPASS
DetailsSteven Webb
Scheduled by a contractor via Hello! on 04/25/2002 at 10:16:49. Contact: ###-####. c. of c. #22385 issued 4/25/2002 2:44:41 PM
DOC - Permit Finaled4/25/20024/25/20024/25/2002PPASS
DetailsSteven Webb
Finaled by inspector at 4/25/2002 2:44:47 PM
BLD-Energy code compliance3/4/20023/5/20023/5/2002APASS
DetailsSteven Webb
Scheduled by a contractor via Hello! on 03/04/2002 at 15:35:59. Contact: ###-####.
BLD-Framing/Rough-in2/28/20023/1/20023/1/2002PPASS
DetailsSteven Webb
Scheduled by a contractor via Hello! on 02/28/2002 at 15:01:30. Contact: ###-####. ok to insulate 3/1/2002 1:59:33 PM
BLD-Other2/19/20022/20/20022/20/2002APASS
DetailsRuss Owen
Scheduled by a contractor via Hello! on 02/19/2002 at 15:01:56. Contact: ###-####.
BLD-Other2/19/20022/19/20022/19/2002PFAIL
DetailsDave Hannah
Scheduled by a contractor via Hello! on 02/19/2002 at 09:46:22. Contact: ###-####. stapels are to deep 2/19/2002 3:41:17 PM
BLD-Other2/14/20022/15/20022/15/2002PFAIL
DetailsSteven Webb
Scheduled by a contractor via Hello! on 02/14/2002 at 11:54:00. Contact: ###-####. SHEAR-blocking on shear panels not completed, holdowns in garage not installed, nailing light in misc. locations. Completed per plans and call for re-inspection. 2/15/2002 2:38:03 PM
BLD-Foundation1/24/20021/25/20021/25/2002APART
DetailsSteven Webb
###-#### wip 10% ready 1/25/2002 9:59:33 AM
BLD-Footing1/24/20021/24/20021/24/2002PPART
DetailsSteven Webb
###-#### JED wip--95% ready 1/24/2002 3:34:15 PM
Issue PAID IN FULL permit  1/22/2002 DONE
Routing - PLAN CHECK1/10/2002 1/18/2002 DONE
Plan assigned to (SAM)1/17/2002 1/18/2002 PASS
DetailsSteve Munroe
1/18/2002 09:00:03 SAM - activity updated through activity BLDA022 from case BLD02-00046.
Case Summary (BLD)  1/18/2002  
Plan Review Report  1/18/2002  
PLANS/APPL TAKEN TO FRONT DESK  1/18/2002 DONE
Inspection Record Card- Bld  1/18/2002 DONE
Telephone call  1/18/2002 DONE
left mess that permit is ready
Pending Assignment by DJO1/9/2002 1/17/2002 DONE
DetailsDan Overy
1/17/2002 13:42:16 SAM - activity updated through activity BLDA183 from case BLD02-00046.
Routing - PUBLIC WORKS1/10/2002 1/10/2002 PASS
Application received  1/9/2002  
Routing - PLANNING1/9/2002   PASS
FRONT SETBACK FROM SIDEWALK