Fee Review-notes | 1/9/2002 | 1/9/2002 | 4/25/2002 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 3/11/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9061 issued 3-11-02 to Baskin Robbins in the Fred Meyer bldg.
|
Permanent Occupancy | | 3/8/2002 | 3/8/2002 | | DONE |
|
|
|
|
BLD-Final | 3/7/2002 | 3/8/2002 | 3/8/2002 | P | PASS |
Tom Arcoraci
|
|
|
fn occ- per tom late pm???- ###-####- daniel ok for perm 3/8/2002 3:57:11 PM
|
FIRE-Final Inspection | 3/8/2002 | 3/8/2002 | 3/8/2002 | P | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 3/8/2002 3:02:35 PM fire life/safety finaled
|
BLD-Final | 2/26/2002 | 2/26/2002 | 2/26/2002 | P | PART |
Russ Owen
|
|
|
###-#### daniel, Ok if all other signatures are on card. None at this time. 2/26/2002 12:47:13 PM
|
FIRE-Final Inspection | 2/26/2002 | 2/26/2002 | 2/26/2002 | P | FAIL |
Troy Cobbley
|
|
|
provide inspection tag on fire extinguisher and provide approved fire sprinkler drawings 2/26/2002 5:05:22 PM
|
BLD-Framing/Rough-in | 2/12/2002 | 2/13/2002 | 2/13/2002 | P | PASS |
Tom Arcoraci
|
|
|
###-#### DANIEL
|
Issue PAID IN FULL permit | | | 2/7/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/6/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/6/2002 | | DONE |
|
|
|
|
Telephone call | | | 2/6/2002 | | DONE |
|
|
|
LEFT MESSAGE PLANS READY
|
Routing - PLAN CHECK | 1/29/2002 | | 2/5/2002 | | PASS |
Ron Hill
|
|
|
|
Plan assigned to (R_H) | 1/10/2002 | | 2/5/2002 | | PASS |
|
|
|
2/5/2002 14:36:56 RMH - activity updated through activity BLDA022 from case BLD02-00053.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/5/2002 | | PASS |
Ron Hill
|
|
|
|
Routing - FIRE | 2/1/2002 | 2/1/2002 | 2/1/2002 | | PASS |
Bill Alexander
|
|
|
|
Routing - FIRE | 1/28/2002 | 1/29/2002 | 1/29/2002 | | FAIL |
Bill Alexander
|
|
|
Lack sufficient plan to know where work is being performed in facility.
|
Plan Review Completed(1st rev) | | | 1/29/2002 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 1/28/2002 | | FAIL |
Ron Hill
|
|
|
Plans failed in building review. Faxed requirements to the architect. Routed plans to the fire department for review on 1-28-02.
|
Routing - PLAN CHECK | 1/15/2002 | | 1/28/2002 | | FAIL |
Ron Hill
|
|
|
|
Routing - PLUMBING | 1/14/2002 | | 1/15/2002 | | PASS |
|
|
|
max trap arm for 3" floor sink is 6'. verify height of the ice mechine for indirect waste to mop sink or provide a floor sink, pipe water heater T&P drain to mop sink, additional cross connection protection may be required, provide a shut off valve with in the space on the water supply.
|
Routing - PLANNING | 1/11/2002 | | 1/14/2002 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 1/10/2002 | | 1/11/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/9/2002 | | DONE |
|
|
|
CDH approval by Deborah Carney.
|
Application received | | | 1/9/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/9/2002 | | |
|
|
|
|