Fee Review-notes | 7/15/2003 | 7/15/2003 | 7/15/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 7/19/2002 | | DONE |
|
|
|
Per. Occ. Cert. #9264 issued 7-19-02 to Stronghold Construction.
|
Permanent Occupancy | | 7/17/2002 | 7/17/2002 | | DONE |
|
|
|
|
BLD-Final | 7/16/2002 | 7/17/2002 | 7/17/2002 | P | PASS |
Jim Storey
|
|
|
jerry; Phone #: ###-#### jerry; Phone #: final ok pending others sign off for perm.###-#### 7/17/2002 3:48:05 PM
|
BLD-Final | 7/9/2002 | 7/10/2002 | 7/10/2002 | A | NR |
Jim Storey
|
|
|
###-####
|
FIRE-Final Inspection | 7/8/2002 | 7/8/2002 | 7/8/2002 | P | PASS |
Rick Jackson
|
|
|
JERRY ###-#### handrail and guardrail not installed and will have installed for structural 7/8/2002 3:23:19 PM
|
BLD-Final | 6/27/2002 | 7/2/2002 | 7/2/2002 | P | NR |
Jim Storey
|
|
|
jerry ###-#### fn
|
FIRE-Final Inspection | 6/27/2002 | 7/1/2002 | 7/1/2002 | A | FAIL |
Rick Jackson
|
|
|
fire fn - jerry- ###-#### need key lock on main exit; need to test duct detectors 7/1/2002 10:49:26 AM
|
Routing - PLANNING Land Div | 6/11/2002 | 6/11/2002 | 6/11/2002 | | PASS |
|
|
|
Recorded declaration of cross-easements received. Recording #102063621, recorded 6/4/02.
|
BLD-Framing/Rough-in | 4/17/2002 | 4/18/2002 | 4/18/2002 | P | PASS |
Jim Storey
|
|
|
###-#### JERRY framing ok recived soil bearing report ok/ welders cert and special insp report ok. in archive. 4/18/2002 3:28:47 PM
|
Override - Parcel Holds | | | 4/17/2002 | | DONE |
Annett Moore
|
|
|
Parcel Tag Notes: OK to issue building permit, but DO NOT issue Certificate of Occupancy until amended cross-access & cross-parking agreement is received. Contact Brandi x3751. (blc) Reason for OverRide:
|
BLD-Footing | 3/18/2002 | 3/19/2002 | 3/19/2002 | P | PASS |
Jim Storey
|
|
|
ft jerry- ###-#### need soil bearing test to be archived. 3/19/2002 3:31:22 PM
|
Override - Parcel Holds | | | 3/18/2002 | | |
|
|
|
|
FIRE-Conference | 3/14/2002 | 3/14/2002 | 3/14/2002 | P | PART |
Rick Jackson
|
|
|
Added by Inspector: 409 On 3/14/2002 1:02:05 PM meet with GC and went over exit signage; AHU detectors required; exiting hardware
|
Override - Parcel Holds | | | 3/7/2002 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/7/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/7/2002 | | DONE |
|
|
|
|
Telephone call | | | 3/7/2002 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 3/7/2002 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/7/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/5/2002 | | 3/6/2002 | | |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2002 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 3/6/2002 | | |
|
|
|
|
Plan assigned to (JCB) | 1/10/2002 | | 3/6/2002 | | PASS |
Jason Blais
|
|
|
3/6/2002 16:42:06 JCB - activity updated through activity BLDA022 from case BLD02-00054.
|
Routing - PLAN CHECK | 2/25/2002 | | 3/5/2002 | | FAIL |
|
|
|
Reviewed resubmittals. Some engineering calculations are still required. Waiting for these.
|
Plan resubmittals received | | | 3/1/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets A-3, A-5, A-8, and structural calculations and copy of letter from Brandi Christon. Routed to Jason Blais.
|
Routing - PLANNING Land Div | 2/26/2002 | | 2/26/2002 | | PASS |
|
|
|
Still need amended agreement but we will release the building permit, and will hold up the Certificate of Occupancy until agreement is received. Parcel tag placed in Permit Plan. Will fax memo to Jack Robertson. (blc)
|
Routing - FIRE | 2/20/2002 | | 2/25/2002 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 2/20/2002 | | |
|
|
|
Engineering resubmittals required for further review.
|
Routing - PLAN CHECK | 2/7/2002 | | 2/20/2002 | | FAIL |
|
|
|
Second plan review report sent to architect. Not all issues from initial plan review addressed adequately. New engineering calculations packet required for all structural work. Plans routed to Fire Dept. again for review.
|
Plan resubmittals received | | | 2/19/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets A-1, A-2, A-3, A-4, A-5, A-6, A-7, A-8, A-9, A-10, A-11, A-12, A-13, A-14, A-15, M-1, E-1, E-2, E-3, structural calculations, MSDS, and letters from United Water. Routed to Jason Blais.
|
Plan Review Completed(1st rev) | | | 2/7/2002 | | FAIL |
|
|
|
|
Routing - FIRE | 2/6/2002 | | 2/7/2002 | | FAIL |
|
|
|
|
Meeting | | | 2/6/2002 | | |
|
|
|
Met with architect, Rocky Towle, and Tenant representative, Jack Robertson to go over issues in plan review report. Resubmittal drawings will be coming.
|
Plan resubmittals requested | | | 2/6/2002 | | |
|
|
|
Plan resubmittals and written response required.
|
Routing - PLAN CHECK | 1/18/2002 | | 2/5/2002 | | FAIL |
|
|
|
Plan review report faxed to architect and tenant. Plan resubmittals and written response required. Will meet with architect and tenant on 2/6/2002 to go over issues. Plans routed to Fire Dept.
|
Plan resubmittals received | | | 1/31/2002 | | |
|
|
|
Plan resubmittals were provided because of structural changes to the new second floor in the building.
|
Routing - PLANNING | 1/17/2002 | | 1/18/2002 | | PASS |
|
|
|
Approved per CZC02-00008.
|
Routing - PUBLIC WORKS | 1/16/2002 | | 1/17/2002 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 1/10/2002 | | 1/16/2002 | | FAIL |
|
|
|
This needs to be approved as a one-time split, but there needs to be a cross-access and cross-parking agreement before P&Z will sign off. Sarah Schafer has CZC02-00008 which relates to this issue and she will contact them to let them know what she needs. Routed to Public Works. (blc)
|
First Notice | 1/9/2002 | 1/9/2002 | 1/9/2002 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/9/2002 | | DONE |
|
|
|
|
Application received | | | 1/9/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/9/2002 | | DONE |
|
|
|
|