Fee Review-notes | 7/15/2003 | 7/15/2003 | 7/15/2003 | | DONE |
|
|
|
|
Permanent Occupancy | | 4/11/2002 | 4/11/2002 | | DONE |
|
|
|
|
BLD-Final | 4/10/2002 | 4/11/2002 | 4/11/2002 | P | PASS |
Jim Sly
|
|
|
###-#### OK for perm occ. 4/11/2002 1:40:36 PM
|
FIRE-Final Inspection | 4/10/2002 | 4/11/2002 | 4/11/2002 | A | PASS |
Rick Jackson
|
|
|
###-#### dryer vent penetrates floor ceiling assembly; not per the plans - mech has final pass; AHU for this space has detector for shutdown and worked properly 4/11/2002 10:26:58 AM
|
Permanent occupancy | | | 4/11/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9101 issued 4-11-02 to RehabAuthority.
|
FIRE-Final Inspection | 4/9/2002 | 4/10/2002 | 4/10/2002 | A | NR |
Troy Cobbley
|
|
|
Contractor was not available to provide access to dampers. No inspection done 4/10/2002 1:53:32 PM
|
BLD-Final | 4/9/2002 | 4/10/2002 | 4/10/2002 | P | CANC |
Jim Sly
|
|
|
###-####- richard evans fn occ-pending fire fn Canc by owner. 4/10/2002 3:55:12 PM
|
BLD-Final | 4/5/2002 | 4/8/2002 | 4/8/2002 | A | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/05/2002 at 14:36:19. Contact: ###-####. Called this number no answer back its now 2:30 called about 11:00 am. This has no fire/life safety yet also note only 1 frame inspection on history. 4/8/2002 3:30:41 PM 4/8/2002 3:30:44 PM 4/8/2002 3:31:05 PM
|
BLD-Framing/Rough-in | 2/25/2002 | 2/26/2002 | 2/26/2002 | P | PART |
Russ Owen
|
|
|
###-#### Ok the office at the existing side (west)is not yet built, (East). ok to start sheetrock. 2/26/2002 3:57:25 PM
|
Issue PAID IN FULL permit | | | 2/12/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/7/2002 | | 2/8/2002 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
Plan assigned to (JCB) | 1/16/2002 | | 2/8/2002 | | PASS |
Jason Blais
|
|
|
2/8/2002 11:20:10 JCB - activity updated through activity BLDA022 from case BLD02-00063.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/8/2002 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 2/8/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/8/2002 | | DONE |
|
|
|
|
Telephone call | | | 2/8/2002 | | DONE |
|
|
|
left mess that permit is ready
|
Routing - PLAN CHECK | 1/28/2002 | | 2/7/2002 | | FAIL |
|
|
|
Two items need to be redesigned and plans resubmitted with changes. Accessible restrooom issue - floor space at water closet and door swing into hallway more than half required width. Called architect and went over issues. New resubmittals will be coming for two sheets.
|
Plan resubmittals requested | | | 2/7/2002 | | |
|
|
|
Resubmittal drawings required again for further review.
|
Plan resubmittals received | | | 2/7/2002 | | |
|
|
|
Plan resubmittals received. Sheets A-1 and A-2.
|
Plan resubmittals received | | | 2/6/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets A-1, A-2, A-3, A-4, with cover letter. Routed to Jason Blais.
|
Routing - FIRE | 1/25/2002 | 1/28/2002 | 1/28/2002 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 1/28/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/18/2002 | | 1/25/2002 | | FAIL |
|
|
|
Plan review letter sent and faxed to architect. Response and resubmittal drawings required for further review. Plans routed to Fire Dept. for review.
|
Plan resubmittals requested | | | 1/25/2002 | | |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - PUBLIC WORKS | 1/16/2002 | | 1/18/2002 | | PASS |
|
|
|
|
First Notice | 1/11/2002 | 1/11/2002 | 1/11/2002 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/11/2002 | | DONE |
|
|
|
No plumbing plans required per Lee Rice.
|
Application received | | | 1/11/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/11/2002 | | |
|
|
|
|