Permanent occupancy UNPAID FEE | | | 5/17/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9143 issued 5-17-02 to the Headmasters School of Hair Design.
|
Permanent Occupancy | | 5/16/2002 | 5/16/2002 | | DONE |
|
|
|
|
BLD-Final | 5/15/2002 | 5/16/2002 | 5/16/2002 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 5/15/2002 3:59:35 PM ok for perm occ 5/16/2002 9:12:46 AM
|
FIRE-Final Inspection | 5/14/2002 | 5/15/2002 | 5/15/2002 | A | PASS |
Rick Jackson
|
|
|
Bret, ###-#### final okay 5/15/2002 9:03:58 AM
|
BLD-Final | 5/14/2002 | 5/15/2002 | 5/15/2002 | P | PASS |
Tom Arcoraci
|
|
|
Bret, ###-#### ok for perm occ 5/16/2002 9:12:37 AM
|
FIRE-Final Inspection | 4/30/2002 | 5/1/2002 | 5/1/2002 | A | FAIL |
Troy Cobbley
|
|
|
duct detector that was installed was mounted outside. It is not listed for exterior use 5/1/2002 9:48:18 AM
|
FIRE-Final Inspection | 4/26/2002 | 4/29/2002 | 4/29/2002 | A | FAIL |
Troy Cobbley
|
|
|
need to test duct detector 4/29/2002 1:44:23 PM
|
BLD-Final | 4/26/2002 | 4/29/2002 | 4/29/2002 | A | NH |
Tom Arcoraci
|
|
|
###-#### fire fail 4/29/2002 2:03:35 PM
|
BLD-Final | 4/29/2002 | 4/29/2002 | 4/29/2002 | P | NR |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 4/29/2002 8:33:28 AM fire fail 4/29/2002 2:03:44 PM
|
BLD-Final | 4/26/2002 | 4/26/2002 | 4/26/2002 | P | NR |
Tom Arcoraci
|
|
|
###-#### x104 - Chris needs other sigs for perm occ 4/26/2002 12:48:15 PM
4/26/2002 12:51:41 PM
|
FIRE-Final Inspection | 4/2/2002 | 4/3/2002 | 4/3/2002 | A | PART |
Troy Cobbley
|
|
|
temp signature was given per letter/agreement between property manager and Dave Miller. Items 2,3 and 4 on correction notice are corrected. Other items to be corrected by May 1,2002. 4/2/2002 1:58:15 PM
|
BLD-Final | 4/2/2002 | 4/2/2002 | 4/2/2002 | P | PASS |
Tom Arcoraci
|
|
|
1-###-#### ok for temp occ bath ok per carl w. will upgrade within 5 years 4/2/2002 2:28:11 PM
|
Temporary occupancy | | | 4/2/2002 | | DONE |
|
|
|
Temp. Occ. Cert. #4773 on 4-2-02 to the Headmasters School of Hair Design.
|
BLD-Final | 3/19/2002 | 3/20/2002 | 3/20/2002 | A | NR |
Tom Arcoraci
|
|
|
1-###-#### needs fire final ect..... 3/20/2002 12:15:53 PM
|
FIRE-Final Inspection | 3/19/2002 | 3/19/2002 | 3/19/2002 | P | FAIL |
Troy Cobbley
|
|
|
remove manual flush bolts from main exit/entrance, provide approved door hardware on all doors (lever type), remove thumbturn and dead bolt on rear door, provide 4" address letters, provide duct detector and led for hvac unit 3/20/2002 10:15:49 AM
|
BLD-Framing/Rough-in | 3/7/2002 | 3/8/2002 | 3/8/2002 | A | PART |
Tom Arcoraci
|
|
|
###-#### need new plan for bathroom plumb and elec permits ok to cover wall at bath pending elec and plumb 3/8/2002 9:31:30 AM
|
Issue PAID IN FULL permit | | | 3/7/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/15/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/15/2002 | | DONE |
|
|
|
|
Telephone call | | | 2/15/2002 | | DONE |
|
|
|
LEFT MESSAGE ON CHRIS STROH VOICE MAIL PLANS READY
|
Routing - PLAN CHECK | 2/13/2002 | | 2/14/2002 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/14/2002 | | PASS |
|
|
|
|
Plan assigned to (CJW) | 1/18/2002 | | 2/14/2002 | | PASS |
Carl Westfall
|
|
|
2/14/2002 13:58:27 CJW - activity updated through activity BLDA022 from case BLD02-00101.
|
Routing - FIRE | 2/7/2002 | | 2/13/2002 | | PASS |
|
|
|
approved without written comment
|
Plan Review Completed(1st rev) | | | 2/13/2002 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 1/18/2002 | | 2/7/2002 | | PASS |
|
|
|
UBC plan review started February 6, 2002 and finished the next day. The drawings were approved with conditions. See the conditions report. A plan review report was sent to the architect.
|
Routing - PUBLIC WORKS | 1/18/2002 | | 1/18/2002 | | PASS |
|
|
|
|
First Notice | 1/17/2002 | 1/17/2002 | 1/17/2002 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/17/2002 | | DONE |
|
|
|
1. Applicant was informed that stamped/signed plumbing plans might be required by the plumbing department, eventhough no lines are being moved.
2. No building code data on front sheet of plans.
|
Application received | | | 1/17/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/17/2002 | | |
|
|
|
|