Permit Information
Permit NumberBLD02-00169
StatusFinaled
Name BOISE PROPERTIES LTD
Site Address 3019 N COLE RD
Project NameEVERGREEN PLAZA
Customer Number 
ePlanReviewNo
Description
(HOLLOW LEG RESTAURANT)(EVERGREEN PLAZA) To remodel the interior of an existing 7,823 sq.ft. tenant space for continued use as a restaurant per approved plans on file. Work includes construction of a 1-hour occupancy separation wall to separate the dining/drinking area of less than 5,000 sq. ft. from remaining accessory areas, such that the area does not equire a fire sprinkler system. To upgrade Type I kitchen hood & exhaust supression system; verify 1-hour shaft surrounding exhaust duct; installation of panic & lever hardware as required; provide exit signs & emergency lighting; upgrade electrical, plumbing, mechanical & interior finishes to meet tenants needs and comply with minimum codes and ordinances. To frame walls, portion of roof/ceiling; to cover with 1-hour fire-resistive construction and plumb a 480 sq. ft. area for a future tenant use with new entry to rated corridor & double doors to exterior. To post occupant load signs in each area as designated on plans. PC#02-074/drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Code Occupancy Approval10/1/20039/30/20039/30/2003APASS
DetailsWm. Michael Meloy
Compliance met. 10/1/2003 11:58:27 AM
Fee Review-notes7/15/20037/15/20037/15/2003 DONE
No mechanical or electrical permit.
BLD-Final9/19/20029/19/20029/19/2002 DONE
Dave said ok/final perm. occ. cn items completed
Permanent occupancy  9/19/2002 DONE
Perm. Occ. Cert. #9352 issued 9-19-02 to the Sockeye Grill & Brewery.
Permanent Occupancy 9/18/20029/18/2002 DONE
Details
Additional plans submitted  8/19/2002 PASS
David Hannah brought in new floor plan layout showing re-routing of the 1-houe occupancy separation wall between the dining & non-dining area to re-align the 1-hour wall around the electrical / mechanical room do to existing electrical panels in what would have been the 1-hour wall and could not be resonably repaired to meet 1-hour construction. The electrical & mechanical room will become part of the 5000 sq. ft. or less drinking /dining area with a 60 minute door, etc. A copy of the plans was returned to the job for inserting into approved plans and a copy was turned into the records division to be inserted in our copies.
BLD-Conference6/27/20026/27/20026/27/2002AFAIL
DetailsDave Hannah
BLD-Final6/10/20026/11/20026/11/2002APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 06/10/2002 at 15:17:41. Contact: ###-####.ok temp oc c/n posted. 6/11/2002 11:43:58 AM
Temporary occupancy  6/11/2002 DONE
Temp. Occ. Cert. #4824 issued 6-11-02 to the Hollow Leg Restaurant/Bar.
BLD-Final6/10/20026/10/20026/10/2002PCANC
DetailsRuss Owen
Scheduled by Inspector: 407 On 6/10/2002 5:13:13 PM Just needed to check history. 6/11/2002 11:25:42 AM
BLD-Final6/7/20026/10/20026/10/2002PFAIL
DetailsRuss Owen
fn -###-####- jason or randy . Needs health dept for a temp also has 4 other building permits at this site. That need to be finaled, also left c/n for 1hr wall penetrations. 6/10/2002 3:40:12 PM 6/10/2002 3:40:20 PM
FIRE-Final Inspection6/5/20026/5/20026/5/2002PPASS
DetailsTroy Cobbley
fire/life safety finaled
FIRE-Final Inspection6/3/20026/3/20026/3/2002APART
DetailsRick Jackson
Scheduled by Inspector: 409 On 6/3/2002 8:16:01 AM tested extinguishing system - okay; still need to resolve the southeast exit door hardware 6/4/2002 6:56:29 AM
FIRE-Final Inspection5/31/20025/31/20025/31/2002PNR
DetailsRick Jackson
Scheduled by Inspector: 409 On 5/31/2002 6:40:58 AM kitchen extinguishing system will be tested on 6/3/02 5/31/2002 3:48:35 PM
FIRE-Final Inspection5/30/20025/30/20025/30/2002AFAIL
DetailsRick Jackson
Added by Inspector: 409 On 5/30/2002 10:40:08 AM panic hardware on SE exit; occupant load signs; repair exit signs; address; need to witness test of AHU duct detectors and extinguishing system; draft stops not complete; complete other permits under structural permits as noted in plan review comments section
BLD-Framing/Rough-in3/19/20023/20/20023/20/2002APART
DetailsJim Sly
fr insp bill-###-#### call 1st before insp please OK to cover walls/ceiling micro brew room. 3/20/2002 12:37:45 PM
Inspection Record Card- Bld  3/14/2002 DONE
Print Occupancy Form  3/14/2002 DONE
Telephone call  3/14/2002 DONE
SPOKE WITH JOE PERMIT READY
Issue PAID IN FULL permit  3/14/2002 DONE
Routing - FIRE3/8/20023/13/20023/13/2002 PASS
DetailsBill Alexander
Plan assigned to (DRS)2/12/2002 3/13/2002 PASS
DetailsDan Stuart
3/13/2002 16:11:28 DRS - activity updated through activity BLDA022 from case BLD02-00169.
Plan Review Completed(1st rev)  3/13/2002 DONE
Routing - PLAN CHECK3/13/2002 3/13/2002 PASS
Approved as noted and attached plan review comments from reviewing agencies.
PLANS/APPL TAKEN TO FRONT DESK  3/13/2002 PASS
To permit desk to issue.
Routing - PLAN CHECK3/1/2002 3/8/2002 PEND
ROUTING TO FIRE CODE ANALYST FOR REVIEW.
Routing - PLUMBING2/26/2002 3/1/2002 PASS
see attached
Plan resubmittals received  2/28/2002 DONE
Received letter from West Boise Sewer District. Attached to plans.
Plan resubmittals received  2/26/2002 DONE
Received two copies of revised sheet A2 Put with plans. kmm
Routing - PLAN CHECK2/20/2002 2/26/2002  
Sent back to plumbing.
Plan resubmittals received  2/26/2002 DONE
Received two sets of resubmittal sheets P-1 and P-2 with Grease Recovery System information. Routed to Dan Stuart.
Routing - PLUMBING2/15/2002 2/20/2002 FAIL
Talked to Bill Matter on 2/15/02 and notified that plans needed to be modified to reflect actual work being done and STOP WORK until plans are approved to include additional sinks and grease abatement.
Routing - PUBLIC WORKS2/12/2002 2/14/2002 PASS
Plans ACCEPTED BY PLAN TECH  2/12/2002 DONE
Plans ACCEPTED BY PLAN TECH  2/5/2002 PEND
<$25,000 Requires plumbing plans, CDH having Bill add hand sinks. Cntacted Bill Matter.
First Notice1/28/20021/28/20021/28/2002 DONE
Plans ACCEPTED BY PLAN TECH  1/28/2002 FAIL
Plans not signed off by CDH. Had Bill Matter give Bud Fuleton a call. He setup a meeting with Bud for 1/29/02. If Bud signs off, Bill will bring plans back and we will start routing. kmm
Application received  1/28/2002  
Recd Pcfee & Taken To Pln CK  1/28/2002