Case Summary (BLD) | | | 8/13/2015 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 3/6/2002 | 3/7/2002 | 3/7/2002 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 03/06/2002 at 21:48:24. Contact: ###-####. ok to cover 3/7/2002 4:58:13 PM
|
BLD-Framing/Rough-in | 3/5/2002 | 3/6/2002 | 3/6/2002 | A | PART |
Dave Hannah
|
|
|
###-#### shear ok needs elec r/i and seal package 3/6/2002 11:36:35 AM
|
BLD-Footing | 2/19/2002 | 2/19/2002 | 2/19/2002 | P | PART |
Dave Hannah
|
|
|
###-####
|
BLD-Foundation | 2/19/2002 | 2/19/2002 | 2/19/2002 | A | PASS |
Dave Hannah
|
|
|
Added by Inspector: 425 On 2/19/2002 9:59:53 AM
|
Inspection Record Card- Bld | | | 1/30/2002 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/30/2002 | | DONE |
|
|
|
|
Plan assigned to (DJO) | 1/29/2002 | 1/29/2002 | 1/29/2002 | | PASS |
Dan Overy
|
|
|
1/29/2002 16:27:10 DJO - activity updated through activity BLDA022 from case BLD02-00178.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/29/2002 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 1/29/2002 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/29/2002 | | DONE |
|
|
|
|
Plan Review Report | | | 1/29/2002 | | DONE |
|
|
|
|
Application received | | | 1/29/2002 | | |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 1/29/2002 | | |
|
|
|
|