BLD-Aging Inspection | 2/20/2004 | 2/20/2004 | 2/20/2004 | | DONE |
Dave Hannah
|
|
|
|
DOC - Permit Expired | 2/20/2004 | 2/20/2004 | 2/20/2004 | P | PASS |
Dave Hannah
|
|
|
Expired by inspector at 2/20/2004 11:32:09 AM
|
Letter of compliance | | | 7/3/2002 | | DONE |
|
|
|
Letter of Complliance #22545 issued 7-3-02.
|
BLD-Final | 6/27/2002 | 6/27/2002 | 6/27/2002 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 06/27/2002 at 06:59:40. Contact: ###-####....card to owner 6/27/2002 11:38:49 AM
|
FIRE-Final Inspection | 6/26/2002 | 6/26/2002 | 6/26/2002 | P | PASS |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 6/26/2002 11:46:38 AM
|
FIRE-Final Inspection | 5/28/2002 | 5/28/2002 | 5/28/2002 | P | FAIL |
Rick Jackson
|
|
|
###-#### dan need alarm plans submitted per plan review notes; strobes not covering all areas; detectors within 3 ft of supply diffusers in hallways; there appears to be 2 in duct detectors as there are two remote LED's; not HVAC plans 5/28/2002 2:55:15 PM
|
BLD-Framing/Rough-in | 4/17/2002 | 4/17/2002 | 4/17/2002 | A | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 04/17/2002 at 07:27:59. Contact: ###-####.
|
BLD-Framing/Rough-in | 4/17/2002 | 4/17/2002 | 4/17/2002 | P | PASS |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 4/17/2002 2:15:43 PM . Ok very little framing, door relocation is scope, also the grid ceiling has been up graded to comply with code,as wire-ties and light supports added, to entire ceiling. 4/17/2002 2:19:14 PM
|
Issue & PRINT to be Invoiced | | | 3/25/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/21/2002 | 3/21/2002 | 3/21/2002 | | PASS |
|
|
|
Approved as noted on plans and attached plan review comments / conditions from all reviewing agencies.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/21/2002 | | PASS |
|
|
|
To permit desk to issue
|
Inspection Record Card- Bld | | | 3/21/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/21/2002 | | DONE |
|
|
|
|
Telephone call | | | 3/21/2002 | | DONE |
|
|
|
emailed permit ready
|
Plan assigned to (DRS) | 2/5/2002 | | 3/21/2002 | | PASS |
Dan Stuart
|
|
|
3/21/2002 08:22:58 DRS - activity updated through activity BLDA022 from case BLD02-00197.
|
Routing - FIRE | 3/15/2002 | | 3/20/2002 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 3/5/2002 | | 3/15/2002 | | PEND |
|
|
|
Approved as noted and attached. No resubmittal required. Routing to fire code analyst for review.
|
Routing - PLUMBING | 2/27/2002 | | 3/5/2002 | | PASS |
|
|
|
per plans and 2000 upc
|
Plan resubmittals received | | | 2/27/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets P1.0, P1.1, P2.0, and P2.1. Routed to Dan Stuart.
|
Routing - PLAN CHECK | 2/8/2002 | | 2/27/2002 | | |
|
|
|
Plumbing plans submitted. Plans routed back to plumbing for review.
|
Routing - PLUMBING | 2/7/2002 | | 2/8/2002 | | FAIL |
|
|
|
please provide plumbing plans
|
Routing - PUBLIC WORKS | 2/5/2002 | | 2/7/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/1/2002 | | DONE |
|
|
|
1. Plans not fully dimensioned.
2. No plumbing/mechanical plans submitted.
3. No building code data on front sheet of plans.
|
First Notice | 1/31/2002 | 1/31/2002 | 1/31/2002 | | DONE |
|
|
|
|
Application received | | | 1/31/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/31/2002 | | |
|
|
|
|