Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD02-00197
StatusExpired
Name ST LUKES STL22611
Site Address 300 E JEFFERSON ST
Project NameST LUKES MOB-2ND FLR
Customer NumberSTL22-611
ePlanReviewNo
Description
(ST LUKES MOB-2ND FLR) To remodel a portion of the 6,800 sq.ft. JMOP office area on the 2nd floor per approved plans on file. To perform selective demolition within an existing tenant space; to construct new interior bearing walls to create a new stroage areas, two nurse area's, a new exam room and reduce size of existing exam room; to relocate entry doors to specific rooms; and modify existing mechanical, electrical, plumbing, sprinkler & alarm as necessary for tenant and minimum code compliance. All per approved plans, notes and attached plan review comments / conditions of reviewing agencies. This building is fully sprinklered to allow additional story increase. A 'LETTER OF COMPLETION/COMPLIANCE IS REQUIRED. PC#02-066/drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection2/20/20042/20/20042/20/2004 DONE
DetailsDave Hannah
DOC - Permit Expired2/20/20042/20/20042/20/2004PPASS
DetailsDave Hannah
Expired by inspector at 2/20/2004 11:32:09 AM
Letter of compliance  7/3/2002 DONE
Letter of Complliance #22545 issued 7-3-02.
BLD-Final6/27/20026/27/20026/27/2002APASS
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 06/27/2002 at 06:59:40. Contact: ###-####....card to owner 6/27/2002 11:38:49 AM
FIRE-Final Inspection6/26/20026/26/20026/26/2002PPASS
DetailsRick Jackson
Scheduled by Inspector: 409 On 6/26/2002 11:46:38 AM
FIRE-Final Inspection5/28/20025/28/20025/28/2002PFAIL
DetailsRick Jackson
###-#### dan need alarm plans submitted per plan review notes; strobes not covering all areas; detectors within 3 ft of supply diffusers in hallways; there appears to be 2 in duct detectors as there are two remote LED's; not HVAC plans 5/28/2002 2:55:15 PM
BLD-Framing/Rough-in4/17/20024/17/20024/17/2002ANR
DetailsTony Young
Scheduled by a contractor via Hello! on 04/17/2002 at 07:27:59. Contact: ###-####.
BLD-Framing/Rough-in4/17/20024/17/20024/17/2002PPASS
DetailsRuss Owen
Scheduled by Inspector: 407 On 4/17/2002 2:15:43 PM . Ok very little framing, door relocation is scope, also the grid ceiling has been up graded to comply with code,as wire-ties and light supports added, to entire ceiling. 4/17/2002 2:19:14 PM
Issue & PRINT to be Invoiced  3/25/2002 DONE
Routing - PLAN CHECK3/21/20023/21/20023/21/2002 PASS
Approved as noted on plans and attached plan review comments / conditions from all reviewing agencies.
PLANS/APPL TAKEN TO FRONT DESK  3/21/2002 PASS
To permit desk to issue
Inspection Record Card- Bld  3/21/2002 DONE
Print Occupancy Form  3/21/2002 DONE
Telephone call  3/21/2002 DONE
emailed permit ready
Plan assigned to (DRS)2/5/2002 3/21/2002 PASS
DetailsDan Stuart
3/21/2002 08:22:58 DRS - activity updated through activity BLDA022 from case BLD02-00197.
Routing - FIRE3/15/2002 3/20/2002 PASS
Routing - PLAN CHECK3/5/2002 3/15/2002 PEND
Approved as noted and attached. No resubmittal required. Routing to fire code analyst for review.
Routing - PLUMBING2/27/2002 3/5/2002 PASS
per plans and 2000 upc
Plan resubmittals received  2/27/2002 DONE
Received two sets of resubmittal sheets P1.0, P1.1, P2.0, and P2.1. Routed to Dan Stuart.
Routing - PLAN CHECK2/8/2002 2/27/2002  
Plumbing plans submitted. Plans routed back to plumbing for review.
Routing - PLUMBING2/7/2002 2/8/2002 FAIL
please provide plumbing plans
Routing - PUBLIC WORKS2/5/2002 2/7/2002 PASS
Plans ACCEPTED BY PLAN TECH  2/1/2002 DONE
1. Plans not fully dimensioned.
2. No plumbing/mechanical plans submitted.
3. No building code data on front sheet of plans.
First Notice1/31/20021/31/20021/31/2002 DONE
Application received  1/31/2002  
Recd Pcfee & Taken To Pln CK  1/31/2002