Permit Information
Permit NumberBLD02-00266
StatusFinaled
Name THE BIG EASY
Site Address 416 S 9TH ST Unit: 106
Project Name9TH STREET WAREHOUSES
Customer Number 
ePlanReviewNo
Description
(THE BIG EASY) This building is fire sprinklered to substitute for 1-hr fire-resistive construction. To remodel the lower level of an existing assembly room to increase the allowable occupant load within the room. The mezzanine level will maintain its maximum occupant load at 192. A 2,500 square foot expansion area in the basement will accommodate support functions (e.g. kitchen, dressing room, storage, etc.) for the assembly room. After the expansion, this tenant will have a total floor area of 11,624 square feet. The maximum occupant load for the lower level of the assembly room is 747 (includes patrons, employees, security personnel, performers, etc.). An approved sign shall be posted near the main exit from the lower level stating: "Maximum occupant load 747 NO tables OR chairs, 348 tables AND/OR chairs" or words to that effect. Work is to include structural headers and trimmers at widened doorways, stairways, guardrails, handrails, fire doors, new structural bracing for the mezzanine, and a toilet/shower room accessible to the disabled all per approved drawings, engineering, and plan review conditions on file. Selective demolition is also covered under this permit. The location of fire sprinkler heads shall comply with NFPA 13-1999 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
(F) Reprint permit  2/25/2008  
Second Notice BLD4/26/20054/26/20054/26/2005 DONE
First Notice has not been responded to.
First Notice 2/3/20054/26/2005 DONE
Case Summary (BLD)  4/20/2005 DONE
Permanent occupancy  2/3/2005 DONE
Perm. Occ. Cert. # 10439 issued 2-3-05 to The Big Easy.
Permanent Occupancy 2/2/20052/2/2005 DONE
Details
BLD-Conference2/2/20052/2/20052/2/2005ACANC
DetailsDave Hannah
BLD-Final2/2/20052/2/20052/2/2005PPASS
DetailsDave Hannah
inspection for occ ok for perm occ dave had carles c/n we went tough all the items and I walked the project allc/n items comlpted 2/2/2005 1:39:50 PM
FIRE-Final Inspection2/2/20052/2/20052/2/2005APASS
DetailsRick Jackson
BLD-Final2/2/20052/2/20052/2/2005PDONE
DetailsDave Hannah
inspection for occ
FIRE-Final Inspection2/2/20052/2/20052/2/2005APASS
DetailsRick Jackson
Final okay 2/2/2005 10:49:18 AM
CHANGE STATUS TO (ISS)  2/2/2005 DONE
Per George Slane///2/2/05 BAS
DOC - Permit Expired2/23/20042/23/20042/23/2004PPASS
DetailsDave Hannah
Expired by inspector at 2/23/2004 11:58:10 AM
BLD-Aging Inspection2/20/20042/20/20042/20/2004 DONE
DetailsDave Hannah
BLD-Aging Inspection8/6/20038/6/20038/6/2003 PASS
DetailsCarl Dependahl
WIP... 8/6/2003 11:28:09 AM WIP... statde work complete?? need engs ok for mezz welds8/6/2003 11:28:09 AM 8/6/2003 11:30:19 AM
BLD-Final5/15/20035/16/20035/16/2003ANR
DetailsCarl Dependahl
david; Phone #: ###-#### Internet Inspection Request from: Darla Downs...keep c/n. 5/16/2003 10:40:41 AM
FIRE-Final Inspection5/15/20035/16/20035/16/2003APART
DetailsRick Jackson
david; Phone #: ###-#### Internet Inspection Request from: Darla Downs balance report for new hood needed 5/16/2003 4:20:29 PM
BLD-Framing/Rough-in5/13/20035/14/20035/14/2003APART
DetailsCarl Dependahl
dave, shaft ok...need other insps for final. 5/14/2003 11:21:59 AM
BLD-Final5/14/20035/14/20035/14/2003PPART
DetailsCarl Dependahl
Dave...###-#### c/n, occ load signs, door listings, misc finish, obtain other finals; ok for t/o except kitchen. 5/14/2003 6:31:24 PM obtain complete mech finals 5/14/2003 6:32:58 PM
BLD-Final5/12/20035/13/20035/13/2003PNR
DetailsCarl Dependahl
DAVID; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Framing/Rough-in5/12/20035/13/20035/13/2003PPART
DetailsCarl Dependahl
dave ; Phone #: ###-#### Internet Inspection Request from: Annette Moore...wip, shaft. 5/14/2003 9:58:35 AM
BLD-Framing/Rough-in5/12/20035/12/20035/12/2003PPART
DetailsCarl Dependahl
shaft over hood ok...duct by 350 5/12/2003 4:05:12 PM
BLD-Final5/9/20035/12/20035/12/2003ACANC
DetailsCarl Dependahl
david; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Framing/Rough-in4/15/20034/16/20034/16/2003APART
DetailsCarl Dependahl
###-#### walls ok, door moved for 18" clr (ADA). 4/16/2003 12:20:02 PM
BLD-Conference4/16/20034/16/20034/16/2003PPART
DetailsCarl Dependahl
Shaft...wip, ok to "3 side" shaft for duct insp by Mechanical insp 4/16/2003 2:03:35 PM
BLD-Conference4/11/20034/14/20034/14/2003APASS
DetailsCarl Dependahl
dave @ devcon...shaft & framing; ###-####; add 18" clr at pull side door at lower level, verify 18" clr to combustibles for hood add drywall as needed...ok to continue, obtain all trade & fire insps prior to frame insp. 4/14/2003 11:40:17 AM
BLD-Aging Inspection3/18/20033/18/20033/18/2003 PASS
DetailsCarl Dependahl
met workmen onsite advised to call for insps as req'd 3/18/2003 9:19:56 AM
Issue PAID IN FULL permit  12/17/2002 DONE
Telephone call  12/13/2002 DONE
TALKED TO SYLVESTER RAMIREZ ON 12/13/02/STATED THAT HE MAY TAKE OVER THE JOB FROM MARK BOWEN. TOLD HIM IT WILL EXPIRE ON DEC 31ST 2002/MLS
Telephone call  9/18/2002 DONE
received letter for tim hogland regarding an extension for the permit until december 31, 2002/mls received letter sept 12, 2002/mls
Telephone call  7/25/2002 DONE
left mess for mark that permit is ready//called on 08/07/02 said they will be in 1st of following week//aim
Telephone call  4/23/2002 DONE
CALLEC MARK PLANS READY 4-23-02 ///DLD
Inspection Record Card- Bld  4/23/2002 DONE
Print Occupancy Form  4/23/2002 DONE
Plan assigned to (CJW)2/12/2002 4/22/2002 PASS
DetailsCarl Westfall
4/22/2002 16:06:29 CJW - activity updated through activity BLDA022 from case BLD02-00266.
Routing - PLAN CHECK3/12/2002 4/22/2002 PASS
Approved with conditions after resubmittal review.
PLANS/APPL TAKEN TO FRONT DESK  4/22/2002 PASS
Plan resubmittals received  4/19/2002 DONE
Received two copies of A3.1, supplemental structural calculationas & sketches and one copy of response letter. Routed to Carl W. kmm
Telephone call  4/15/2002 DONE
Called the architect's representative (Tarrie Wagner). Told her I needed the following information: (1) new elevations showing actual location of new wall openings relative to existing openings, (2) new engineering addressing that loading condition, and (3) engineering addressing the uplift condition by the brace frame on the existing footing.
Plan resubmittals received  4/11/2002 DONE
Received two sets of resubmittal sheets A2.0, A3.1, structural calculations, letter from Engineering Incorporated, and cover letter. routed to Carl Westfall.
Routing - PLAN CHECK3/6/2002 3/12/2002  
On hold waiting for Fire to review.
Routing - FIRE3/12/2002 3/12/2002 PASS
DetailsBill Alexander
Routing - FIRE3/5/2002 3/6/2002  
DetailsBill Alexander
Failed first UFC review. Direction from Fire Department that no permitting allowed (specifically Assembly Increase) prior to aggreement on assembly occupancy control/s. Requires owner meeting with owner and Dave Miller and/or Steve Minnis.
Plan Review Completed(1st rev)  3/6/2002 DONE
Routing - PLAN CHECK2/21/2002 3/5/2002  
Failed first UBC review. UBC plan review started March 4, 2002 and finished the next day. A response from the architect was required. See the conditions list. A copy of the plan review report was sent to the architect.
Routing - PLUMBING2/19/2002 2/21/2002 PASS
per plans and 2000 upc
Routing - PUBLIC WORKS2/13/2002 2/19/2002 PASS
Application received  2/11/2002  
Recd Pcfee & Taken To Pln CK  2/11/2002  
Plans ACCEPTED BY PLAN TECH  2/11/2002 DONE
1. Plans not fully dimensioned.
Fee Review-notes2/11/20022/11/2002