Fee Review-notes | 7/17/2003 | 7/17/2003 | 7/17/2003 | | DONE |
|
|
|
|
(F) Reprint permit | | | 4/23/2003 | | |
|
|
|
|
Permanent Occupancy | | 9/25/2002 | 9/25/2002 | | DONE |
|
|
|
|
Permanent Occupancy | | 9/25/2002 | 9/25/2002 | | DONE |
|
|
|
|
BLD-Final | 9/24/2002 | 9/25/2002 | 9/25/2002 | P | PASS |
Carl Dependahl
|
|
|
Try late in the afternoon and let me know if you are successful in learning anything about the door issue. Thanks!!...doors installed, final ok 9/25/2002 4:47:41 PM
|
Permanent occupancy | | | 9/25/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9379 issued 9-25-02 to the Lock Stock & Barrel.
|
BLD-Conference | 9/12/2002 | 9/18/2002 | 9/18/2002 | P | PASS |
Carl Dependahl
|
|
|
w/ Cathy W...will call Benneton Const re final. 9/18/2002 1:35:18 PM
|
BLD-Conference | 9/10/2002 | 9/17/2002 | 9/17/2002 | P | CANC |
Carl Dependahl
|
|
|
|
BLD-Conference | 9/12/2002 | 9/12/2002 | 9/12/2002 | P | PART |
Carl Dependahl
|
|
|
w/ fire insp....need final?
|
BLD-Conference | 9/10/2002 | 9/12/2002 | 9/12/2002 | P | NH |
Carl Dependahl
|
|
|
|
BLD-Conference | 9/10/2002 | 9/12/2002 | 9/12/2002 | P | NH |
Carl Dependahl
|
|
|
|
BLD-Conference | 9/6/2002 | 9/9/2002 | 9/9/2002 | A | NH |
Carl Dependahl
|
|
|
unable to contact 9/12/2002 1:31:07 PM
|
DOC - Permit Finaled | 9/6/2002 | 9/6/2002 | 9/6/2002 | P | PASS |
Carl Dependahl
|
|
|
|
BLD-Conference | 8/29/2002 | 9/3/2002 | 9/6/2002 | P | CANC |
Carl Dependahl
|
|
|
|
BLD-Conference | 8/27/2002 | 8/28/2002 | 8/29/2002 | P | NR |
Carl Dependahl
|
|
|
For t/o review
|
BLD-Final | 8/27/2002 | 8/27/2002 | 8/27/2002 | P | NR |
Carl Dependahl
|
|
|
left msg. 8/27/2002 5:27:15 PM
|
Fee Review-notes | 2/12/2002 | 2/12/2002 | 6/20/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/10/2002 | 5/13/2002 | 5/13/2002 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 05/10/2002 at 12:07:27. Contact: ###-####. one bulb on emergency light on second floor not working; rated door on second floor has hold open; both to be fixed for structural inspection 5/13/2002 8:49:11 AM
|
BLD-Final | 5/10/2002 | 5/13/2002 | 5/13/2002 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/10/2002 at 12:08:10. Contact: ###-####.
|
BLD-Conference | 5/13/2002 | 5/13/2002 | 5/13/2002 | P | PASS |
Carl Dependahl
|
|
|
re exist rated door at 2nd fl. kee 5/13/2002 2:53:12 PM c/n, need latching at 2nd fl occ sep wall 5/13/2002 2:56:58 PM
|
Temporary occupancy | | | 5/13/2002 | | DONE |
|
|
|
Temp. Occ. Cert. #4807 issued 5-13-02 to the Lock Stock & Barrel.
|
BLD-Conference | 5/6/2002 | 5/7/2002 | 5/7/2002 | A | DONE |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 05/06/2002 at 13:43:40. Contact: ###-####.
conf by 340 5/7/2002 2:16:18 PM
|
BLD-Conference | 5/7/2002 | 5/7/2002 | 5/7/2002 | P | CANC |
Tony Young
|
|
|
5/7/2002 11:34:20 AM
|
FIRE-Conference | 4/9/2002 | 4/9/2002 | 4/9/2002 | P | PART |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 4/9/2002 9:14:14 AM met with Cheryl of Erstad and went through the plans for exit signs; emergency lights; door hardware and kitchen requirements; basement sprinklers are overspaced and several areas unprotected; called Jsson about it and he said the exiting was based on full sprinklers from the basement; called Cheryl and told her the basement will have to be fully sprinklered 4/9/2002 3:33:28 PM
|
BLD-Conference | 4/9/2002 | 4/9/2002 | 4/9/2002 | P | PASS |
Carl Dependahl
|
|
|
w/ Fire & arch onsite re exit doors.
|
BLD-Framing/Rough-in | 4/8/2002 | 4/9/2002 | 4/9/2002 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/08/2002 at 12:35:23. Contact: ###-####. ok to cover, c/n ok...install rails & doors as needed per plan 4/9/2002 1:25:32 PM
|
BLD-Conference | 4/8/2002 | 4/8/2002 | 4/8/2002 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/8/2002 4:17:51 PM w/ arch re c/n...consult fire insp re door hdwe.
|
BLD-Framing/Rough-in | 4/4/2002 | 4/8/2002 | 4/8/2002 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/04/2002 at 15:50:12. Contact: ###-####.complete fireblocks, remove face paper & un-backed 1/4" panelling 4/8/2002 11:28:11 AM
|
Issue PAID IN FULL permit | | | 4/3/2002 | | DONE |
|
|
|
|
Routing - FIRE | 3/28/2002 | 4/2/2002 | 4/2/2002 | | PASS |
Bill Alexander
|
|
|
Review attached waiver by Tim Hoagland.
|
Routing - PLAN CHECK | 4/2/2002 | | 4/2/2002 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/2/2002 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 4/2/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/2/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/2/2002 | | DONE |
|
|
|
|
Telephone call | | | 4/2/2002 | | DONE |
|
|
|
|
Plan assigned to (JCB) | 2/14/2002 | | 4/2/2002 | | PASS |
Jason Blais
|
|
|
4/2/2002 13:44:40 JCB - activity updated through activity BLDA022 from case BLD02-00276.
|
Routing - PLAN CHECK | 3/19/2002 | | 3/28/2002 | | FAIL |
|
|
|
MIS permit application still needs to be provided for the 2nd floor office tenant. Plans routed to the Fire Dept. for 2nd review.
|
Additional plans submitted | | | 3/27/2002 | | DONE |
|
|
|
Received letter from Andy Erstad/Cheryl Pearse to Jason and Tim Hogland, requesting the exception to half of the diagional to the basement stairs. Routed to Jason B. kmm
|
Plan resubmittals received | | | 3/27/2002 | | DONE |
|
|
|
RECEIVED TWO COPIES OF RESUBMITTAL SHEET a2.12 WITH TRANSMITTAL. ROUTED TO JASON BLAIS.
|
Telephone call | | | 3/26/2002 | | DONE |
|
|
|
Called architect's representative to discuss resubmittal drawings received. Basement floor plan to be addressed and another sheet will be provided.
|
Plan resubmittals received | | | 3/25/2002 | | DONE |
|
|
|
Received two copies of revised sheets a0.01, a1.00, a1.11, a2.10, a2.11, a2.12, a2.21, a6.11. One copy of plan check response letter, one copy of fire response letter, one copy of Unitied Water letter and one copy of Tenant Improvement Permit Application for Sandpiper Offices. Routed to Jason B. kmm
|
Routing - FIRE | 3/13/2002 | 3/19/2002 | 3/19/2002 | | FAIL |
Bill Alexander
|
|
|
Construction type is vague/conflicting which affect fire protection and required fire resistive issues, including exteriror walls and property lines. Verify hydrants and fire flows. Require info on cooking hood/s. Show egress ilumination, egress exit identification. Door hardware info is vague or lacking, etc.
|
Plan Review Completed(1st rev) | | | 3/19/2002 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/18/2002 | | DONE |
|
|
|
Received eight copies of a letter requesting exception for the occupant load. Routed to Jason Blais
|
Routing - PLANNING | 3/12/2002 | | 3/12/2002 | | PASS |
|
|
|
Route to Sarah Schafer. Approved per CZC02-24.
|
Plan resubmittals requested | | | 3/12/2002 | | |
|
|
|
Plan resubmittals and response required for further review.
|
Routing - PLAN CHECK | 2/20/2002 | | 3/12/2002 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to Planning and Fire Dept. for review.
|
Meeting | | | 3/11/2002 | | |
|
|
|
Met with architect's representative and went over deficient or missing items from submitted plans.
|
Routing - PLUMBING | 2/15/2002 | | 2/20/2002 | | PASS |
|
|
|
if any equipmenis relocated or installed a plumbing permit and inspection will be required
|
Routing - PUBLIC WORKS | 2/14/2002 | | 2/15/2002 | | PASS |
|
|
|
|
Additional plans submitted | | | 2/15/2002 | | DONE |
|
|
|
Received request for demo permit as soon as possible. Had applicant fill out revised certificate of value. Routed to Jason Blais.
|
Plans ACCEPTED BY PLAN TECH | | | 2/12/2002 | | DONE |
|
|
|
1. Plans not fully dimensioned.
|
Application received | | | 2/12/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/12/2002 | | |
|
|
|
|