BLD-Final | 7/17/2002 | 7/18/2002 | 7/18/2002 | A | FAIL |
Steven Webb
|
|
|
RICK ; Phone #: ###-#### C/N--gaskets or caulk behind electrical outlets at outside walls. 7/18/2002 10:17:31 AM
|
BLD-Final | 7/18/2002 | 7/18/2002 | 7/18/2002 | P | PASS |
Steven Webb
|
|
|
RICH; Phone #: ###-#### 7/18/2002 2:46:39 PM C. of C. #22468 issued. 7/18/2002 2:47:25 PM
|
DOC - Permit Finaled | 7/18/2002 | 7/18/2002 | 7/18/2002 | P | PASS |
Steven Webb
|
|
|
Finaled by inspector at 7/18/2002 2:47:33 PM
|
BLD-Framing/Rough-in | 5/8/2002 | 5/9/2002 | 5/9/2002 | A | PASS |
Steven Webb
|
|
|
###-#### Ok to cover 5/9/2002 11:24:35 AM
|
BLD-Energy code compliance | 5/8/2002 | 5/8/2002 | 5/8/2002 | P | NR |
Steven Webb
|
|
|
###-#### C/N issued--Truss package does not match per construction. Unable to re-inspect per prior correction notice. Re-inspection fee accessed. Re-inspection required before covering is allowed. 5/8/2002 1:52:55 PM
|
BLD-Energy code compliance | 5/8/2002 | 5/8/2002 | 5/8/2002 | P | NR |
Steven Webb
|
|
|
###-#### C/N issued--Truss package does not match per construction. Unable to re-inspect per prior correction notice. Re-inspection fee accessed. Re-inspection required before covering is allowed. 5/8/2002 1:52:55 PM
|
BLD-Energy code compliance | 5/6/2002 | 5/8/2002 | 5/8/2002 | A | FAIL |
Jim Storey
|
|
|
1. no aproved plan and engineering on site to inspect c/n isued previously. DO NOT COVER WITH OUT REINSP.
|
BLD-Framing/Rough-in | 5/6/2002 | 5/6/2002 | 5/6/2002 | P | FAIL |
Dave Hannah
|
|
|
###-#### RICH c/n on site ok to insulate 5/6/2002 2:03:15 PM
|
BLD-Wall cover | 4/19/2002 | 4/22/2002 | 4/22/2002 | A | FAIL |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 04/19/2002 at 10:45:17. Contact: ###-####.
|
BLD-Framing/Rough-in | 4/22/2002 | 4/22/2002 | 4/22/2002 | P | PART |
Steven Webb
|
|
|
shear wall- ###-#### rich Shear--ok to side 4/22/2002 1:49:53 PM
|
BLD-Foundation | 3/14/2002 | 3/15/2002 | 3/15/2002 | A | PART |
Steven Webb
|
|
|
###-#### rich wip 3/15/2002 10:44:37 AM
|
BLD-Footing | 3/12/2002 | 3/13/2002 | 3/13/2002 | A | PART |
Steven Webb
|
|
|
###-#### rich wip--70% completed at time of inspection 3/13/2002 10:18:16 AM
|
Issue PAID IN FULL permit | | | 3/12/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/19/2002 | | 3/7/2002 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 2/25/2002 | | 3/7/2002 | | PASS |
Steve Munroe
|
|
|
3/7/2002 10:32:28 SAM - activity updated through activity BLDA022 from case BLD02-00287.
|
Print Pending Permit.LaserJet4 | | | 3/7/2002 | | |
|
|
|
|
Plan Review Report | | | 3/7/2002 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/7/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/7/2002 | | DONE |
|
|
|
|
Telephone call | | | 3/7/2002 | | DONE |
|
|
|
permit ready
|
Plan Reviewer's activity | | | 3/6/2002 | | PEND |
|
|
|
3/6/02 13:30 I called and left a message for the engineer. I recieved lateral engineering for the project but NO engineering for the over height walls. I also have a question on the drag truss. Plans are on hold till I hear from the engineer.
|
Plan Reviewer's activity | | | 2/25/2002 | | PEND |
|
|
|
2/25/02 15:55 I talked to Rich. I let him know that I need overheight wall and lateral engineering for the entry and dining room. He had me make the fireplace full height to fit a brace panel. He will also get me a truss plan and a attic truss profile. Plans are on hold till I recieve the information.
|
Pending Assignment by DJO | 2/13/2002 | | 2/25/2002 | | DONE |
Dan Overy
|
|
|
2/25/2002 14:44:06 SAM - activity updated through activity BLDA183 from case BLD02-00287.
|
Routing - PUBLIC WORKS | 2/19/2002 | | 2/19/2002 | | PASS |
|
|
|
|
Routing - PLANNING | 2/13/2002 | | 2/15/2002 | | PASS |
|
|
|
|
Application received | | | 2/13/2002 | | |
|
|
|
|