Case Summary (BLD) | | | 2/20/2007 | | |
|
|
|
|
Case Summary (BLD) | | | 2/15/2007 | | |
|
|
|
|
Fee Review-notes | 7/17/2003 | 7/17/2003 | 7/17/2003 | | DONE |
|
|
|
|
Fee Review-notes | 2/13/2002 | 2/13/2002 | 8/21/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/14/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9171 issued 6-14-02 to the Bear Creek Fly Shop.
|
BLD-Final | 6/5/2002 | 6/6/2002 | 6/6/2002 | P | PASS |
Tony Young
|
|
|
fn isnp - richard ###-####
|
BLD-Final | 4/8/2002 | 4/9/2002 | 4/9/2002 | A | FAIL |
Tony Young
|
|
|
fn occ-re-insp -richard ###-####
c/n posted 4/9/2002 9:34:17 AM
|
FIRE-Final Inspection | 4/8/2002 | 4/9/2002 | 4/9/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life safety OK 4/9/2002 10:31:28 AM
|
BLD-Final | 4/9/2002 | 4/9/2002 | 4/9/2002 | P | PART |
Tony Young
|
|
|
temp. occ. ok untill tenant moves in, then we can look at aisle widths and ada on counter height, etc.(unless supervisor is ok w/ it now, all else ok) 4/9/2002 3:12:26 PM
|
FIRE-Final Inspection | 4/8/2002 | 4/8/2002 | 4/8/2002 | P | FAIL |
Troy Cobbley
|
|
|
repair rear exit sign, provide "door to remain unlocked" sticker on main exit and test duct detector. Fire sprinklers OK 4/8/2002 12:03:08 PM 4/8/2002 12:05:46 PM
04/08/02 - Dave Miller approved this project with no FIR permit/plans as requested under UFC plan review.
|
BLD-Final | 4/8/2002 | 4/8/2002 | 4/8/2002 | P | FAIL |
Tony Young
|
|
|
richard or randy - ###-#### pending fire fn--key above the entry
no inspection made, need fire sign off 4/8/2002 3:53:46 PM
|
FIRE-Final Inspection | 4/3/2002 | 4/4/2002 | 4/4/2002 | P | FAIL |
Troy Cobbley
|
|
|
no approved fire sprinkler plans on site, hvac unit did not shut down per umc section 608. No other items were inspected 4/5/2002 9:22:27 AM
|
BLD-Framing/Rough-in | 3/18/2002 | 3/18/2002 | 3/18/2002 | P | PART |
Tony Young
|
|
|
###-#### larry
walls ok to cover 3/18/2002 4:40:20 PM
|
Issue PAID IN FULL permit | | | 3/14/2002 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 2/14/2002 | | 3/13/2002 | | PASS |
|
|
|
3/13/2002 14:29:27 RMH - activity updated through activity BLDA022 from case BLD02-00293.
|
Routing - PLAN CHECK | 3/12/2002 | | 3/13/2002 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/13/2002 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 3/13/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/13/2002 | | DONE |
|
|
|
|
Telephone call | | | 3/13/2002 | | DONE |
|
|
|
|
Routing - FIRE | 3/8/2002 | 3/12/2002 | 3/12/2002 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 3/12/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/21/2002 | | 3/8/2002 | | FAIL |
Ron Hill
|
|
|
|
Plan Reviewer's activity | | | 3/7/2002 | | FAIL |
Ron Hill
|
|
|
Faxed requirements to the architect and routed plans to the fire department on 3/8/02
|
Case Summary (BLD) | | | 3/7/2002 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/7/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets A-1 and A-2. Routed to ron hill.
|
Routing - PUBLIC WORKS | 2/14/2002 | | 2/21/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/14/2002 | | DONE |
|
|
|
1. Plans not fully dimensioned.
2. Informed applicant that plumbing plans might be required. General Notes state "Plumbing work to be design-build"
|
Application received | | | 2/13/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/13/2002 | | DONE |
|
|
|
|