Fee Review-notes | 7/17/2003 | 7/17/2003 | 7/17/2003 | | DONE |
|
|
|
Additional value from subcontractors.
|
Permanent occupancy | | | 6/17/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9176 issued 6-17-02 to Community Partnerships in the Medallion Bldg. #2.
|
Permanent Occupancy | | 6/14/2002 | 6/14/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 6/13/2002 | 6/14/2002 | 6/14/2002 | A | PASS |
Troy Cobbley
|
|
|
Fire life/safety ok. Structural inspector to verify that sticker is on south door and that the thumbturn/deadbolt has been removed from interior door 6/14/2002 2:46:44 PM
|
BLD-Final | 6/13/2002 | 6/14/2002 | 6/14/2002 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 06/13/2002 at 09:19:17. Contact: ###-####. OK for Perm Occ. 6/14/2002 3:44:12 PM
|
BLD-Framing/Rough-in | 6/10/2002 | 6/11/2002 | 6/11/2002 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 06/10/2002 at 16:07:15. Contact: ###-####. NEEDS SPACER BARS CHECK AT FINAL 6/11/2002 2:45:07 PM
|
BLD-Framing/Rough-in | 6/10/2002 | 6/11/2002 | 6/10/2002 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 06/10/2002 at 15:14:33. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 06/10/2002 at 16:05:53.
|
BLD-Framing/Rough-in | 5/20/2002 | 5/21/2002 | 5/21/2002 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 05/20/2002 at 10:24:20. Contact: ###-####.
|
Print Occupancy Form | | | 4/17/2002 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/16/2002 | | |
|
|
|
|
Routing - FIRE | 4/10/2002 | 4/15/2002 | 4/15/2002 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 4/15/2002 | | 4/15/2002 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/15/2002 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 4/15/2002 | | DONE |
|
|
|
|
Telephone call | | | 4/15/2002 | | DONE |
|
|
|
CALLED SAM LEFT VOICE MESSAGE PLANS READY
|
Plan assigned to (JCB) | 2/21/2002 | | 4/15/2002 | | PASS |
Jason Blais
|
|
|
4/15/2002 14:24:58 JCB - activity updated through activity BLDA022 from case BLD02-00308.
|
Routing - PLAN CHECK | 3/26/2002 | | 4/10/2002 | | PEND |
|
|
|
When approved by Fire Dept. permit can be issued. Plans routed to Fire Dept.
|
Plan resubmittals received | | | 4/1/2002 | | DONE |
|
|
|
Received two copies of resubmittal sheets A-0, A-1, A-2, AND Mechanical comments. Routed to Jason Blais.
|
Routing - FIRE | 3/22/2002 | 3/26/2002 | 3/26/2002 | | FAIL |
Bill Alexander
|
|
|
UBC related UFC issues with 1111, 1112, 1209, 1211, 1213 and Table 10-A.
|
Plan Review Completed(1st rev) | | | 3/26/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/26/2002 | | 3/22/2002 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to Fire Dept.
|
Plan resubmittals requested | | | 3/22/2002 | | |
|
|
|
Plan resubmittals and written response required for further review.
|
Telephone call | | | 3/21/2002 | | DONE |
|
|
|
Called architect's representative, Sam Burrows, and went over some issues concerning exiting on the design.
|
Routing - PUBLIC WORKS | 2/21/2002 | | 2/26/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/19/2002 | | DONE |
|
|
|
1. Mechanical/Electrical plans not stamped/signed.
2. I called Sam Burrows/Lombard Conrad Architects regarding the kitchen on the plan. He said that the kitchen is strictly for heating up food that has been prepared elsewhere and brought in.
|
First Notice | 2/15/2002 | 2/15/2002 | 2/15/2002 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/15/2002 | | |
|
|
|
|
Application received | | | 2/15/2002 | | |
|
|
|
|