BLD-Aging Inspection | 12/19/2003 | 12/19/2003 | 12/19/2003 | | DONE |
Jim Storey
|
|
|
310 12/19/2003 7:58:53 AM
|
DOC - Permit Finaled | 12/19/2003 | 12/19/2003 | 12/19/2003 | A | PASS |
Jim Storey
|
|
|
Finaled by inspector at 12/19/2003 7:59:47 AM
|
BLD-Final | 6/19/2002 | 6/20/2002 | 6/20/2002 | A | PASS |
Jim Storey
|
|
|
final ok lost occ sign off card. l/c 6/20/2002 11:04:09 AM
|
FIRE-Final Inspection | 6/20/2002 | 6/20/2002 | 6/20/2002 | | DONE |
|
|
|
Fire Life Safety & Sprinkler - final approved
|
Letter of compliance | | | 6/20/2002 | | DONE |
|
|
|
Letter of Compliance #22525 issued 6-20-02.
|
Print Occupancy Form | | | 6/20/2002 | | DONE |
|
|
|
|
BLD-Final | 6/19/2002 | 6/19/2002 | 6/19/2002 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 06/19/2002 at 07:06:15. Contact: ###-####.out of time. 6/19/2002 6:02:15 PM
|
BLD-Final | 6/13/2002 | 6/13/2002 | 6/13/2002 | P | CANC |
Jim Storey
|
|
|
DENNIS ###-#### need fir insp first. 6/13/2002 2:22:12 PM
|
BLD-Other | 6/11/2002 | 6/12/2002 | 6/12/2002 | A | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 06/11/2002 at 15:08:24. Contact: ###-####. wrong call for type of insp. 6/12/2002 3:18:47 PM
|
BLD-Framing/Rough-in | 4/15/2002 | 4/15/2002 | 4/15/2002 | P | PASS |
Jim Storey
|
|
|
###-#### dennis welding ok framing ok. 4/15/2002 1:39:04 PM
|
Plan assigned to (JCM) | 2/22/2002 | | 4/11/2002 | | PASS |
John Menard
|
|
|
4/11/2002 10:36:29 JCM - activity updated through activity BLDA022 from case BLD02-00351.
|
Routing - FIRE | 4/3/2002 | | 4/11/2002 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 4/11/2002 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/11/2002 | | 4/11/2002 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/11/2002 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 4/11/2002 | | DONE |
|
|
|
|
Telephone call | | | 4/11/2002 | | DONE |
|
|
|
paul will be in today
|
Issue & PRINT to be Invoiced | | | 4/11/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/5/2002 | | 4/3/2002 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 4/3/2002 | | PASS |
|
|
|
Resubmittals reviewed and approved as submitted with attached comment list. JCM
|
Plan resubmittals received | | | 4/1/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets S5.1, S5.2, and steel beam design, with cover letter and updated floor plan. Routed to John Menard.
|
Plan resubmittals received | | | 3/29/2002 | | |
|
|
|
mls
|
Plan resubmittals requested | | | 3/11/2002 | | HOLD |
|
|
|
Sent the architect or record an e-mail requesting additional information necessary to process this application. JCM
|
Routing - PLUMBING | 2/26/2002 | | 3/5/2002 | | PASS |
|
|
|
per plans and 2000 upc
|
Routing - PUBLIC WORKS | 2/22/2002 | | 2/26/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/22/2002 | | DONE |
|
|
|
|
Plan routing begun/TENANTS | | | 2/22/2002 | | DONE |
|
|
|
|
First Notice | 2/21/2002 | 2/21/2002 | 2/21/2002 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/21/2002 | | DONE |
|
|
|
|