Permit Information
Permit NumberBLD02-00373
StatusFinaled
Name CIVIC PLAZA PA-2 APARTMENTS
Site Address 252 E FRONT ST
Project NameID WATER CENTER-PA2 BLDG D
Customer Number 
ePlanReviewNo
Description
Civic Plaza Apartments PA-2 * (Section 4 of 6) * To construct two four-hour area separation walls to divide this building into six separate buildings. This section is 5 stories and 25 units, @ 4,666 sq.ft. per floor, above a three-hour occupancy separation per UBC Section 311.2.2.1. NOTE: This building is fully fire sprinklered for story increase. All construction per the aproved plans, attached comment list and CABO/ANSI A117.9-1992. MJP PC#111-02 DRH-01-00186 CUP01-00120
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  6/15/2016 DONE
Second Notice BLD4/26/20054/26/20054/26/2005 DONE
First Notice has not been responded to.
First Notice 5/11/20044/26/2005 DONE
Case Summary (BLD)  12/7/2004  
Fee Review-notes2/22/20022/22/20028/10/2004 DONE
BLD-Final5/11/20045/11/20045/11/2004APASS
DetailsDave Hannah
Permanent Occupancy 5/11/20045/11/2004 DONE
Details
Permanent occupancy  5/11/2004 DONE
Perm. Occ. Cert. # 10134 issued 5-11-04 to the Civic Plaza Apts., Bldg. d, sec. 4 of 6.
FIRE-Final Inspection2/24/20042/25/20042/25/2004APASS
DetailsRick Jackson
RANDY; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Final2/24/20042/25/20042/25/2004APART
DetailsDave Hannah
RANDY; Phone #: ###-#### Internet Inspection Request from: Darla Downs ok for temp occ 2/25/2004 12:37:33 PM
Temporary occupancy  2/25/2004 DONE
Temp. Occ. Cert. # 5081 issued 2-25-04 to the Civic Plaza Apts., sec. 4 of 6.
BLD-Final2/23/20042/24/20042/24/2004ACANC
DetailsDave Hannah
Dennis; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
BLD-Final2/20/20042/23/20042/23/2004AFAIL
DetailsDave Hannah
dennis; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
Code Occupancy Approval  2/23/2004 DONE
BLD-Final2/19/20042/20/20042/20/2004AFAIL
DetailsTroy James
dennis; Phone #: ###-#### Internet Inspection Request from: Annette Moore Checked doors for closure, seal and hardware. 2/20/2004 11:13:53 AM
BLD-Final2/17/20042/18/20042/18/2004ANR
DetailsDave Hannah
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore
FIRE-Final Inspection2/17/20042/18/20042/18/2004AFAIL
DetailsRick Jackson
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore need signs on FACP and sprinkler room doors; signs in stairwells; extinguishers in lobby and fire pump room; lobby doors can't locked to trap people in lobby area; need extinguishers in penthouse rooms and on all floors; need smoke seals on all rated doors and they must latch; need to verify emergency lighting in corridors; stairwells and exit systems must be free of construction materials; update keys in knox box; complete elevator recall/shunt and sign-off 2/18/2004 3:43:29 PM 2/18/2004 3:44:23 PM
BLD-Final2/9/20042/9/20042/9/2004PNR
DetailsDave Hannah
dennis; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Framing/Rough-in2/4/20042/4/20042/4/2004PPART
DetailsDave Hannah
dennis ; Phone #: ###-#### Internet Inspection Request from: Annette Moore
BLD-Aging Inspection8/20/20038/20/20038/20/2003 PASS
DetailsCarl Dependahl
PA2 wip 8/20/2003 9:33:29 AM
BLD-Framing/Rough-in6/19/20036/20/20036/20/2003APART
DetailsCarl Dependahl
4hr wall, wip, ok. 6/20/2003 2:32:16 PM
BLD-Conference6/20/20036/20/20036/20/2003PPASS
DetailsCarl Dependahl
need modification detail for shaft 6/20/2003 5:15:40 PM
BLD-Framing/Rough-in5/5/20035/9/20035/9/2003ACANC
DetailsCarl Dependahl
randy; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Framing/Rough-in5/5/20035/8/20035/9/2003APART
DetailsCarl Dependahl
randy; Phone #: ###-#### Internet Inspection Request from: Barbara Moore; prelim only, wip. 5/9/2003 11:55:50 AM
BLD-Framing/Rough-in5/5/20035/7/20035/7/2003APART
DetailsCarl Dependahl
randy; Phone #: ###-#### Internet Inspection Request from: Barbara Moore...rec'd eng's ok for ISI's eng'd design of 4hr wall framing...wip ok, extend to/thru corridors as req'd. 5/7/2003 5:00:40 PM
BLD-Framing/Rough-in5/5/20035/6/20035/6/2003APART
DetailsCarl Dependahl
randy; Phone #: ###-#### Internet Inspection Request from: Barbara Moore firewall wip 5/6/2003 3:50:50 PM
BLD-Conference4/18/20034/21/20034/21/2003PPASS
DetailsCarl Dependahl
Need stamped eng'g & arch's ok for altered framing 4/21/2003 5:00:49 PM
BLD-Conference4/14/20034/14/20034/14/2003PPASS
DetailsCarl Dependahl
re 4hr walls...build per eng'g 4/14/2003 5:45:50 PM
BLD-Conference3/25/20033/25/20033/25/2003PPASS
DetailsCarl Dependahl
met arch onsite...keep c/n re struct obsevation; Margie will obtain eng's schedule of insps....will advise 3/25/2003 5:44:00 PM
Print Occupancy Form  2/19/2003 DONE
Override - Parcel Holds  2/19/2003  
Issue PAID IN FULL permit  2/19/2003 DONE
Plan assigned to (M_P)2/26/2002 2/18/2003 PASS
DetailsMike Phillips
2/18/2003 16:38:06 M_P - activity updated through activity BLDA022 from case BLD02-00373.
Routing - PLAN CHECK2/13/2003 2/18/2003 PASS
PLANS/APPL TAKEN TO FRONT DESK  2/18/2003 DONE
Override - Parcel Holds  2/18/2003  
Print Pending Permit.LaserJet4  2/18/2003 DONE
Case Summary (BLD)  2/18/2003 DONE
Plan resubmittals received  2/13/2003 DONE
Received two copies of resubmittal sheets A1.2, A2.1, A2.2, A2.3, A3.25, A4.2, A4.4, A4.5, A4.6, A4.7, A4.14, A6.80, M1.1. Routed to Mike Phillips.
Routing - PUBLIC WORKS2/11/2003 2/12/2003 PASS
Routing - PLUMBING2/12/2003 2/12/2003 PASS
see bld02-00369
Routing - PLAN CHECK2/10/2003 2/11/2003  
Plan resubmittals received  2/11/2003 DONE
Received two sets of resubmittal sheets P1.0, P1.1, P1.2, P1.4, P2.1, P4.1, with Letter and Hot Water Calculations and Transmittal. Routed to Mike Phillips.
Routing - PUBLIC WORKS2/10/2003 2/10/2003 FAIL
Need PW Dewater Agreement per Brian Murphy.
Routing - FIRE2/6/2003 2/10/2003 PASS
DetailsBill Alexander
Routing - PLUMBING1/27/2003 1/29/2003 FAIL
see bld02-0369 for comments
Routing - PLAN CHECK1/21/2003 1/27/2003 FAIL
Plans are being routed while construction design is conformed. Re: wood in exterior walls which is not fire retarded lumber and wood in 4 hour area separation walls.
Routing - PLUMBING1/15/2003 1/21/2003 FAIL
overflow drains will not be allowed to drain into courtyard, provide a plan showing all piping in the lower parking level, provide a plan showing laundry room piping, provide a plan showing upper floor perking level floor drainage and interceptor detail and location, piping to area drain shown on page C-5.10, trash enclosure?, provide page P4.1, provide a plan showing piping to drains for fire water blowdown shown on page M5.02, provide page M5.02, provide water sizing calculation for pipe sizes 1/2" thru 4", provide courtyard and planter drain detail and piping.
Routing - PUBLIC WORKS1/3/2003 1/15/2003 FAIL
Need PW de-water agreement
Routing Off Site - STRUCTURAL12/26/2002 1/3/2003 PASS
Contacted PDQ to take reivsed plans of 12/24/02 to outside eng. kmm
No further review required by outside engineering firm.
Routing - PLANNING12/31/2002 1/3/2003 PASS
Approve per DRH02-102 (Modification of DRH01-186).
Routing - PLAN CHECK11/4/2002 12/31/2002  
Plan resubmittals received  12/24/2002 DONE
Received three copies of revised T-1, GEN-2, GEN-3, A-0.01, AP-1.1, A-1.0, A-1.01, A-1.02, A-1.1, A-1.2, A-1.3, A-1.4, A-1.5, A-1.6, A-1.7, A-1.8, A-1.9, A-1.10, A-1.11, A-2.1, A-2.2, A-2.3, A-3.1, A-3.11, A-3.12A-3.13, A-3.14, A-3.21, A-3.22, A-3.23, A-3.24, A-3.25, A-3.26,, A-3.27, A-3.30, A-4.1, A-4.2, A-4.3, A-4.4, A-4.5, A-4.6, A-4.7, A-4.11, A-4.12, A-4.13, A-4.14, A-4.15, A-4.16, A-4.20, A-4.42, A-5.01, A-5.01a, A-5.02, A-5.03, A-6.10, A-6.11, A-6.12, A-6.13, A-6.14, A-6.15, A-6.16, A-6.40, A-6.50, A-6.60, A-6.70, A-6.71, A-6.72, A-6.73, A-6.;80, A-6.81, A-6.86, A-6.87, S0.01, S0.02, S0.03, S2.01, S2.11, S2.12, S2.21, S2.22, S2.23, S2.24, S2.31, S2.41, S3.01, S3.11, S3.21, S3.31, S3.32, S4.01, S4.02, P0.0, P0.1, P1.1, P1.2, P1.3, P1.4, P2.1, P3.1, M0.0, M0.1, M1.1, M2.1, M2.6, M3.1, M3.2, M4.0. E.0, E1.0A, E1.0FB, E1.0, E2.1F, E2.1L, E2.1P, E2.2F, E2.2L, E2.2P, E2.2S, E2.3F, E2.3L, E2.3P, E2.3S, E2.4F, E2.4L, E2.4P, E2.4S, E2.5F, E2.5L, E2.5P, E2.5S, E2.6F, E2.6L, E2.6P, E2.6S, E2.7F, E2.7P, E2.8T, E2.8PA, E2.8PB, E2.8PC, E2.8PD, E2.8PE, E3.0, E4.0, E4.1, E4.2. One copy of cover letter and three copies of struct. calcs. Routed one copy to outside eng. and two to Mike Phillips
Routing - PUBLIC WORKS11/1/2002 11/4/2002 FAIL
Need PW Dewater agreement. Requires Drainage Plan.
Routing - PLAN CHECK3/25/2002 11/1/2002  
Routing - FIRE3/22/20023/25/20023/25/2002 FAIL
DetailsBill Alexander
LACK AREA SEPARATIONS: M1.02, M2.01, M2.02, M2.03, M2.04, M2.05 and M4.01 have ducts/venting penetrating area separation walls without smoke/fire damper protection. The required smoke/fire dampers (recorded and addressed - UBC review) shall be included in the conceptual fire alarm drawings E-4.00, E-4.01, E-4.02, E-4.03, E-4.04, E-4.05 and E-4.06. Also required is location of horizontal exits and the verification of it's areas separation requirements.
LACKHORIZONTAL EXITS: No information provided verifying horizontal exit requirements. This also affects requirements for installation of standpipe system outlets per UFC 1004.3.
LACK MEANS OF EGRESS IDENTIFICATION: No information provided for means of egress identification.
LACK MEANS OF EGRESS ILLUMINATION: No information provided for means of egress illumination.
Plan Review Completed(1st rev)  3/25/2002 DONE
Routing - PLAN CHECK3/14/2002 3/22/2002 FAIL
Plan review completed sent correction report to architect. Additional information required for further review.
Routing Off Site - STRUCTURAL2/26/2002 3/18/2002 FAIL
Contacted PDQ to take plans to outside eng. kmm
Review completed, second review required by outside engineering firm.
Routing - PLUMBING3/11/2002 3/14/2002 FAIL
overflow drains will not be allowed to drain to courtyard, provide a plan showing all piping in the lower parking area, provide a plan showing laundry room piping, provide a plan showing upper parking level floor drainage and interceptor detail and location, piping to area drain shown on page C-5.10, provide a plan showing piping to drains for fire water blowdown shown on page M5.02, provide water sizing calculations for pipe sizes 4" thru 1/2", provide courtyard and planter drain detail and piping.
Routing - PLANNING3/7/2002 3/11/2002 FAIL
Approved by DAA on 3/7/02. Design Review pending per TKW.
Routing - PLANNING3/6/2002 3/7/2002 PEND
Approved as per CUP01-00120. Pending Design Review approval.
Routing - PUBLIC WORKS3/6/2002 3/6/2002 FAIL
Requires drainage plan. Need PW dewater agreement.
Routing - PLANNING Land Div2/26/2002 2/27/2002 PASS
Land division ok - parcel meets >5 acre exception to the Subdivision Ordinance. Routed to Public Works. (blc)
Plans ACCEPTED BY PLAN TECH  2/26/2002 DONE
Plan routing begun/NEW & ADDTN  2/26/2002  
Override - Parcel Holds  2/22/2002  
Override - Parcel Holds  2/22/2002  
Application received  2/22/2002  
Recd Pcfee & Taken To Pln CK  2/22/2002 DONE