BLD-Final | 3/11/2003 | 3/11/2003 | 3/11/2003 | P | PASS |
Tony Young
|
|
|
jeff ###-####
|
DOC - Permit Finaled | 3/11/2003 | 3/11/2003 | 3/11/2003 | P | PASS |
Tony Young
|
|
|
Finaled by inspector at 3/11/2003 1:52:56 PM
|
BLD-Final | 3/3/2003 | 3/4/2003 | 3/4/2003 | P | PART |
Tony Young
|
|
|
###-#### cory
need to insulate crawl, ducting, clean debris out,/// fire caulk firewall, finish spiral stairs, give verification on temp. glass in bath, etc.,,
finals on other permits 3/4/2003 4:37:39 PM
|
BLD-Grading Inspection | 3/3/2003 | 3/3/2003 | 3/3/2003 | | PASS |
Rita DeYoung
|
|
|
final grading and drainage approved
|
BLD-Conference | 2/25/2003 | 2/26/2003 | 2/26/2003 | A | PART |
Tony Young
|
|
|
###-#### cory
conf. on final 2/26/2003 11:04:20 AM
|
BLD-Framing/Rough-in | 10/22/2002 | 10/23/2002 | 10/23/2002 | A | PASS |
Tony Young
|
|
|
late am
|
BLD-Framing/Rough-in | 10/22/2002 | 10/22/2002 | 10/22/2002 | P | NR |
Tony Young
|
|
|
###-####
|
BLD-Framing/Rough-in | 10/15/2002 | 10/17/2002 | 10/17/2002 | A | NR |
Tony Young
|
|
|
###-####
|
BLD-Foundation | 10/16/2002 | 10/17/2002 | 10/17/2002 | A | PART |
Tony Young
|
|
|
outdoor inground spa rebar inspection ###-####
|
BLD-Framing/Rough-in | 10/17/2002 | 10/17/2002 | 10/17/2002 | P | PART |
Tony Young
|
|
|
c/n posted, ok to insulate 10/17/2002 4:25:26 PM
|
BLD-Framing/Rough-in | 9/17/2002 | 9/17/2002 | 9/17/2002 | P | FAIL |
Tony Young
|
|
|
fr insp cory -###-####--call 1st before insp
conf. only, ceiling lighting, need to be sealed units, listed, and installed per specs.,,, also ok to cover soffit areas 9/17/2002 4:00:22 PM
|
BLD-Wall cover | 7/23/2002 | 7/24/2002 | 7/24/2002 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 07/23/2002 at 14:31:37. Contact: ###-####.
ext shear ok 7/24/2002 12:00:55 PM
|
BLD-Wall cover | 7/22/2002 | 7/23/2002 | 7/23/2002 | A | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 07/22/2002 at 13:30:06. Contact: ###-####.
no plans onsite 7/23/2002 9:48:17 AM
|
BLD-Foundation | 4/26/2002 | 4/29/2002 | 4/29/2002 | A | PART |
Tony Young
|
|
|
###-#### BOB
wip 4/29/2002 11:09:09 AM
|
BLD-Footing | 4/24/2002 | 4/25/2002 | 4/25/2002 | A | PART |
Tony Young
|
|
|
ft insp- bob- ###-####
|
BLD-Grading Inspection | 4/25/2002 | 4/25/2002 | 4/25/2002 | | DONE |
Rita DeYoung
|
|
|
Foundation subgrade has been approved by the engineer.
|
Issue PAID IN FULL permit | | | 3/18/2002 | | DONE |
|
|
|
|
Plan assigned to (DJO) | 3/14/2002 | 3/14/2002 | 3/14/2002 | | PASS |
Dan Overy
|
|
|
3/14/2002 11:45:41 DJO - activity updated through activity BLDA022 from case BLD02-00402.
|
Case Summary (BLD) | | | 3/14/2002 | | DONE |
|
|
|
|
Plan Review Report | | | 3/14/2002 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/14/2002 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 3/14/2002 | | DONE |
|
|
|
only one kitchen allowed per planning/zoning and signature by owner.
|
Inspection Record Card- Bld | | | 3/14/2002 | | DONE |
|
|
|
|
Telephone call | | | 3/14/2002 | | DONE |
|
|
|
PERMIT READY
|
Plans ACCEPTED BY PLAN CHECK | | | 3/14/2002 | | |
|
|
|
|
Routing - FIRE | 3/7/2002 | | 3/7/2002 | | DONE |
|
|
|
No fire sprinklers are required for Arrowhead Canyon subdivision.
|
Routing - PUBLIC WORKS | 3/5/2002 | | 3/5/2002 | | PASS |
|
|
|
|
Routing - PLANNING | 3/5/2002 | | 3/5/2002 | | FAIL |
|
|
|
House, deck, stairs may not be built in 10 ft easement. Called Robert Chavez. He will bring new site plan. Also, 2nd cooktop in wetbar must be removed, not approved as duplex.
|
Routing - PUBLIC WORKS GRADING | 3/4/2002 | 3/4/2002 | 3/4/2002 | | PASS |
Rita DeYoung
|
|
|
Approved as category 3 with conditions of approval in letter attached to plans
|
Routing - PUBLIC WORKS GRADING | 2/26/2002 | | 2/27/2002 | | FAIL |
Rita DeYoung
|
|
|
Roof Drain stubout shown in wrong location. Talked to Strata about revising.
|
Application received | | | 2/26/2002 | | |
|
|
|
|
Routing - PLANNING | 3/7/2002 | 3/7/2002 | | | PASS |
|
|
|
New site plan, house and deck moved out of 10 ft. easement, stairs up to deck removed. 2nd cooktop removed per Robert Chavez.
|
Pending Assignment by DJO | 2/26/2002 | | | | |
Dan Overy
|
|
|
|
Routing - PLAN CHECK | 3/7/2002 | | | | |
|
|
|
|