BLD-Final | 5/3/2002 | 5/6/2002 | 5/6/2002 | P | PASS |
Jim Sly
|
|
|
###-#### C/C issued. 5/6/2002 1:14:25 PM
|
DOC - Permit Finaled | 5/6/2002 | 5/6/2002 | 5/6/2002 | P | PASS |
Jim Sly
|
|
|
Finaled by inspector at 5/6/2002 1:14:38 PM
|
BLD-Framing/Rough-in | 3/29/2002 | 4/1/2002 | 4/1/2002 | A | FAIL |
Jim Sly
|
|
|
###-#### DAVE C/N posted. 4/1/2002 9:27:51 AM
|
BLD-Framing/Rough-in | 4/1/2002 | 4/1/2002 | 4/1/2002 | P | PASS |
Jim Sly
|
|
|
dave ###-#### fr
|
BLD-Energy code compliance | 4/1/2002 | 4/1/2002 | 4/1/2002 | P | PASS |
Jim Sly
|
|
|
dave ###-#### energy code
|
BLD-Framing/Rough-in | 3/28/2002 | 3/29/2002 | 3/29/2002 | P | FAIL |
Dave Hannah
|
|
|
###-#### DAVE no plans or truss engin on site 3/29/2002 4:27:36 PM
|
BLD-Foundation | 3/13/2002 | 3/14/2002 | 3/14/2002 | A | PASS |
Jim Sly
|
|
|
eric- ###-#### found wall
|
BLD-Footing | 3/13/2002 | 3/13/2002 | 3/13/2002 | P | PART |
Jim Sly
|
|
|
ft insp eric- ###-####
|
Issue PAID IN FULL permit | | | 3/12/2002 | | |
|
|
|
|
Plan assigned to (PEP) | 3/1/2002 | | 3/11/2002 | | PASS |
Perry Paine
|
|
|
3/11/2002 11:33:28 PEP - activity updated through activity BLDA022 from case BLD02-00424.
|
Plan assigned to (PEP) | 3/11/2002 | | 3/11/2002 | | PASS |
Perry Paine
|
|
|
3/11/2002 11:33:28 PEP - activity updated through activity BLDA022 from case BLD02-00424.
|
Inspector's copy Bld permit | | | 3/11/2002 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/11/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/11/2002 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/11/2002 | | |
|
|
|
|
Routing - PUBLIC WORKS | 3/5/2002 | | 3/5/2002 | | PASS |
|
|
|
|
Routing - PLANNING | 3/1/2002 | | 3/4/2002 | | PASS |
|
|
|
|
Application received | | | 3/1/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/5/2002 | | | | |
|
|
|
|