BLD-Final | 1/21/2003 | 1/21/2003 | 1/21/2003 | P | PASS |
Tony Young
|
|
|
|
DOC - Permit Finaled | 1/21/2003 | 1/21/2003 | 1/21/2003 | P | PASS |
Tony Young
|
|
|
Finaled by inspector at 1/21/2003 3:31:57 PM
|
BLD-Final | 1/16/2003 | 1/17/2003 | 1/17/2003 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
some corrections being worked on, will ck later 1/17/2003 1:06:21 PM
|
BLD-Final | 1/17/2003 | 1/17/2003 | 1/17/2003 | P | CANC |
Tony Young
|
|
|
|
BLD-Grading Inspection | 1/17/2003 | 1/17/2003 | 1/17/2003 | | PASS |
Rita DeYoung
|
|
|
Final grading and drainage conditionally approved with submission of $900.00 bond for incomplete fine grading and revegetation.
|
CHANGE STATUS TO (ISS) | | | 1/17/2003 | | DONE |
|
|
|
|
BLD-Conference | 11/14/2002 | 11/15/2002 | 11/15/2002 | P | DONE |
Steven Webb
|
|
|
###-#### or ###-#### Wai Ng (pronounced Y Ing) call first to meet there
|
BLD-Framing/Rough-in | 10/11/2002 | 10/14/2002 | 10/14/2002 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoungenergy code ok also 10/14/2002 11:29:03 AM
|
BLD-Framing/Rough-in | 10/7/2002 | 10/7/2002 | 10/7/2002 | P | PART |
Tony Young
|
|
|
###-####
c/n posted, ok to insulate 10/7/2002 3:10:31 PM
|
BLD-Framing/Rough-in | 10/1/2002 | 10/1/2002 | 10/1/2002 | P | NR |
Tony Young
|
|
|
scott-shear wall ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Footing | 7/10/2002 | 7/10/2002 | 7/10/2002 | P | PART |
Tony Young
|
|
|
###-####
int ftg 7/10/2002 3:59:46 PM
|
BLD-Foundation | 6/17/2002 | 6/18/2002 | 6/18/2002 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 06/17/2002 at 17:36:42. Contact: ###-####.
|
BLD-Foundation | 6/12/2002 | 6/13/2002 | 6/13/2002 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 06/12/2002 at 13:19:41. Contact: ###-####. All walls appear OK....Except approx 15 - 20' retaining wall. 6/13/2002 10:14:00 AM
|
BLD-Footing | 6/6/2002 | 6/6/2002 | 6/6/2002 | P | PART |
Tony Young
|
|
|
mike ###-#### ft
wip 6/6/2002 3:28:26 PM
|
BLD-Footing | 6/4/2002 | 6/5/2002 | 6/5/2002 | P | NR |
Tony Young
|
|
|
ft insp mike- ###-####
|
Issue PAID IN FULL permit | | | 5/15/2002 | | DONE |
|
|
|
|
Plan assigned to (DJO) | 5/8/2002 | 5/8/2002 | 5/10/2002 | | PASS |
Dan Overy
|
|
|
5/10/2002 11:13:58 DJO - activity updated through activity BLDA022 from case BLD02-00541.
|
Plan Reviewer's activity | | | 5/10/2002 | | DONE |
|
|
|
recieved information requested. ok to issue.
|
Case Summary (BLD) | | | 5/10/2002 | | DONE |
|
|
|
|
Plan Review Report | | | 5/10/2002 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/10/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/10/2002 | | |
|
|
|
|
Print Occupancy Form | | | 5/10/2002 | | |
|
|
|
|
Telephone call | | | 5/10/2002 | | DONE |
|
|
|
left mess that permit is ready
|
Plan Reviewer's activity | | | 5/8/2002 | | PEND |
|
|
|
will issue permit when plan addendums addressing natural light and exiting from third level are received.
|
Plans ACCEPTED BY PLAN CHECK | | | 5/8/2002 | | |
|
|
|
|
Plan Reviewer's activity | | | 4/30/2002 | | DONE |
|
|
|
No Fire sprinklers required per Dave Miller.
|
Routing - FIRE | 4/24/2002 | | 4/24/2002 | | PEND |
|
|
|
No information on file for this location. Reqested from Dave Miller. Holding plans pending reply from Dave Miller.
|
Routing - PLANNING | 4/8/2002 | | 4/24/2002 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 4/8/2002 | | 4/8/2002 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 4/5/2002 | 4/5/2002 | 4/5/2002 | | PASS |
Rita DeYoung
|
|
|
Approved as Category 1 with conditions of approval in letter attached to plan
|
Routing - PUBLIC WORKS GRADING | 3/14/2002 | | 3/19/2002 | | FAIL |
Rita DeYoung
|
|
|
Driveway grading not indicated on plan, soils report doesnt require benched fill on slope.
|
Application received | | | 3/14/2002 | | |
|
|
|
|
Pending Assignment by DJO | 3/14/2002 | | | | |
Dan Overy
|
|
|
|
Routing - PLAN CHECK | 4/30/2002 | | | | |
|
|
|
|