BLD-Final | 6/5/2002 | 6/5/2002 | 6/5/2002 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 06/05/2002 at 06:59:53. Contact: ###-####. C/C issued. 6/5/2002 11:55:36 AM
|
DOC - Permit Finaled | 6/5/2002 | 6/5/2002 | 6/5/2002 | P | PASS |
Jim Sly
|
|
|
Finaled by inspector at 6/5/2002 11:55:19 AM
|
BLD-Energy code compliance | 5/1/2002 | 5/1/2002 | 5/1/2002 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 05/01/2002 at 06:55:54. Contact: ###-####.
|
BLD-Framing/Rough-in | 4/29/2002 | 4/29/2002 | 4/29/2002 | P | PASS |
Jim Sly
|
|
|
###-#### JOHN
|
BLD-Foundation | 4/5/2002 | 4/5/2002 | 4/5/2002 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 04/05/2002 at 05:57:53. Contact: ###-####.
|
BLD-Footing | 4/3/2002 | 4/3/2002 | 4/3/2002 | P | PART |
Jim Sly
|
|
|
###-####
|
Issue PAID IN FULL permit | | | 4/1/2002 | | DONE |
|
|
|
|
Plan assigned to (PEP) | 3/18/2002 | | 3/28/2002 | | PASS |
Perry Paine
|
|
|
3/28/2002 08:47:46 PEP - activity updated through activity BLDA022 from case BLD02-00580.
|
Inspector's copy Bld permit | | | 3/28/2002 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/28/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/28/2002 | | DONE |
|
|
|
|
Telephone call | | | 3/28/2002 | | DONE |
|
|
|
CALLED LEFT MESSAGE PLANS READY 3-28-02 //DLD
|
Routing - PLANNING | 3/18/2002 | | 3/19/2002 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 3/19/2002 | | 3/19/2002 | | PASS |
|
|
|
|
Application received | | | 3/18/2002 | | |
|
|
|
|
Routing - PLAN CHECK | 3/19/2002 | | | | |
|
|
|
|