Agreement of Future work | 8/7/2002 | 1/1/2007 | 3/22/2010 | | DONE |
Scott Arellano
|
|
|
Applicant agrees to complete fire alqarm system upgrade to entire bldg by Jan 2007
|
BLD-Final | 7/26/2002 | 7/29/2002 | 7/29/2002 | A | PART |
Tom Arcoraci
|
|
|
jeremy; Phone #: ###-#### bathrooms behind eleavator shaft not complete 7/29/2002 2:19:19 PM
|
FIRE-Final Inspection | 7/25/2002 | 7/26/2002 | 7/26/2002 | P | PASS |
Rick Jackson
|
|
|
CALL PAUL AT ###-#### GO AFTER 2:00 PLEASE
|
FIRE-Final Inspection | 7/23/2002 | 7/25/2002 | 7/25/2002 | A | FAIL |
Rick Jackson
|
|
|
call paul ###-#### need fire alarm approval prior to occupancy 7/25/2002 9:57:20 AM
|
BLD-Final | 7/23/2002 | 7/25/2002 | 7/25/2002 | P | CANC |
Carl Dependahl
|
|
|
call Paul first ###-#### paul, called to canc this inspection not ready yet
|
BLD-Conference | 6/7/2002 | 6/7/2002 | 6/7/2002 | A | PASS |
Carl Dependahl
|
|
|
w/ ISI re frame insp...provide continuous studs at added tall wall, or equal...ok to continue
|
BLD-Framing/Rough-in | 6/5/2002 | 6/6/2002 | 6/6/2002 | A | FAIL |
Carl Dependahl
|
|
|
###-#### complete firestops at plbg penetrations at floor...see c/n. verify sprinkler r/i ok...ok to rock as noted. 6/6/2002 12:02:17 PM
|
BLD-Framing/Rough-in | 6/5/2002 | 6/6/2002 | 6/6/2002 | A | FAIL |
Carl Dependahl
|
|
|
###-#### complete firestops at plbg penetrations at floor...see c/n. verify sprinkler r/i ok...ok to rock as noted. 6/6/2002 12:02:17 PM
|
BLD-Framing/Rough-in | 6/6/2002 | 6/6/2002 | 6/6/2002 | P | PART |
Carl Dependahl
|
|
|
firestops at floor ok 6/6/2002 3:33:26 PM
|
BLD-Framing/Rough-in | 6/6/2002 | 6/6/2002 | 6/6/2002 | P | PART |
Carl Dependahl
|
|
|
keep c/n ...ok to cover int walls...chk kickers at next insp...floor firestops, straps ok 6/7/2002 11:22:58 AM
|
Inspection Record Card- Bld | | | 5/17/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/17/2002 | | DONE |
|
|
|
|
Telephone call | | | 5/17/2002 | | DONE |
|
|
|
CALLED BOB PLANS READY 5-17-02 ///DLD
|
Issue PAID IN FULL permit | | | 5/17/2002 | | |
|
|
|
|
Plan assigned to (CJW) | 3/22/2002 | | 5/16/2002 | | PASS |
Carl Westfall
|
|
|
5/16/2002 13:27:58 CJW - activity updated through activity BLDA022 from case BLD02-00595.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/16/2002 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/18/2002 | | 5/16/2002 | | PASS |
|
|
|
Drawings approved with conditions.
|
Plan resubmittals received | | | 5/15/2002 | | DONE |
|
|
|
Received two copies of revised sheet A1.0. Routed to Carl W. kmm
|
Routing - FIRE | 4/11/2002 | | 4/18/2002 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 4/18/2002 | | |
|
|
|
Failed first UBC review.
|
Routing - PLAN CHECK | 3/26/2002 | | 4/11/2002 | | |
|
|
|
Failed first UBC review. UBC plan review started April 8, 2002 and finished April 11, 2002. Resubmitted drawings were required from the architect. See the conditions list. A copy of the plan review report was sent to the architect.
|
Routing - PUBLIC WORKS | 3/22/2002 | | 3/26/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/21/2002 | | DONE |
|
|
|
1. Plans not fully dimensioned.
2. No key plan.
|
Application received | | | 3/20/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/20/2002 | | DONE |
|
|
|
|
Fee Review-notes | 3/20/2002 | 3/20/2002 | | | |
|
|
|
|