BLD-Final | 4/9/2003 | 4/9/2003 | 4/9/2003 | P | PASS |
Carl Dependahl
|
|
|
work finalled w/ T/I for "deli"...ok for l/c. 4/9/2003 1:45:08 PM
|
DOC - Permit Finaled | 4/9/2003 | 4/9/2003 | 4/9/2003 | P | PASS |
Carl Dependahl
|
|
|
Finaled by inspector at 4/9/2003 1:45:10 PM
|
BLD-Final | 6/28/2002 | 7/1/2002 | 7/1/2002 | A | NR |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 5/13/2002 | 5/14/2002 | 5/14/2002 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/13/2002 at 16:59:16. Contact: ###-####. demising wall ok; seal firestop penetrations after gyp installed. 5/14/2002 5:00:49 PM
|
BLD-Conference | 5/14/2002 | 5/14/2002 | 5/14/2002 | P | PASS |
Carl Dependahl
|
|
|
need braces at t.o.w...repair studs cut for plbg pipes
|
Issue PAID IN FULL permit | | | 4/11/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/5/2002 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 3/25/2002 | | 4/5/2002 | | PASS |
Carl Westfall
|
|
|
4/5/2002 07:57:02 CJW - activity updated through activity BLDA022 from case BLD02-00634.
|
Routing - PLAN CHECK | 4/3/2002 | | 4/4/2002 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/4/2002 | | PASS |
|
|
|
|
Routing - FIRE | 3/28/2002 | 4/2/2002 | 4/3/2002 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 4/3/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/27/2002 | | 3/28/2002 | | PASS |
|
|
|
UBC plan review started March 27, 2002 and finished the next day. The drawings were approved with conditions. See the conditions list.
|
Routing - PUBLIC WORKS | 3/25/2002 | | 3/27/2002 | | |
|
|
|
|
First Notice | 3/22/2002 | 3/22/2002 | 3/22/2002 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/22/2002 | | DONE |
|
|
|
|
Application received | | | 3/22/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/22/2002 | | DONE |
|
|
|
|