Fee Review-notes | 3/22/2002 | 3/22/2002 | 4/21/2004 | | DONE |
|
|
|
|
DOC - Permit Finaled | | | 8/18/2003 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/20/2002 | 8/21/2002 | 8/21/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled 8/21/2002 11:59:45 AM
|
BLD-Final | 8/21/2002 | 8/21/2002 | 8/21/2002 | P | PASS |
Dave Hannah
|
|
|
ok for perm occ.
|
FIRE-Final Inspection | 8/19/2002 | 8/20/2002 | 8/20/2002 | A | FAIL |
Troy Cobbley
|
|
|
duct detectors are mounted outside with no proof that they are listed for outdoor use. Contractor said they would provide the listing. Duct detectors still need to be tested 8/20/2002 12:14:14 PM
|
FIRE-Final Inspection | 8/19/2002 | 8/20/2002 | 8/20/2002 | A | FAIL |
Troy Cobbley
|
|
|
duct detectors are mounted outside with no proof that they are listed for outdoor use. Contractor said they would provide the listing. Duct detectors still need to be tested 8/20/2002 12:14:14 PM
|
BLD-Final | 8/19/2002 | 8/20/2002 | 8/20/2002 | P | NR |
Dave Hannah
|
|
|
###-#### JOHN needs fire life safty sign off 8/20/2002 4:37:21 PM
|
BLD-Framing/Rough-in | 5/15/2002 | 5/15/2002 | 5/15/2002 | P | FAIL |
Dave Hannah
|
|
|
###-#### john needs fire blocki in firred out walls 5/15/2002 4:06:40 PM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/30/2002 | | PASS |
|
|
|
To permit desk to issue.
|
Inspection Record Card- Bld | | | 4/30/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/30/2002 | | DONE |
|
|
|
|
Telephone call | | | 4/30/2002 | | DONE |
|
|
|
CALLED PLANS READY 4-29-02 ///DLD
|
Issue PAID IN FULL permit | | | 4/30/2002 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 3/25/2002 | | 4/30/2002 | | PASS |
Dan Stuart
|
|
|
4/30/2002 13:41:21 DRS - activity updated through activity BLDA022 from case BLD02-00645.
|
Routing - PLAN CHECK | 4/29/2002 | | 4/30/2002 | | PASS |
|
|
|
Approved as noted and attached
|
Routing - FIRE | 4/24/2002 | 4/29/2002 | 4/29/2002 | | PASS |
Bill Alexander
|
|
|
|
Plan resubmittals received | | | 4/29/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets A1, a1.1, a1.2, cabinet elevations, and damper details, with transmittal. Routed to Dan Stuart.
|
Plan Review Completed(1st rev) | | | 4/29/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/18/2002 | | 4/24/2002 | | FAIL |
|
|
|
Resubmittals required. Route to fire code analyst for review.
|
Plan resubmittals requested | | | 4/24/2002 | | FAIL |
|
|
|
Copy of plan review report and re-submittals request faxed and mailed to architect.
|
Routing - PLUMBING | 4/15/2002 | 4/15/2002 | 4/18/2002 | | PASS |
|
|
|
per resubmitted A1.3 dated 4/3/02 and 2000 upc.
|
Routing - PLAN CHECK | 3/28/2002 | | 4/15/2002 | | |
|
|
|
Plumbing resubmittals received. Inserted into plans and routed back to plumbing div. for re-review.
|
Plan resubmittals received | | | 4/3/2002 | | DONE |
|
|
|
Received two copies of resubmittal sheets A1.3 with cover letter. Routed to Dan Stuart.
|
Routing - PLUMBING | 3/26/2002 | | 3/28/2002 | | FAIL |
|
|
|
please provide a diagram of the water system for this project, note type of existing toilets for sizing verification, note location of tenant isolation valve, thermol expantion protection, premise cross connection protection if required, and pipe sizing.
|
Routing - PUBLIC WORKS | 3/25/2002 | | 3/26/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/25/2002 | | DONE |
|
|
|
|
Application received | | | 3/22/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/22/2002 | | |
|
|
|
|