BLD-Final | 8/29/2002 | 8/30/2002 | 8/30/2002 | A | FAIL |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 08/29/2002 at 10:38:25. Contact: ###-####. C/N on site. 8/30/2002 10:23:46 AM
|
BLD-Final | 8/30/2002 | 8/30/2002 | 8/30/2002 | P | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 08/30/2002 at 10:49:27. Contact: ###-####. C. of C. #22459 issued. 8/30/2002 2:29:15 PM
|
DOC - Permit Finaled | 8/30/2002 | 8/30/2002 | 8/30/2002 | P | PASS |
Steven Webb
|
|
|
Finaled by inspector at 8/30/2002 2:29:22 PM
|
BLD-Energy code compliance | 7/8/2002 | 7/9/2002 | 7/9/2002 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 14:59:41. Contact: ###-####.
|
BLD-Framing/Rough-in | 7/9/2002 | 7/9/2002 | 7/9/2002 | A | PASS |
Jim Storey
|
|
|
c/n made ok
|
BLD-Framing/Rough-in | 7/2/2002 | 7/3/2002 | 7/3/2002 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 07/02/2002 at 14:40:40. Contact: ###-####. ok to insulate after mec r/i c/n on site shear ok to cover ext 7/3/2002 2:37:17 PM
|
BLD-Wall cover | 6/25/2002 | 6/26/2002 | 6/26/2002 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 06/25/2002 at 12:24:03. Contact: ###-####. 6/26/2002 Shear--Ext. ok--Interior shear needed per approved plans 6/26/2002 11:40:55 AM
|
BLD-Wall cover | 6/24/2002 | 6/25/2002 | 6/25/2002 | A | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/24/2002 at 14:51:17. Contact: ###-####. no approved plans on site will recall. 6/25/2002 3:19:57 PM
|
BLD-Foundation | 6/3/2002 | 6/4/2002 | 6/4/2002 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 06/03/2002 at 15:00:30. Contact: ###-####. No approved plans--rebar in walls per non-approved plans--pour at own risk 6/4/2002 9:20:06 AM
|
Case Summary (BLD) | | | 6/4/2002 | | |
|
|
|
|
Plan Review Report | | | 6/4/2002 | | |
|
|
|
|
(F) Reprint permit | | | 6/4/2002 | | DONE |
|
|
|
|
BLD-Foundation | 6/3/2002 | 6/3/2002 | 6/3/2002 | P | NR |
Steven Webb
|
|
|
found wall- mike ###-#### Contacted builder-will re-schedule. 6/3/2002 4:26:50 PM
|
BLD-Footing | 5/29/2002 | 5/30/2002 | 5/30/2002 | A | FAIL |
Dave Hannah
|
|
|
###-#### RANDY needs to resubmit plans plans that footing crew is useing has changed from what city approved crew is going to pour at own risk check setbacks they look ok 5/30/2002 10:46:45 AM
|
BLD-Footing | 5/29/2002 | 5/30/2002 | 5/30/2002 | A | PART |
Dave Hannah
|
|
|
###-#### RANDY builder has changed lay out of house needs to resubmit plans contractor will pour footing at own risk 5/30/2002 10:18:48 AM
|
BLD-Final | 5/30/2002 | 5/30/2002 | 5/30/2002 | P | CANC |
Steven Webb
|
|
|
###-#### MIKE
|
Issue PAID IN FULL permit | | | 5/22/2002 | | |
|
|
|
|
CHANGE ISSUED DATE | | | 5/22/2002 | | DONE |
|
|
|
|
Plan assigned to (DJO) | 4/3/2002 | 4/3/2002 | 4/3/2002 | | PASS |
Dan Overy
|
|
|
4/3/2002 10:35:27 DJO - activity updated through activity BLDA022 from case BLD02-00669.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/3/2002 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/3/2002 | | DONE |
|
|
|
|
Plan Review Report | | | 4/3/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/3/2002 | | DONE |
|
|
|
|
Telephone call | | | 4/3/2002 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 4/3/2002 | | |
|
|
|
|
Routing - PUBLIC WORKS | 3/28/2002 | | 3/28/2002 | | PASS |
|
|
|
|
Routing - PLANNING | 3/26/2002 | | 3/27/2002 | | PASS |
|
|
|
|
Pending Assignment by DJO | 3/26/2002 | | | | |
Dan Overy
|
|
|
|
Routing - PLAN CHECK | 3/28/2002 | | | | |
|
|
|
|