BLD-Final | 10/17/2002 | 10/18/2002 | 10/18/2002 | A | PASS |
Tom Arcoraci
|
|
|
after 10:00 am; Phone #: ###-#### Internet Inspection Request from: Amy Lawson
|
DOC - Permit Finaled | 10/18/2002 | 10/18/2002 | 10/18/2002 | A | PASS |
Tom Arcoraci
|
|
|
Finaled by inspector at 10/18/2002 10:05:26 AM
|
BLD-Framing/Rough-in | 9/25/2002 | 9/26/2002 | 9/26/2002 | A | DONE |
Steven Webb
|
|
|
hand rail- rick ###-#### Conference not framing. 9/26/2002 10:29:06 AM
|
BLD-Conference | 9/10/2002 | 9/10/2002 | 9/10/2002 | A | PART |
Carl Dependahl
|
|
|
need to provide access for underfloor furnace; firebox side is "turned away" and is not accessible for service/filters etc....
|
BLD-Energy code compliance | 7/12/2002 | 7/15/2002 | 7/15/2002 | A | PASS |
Steven Webb
|
|
|
###-####
|
BLD-Framing/Rough-in | 7/10/2002 | 7/11/2002 | 7/11/2002 | A | PASS |
Steven Webb
|
|
|
BEHIND THE FIREPLACE CARDBOARD ARE THE PLANS AND ENGINEERING FOR SAFEKEEPING PLEASE CALL STEVE ###-#### PRIOR Prior c/n items corrected--engineer signed off for the (2) 9" microlam under stairs to bonus room. 7/11/2002 8:53:15 AM
|
BLD-Framing/Rough-in | 7/3/2002 | 7/5/2002 | 7/5/2002 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/03/2002 at 13:32:58. Contact: ###-####. C/N posted. 7/5/2002 11:25:44 PM
|
BLD-Framing/Rough-in | 6/21/2002 | 6/24/2002 | 6/24/2002 | A | NR |
Steven Webb
|
|
|
STEVE ###-#### SHEER NAIL
|
BLD-Wall cover | 6/24/2002 | 6/24/2002 | 6/24/2002 | P | PART |
Dave Hannah
|
|
|
Scheduled by Inspector: 420 On 6/24/2002 10:34:14 AM shear nail ok to cover ext garage headers ok contractor wants to cover back side with osb 6/24/2002 4:04:33 PM
|
BLD-Wall cover | 6/24/2002 | 6/24/2002 | 6/24/2002 | P | PART |
Dave Hannah
|
|
|
Scheduled by Inspector: 420 On 6/24/2002 10:34:14 AM shear nail ok to cover ext garage headers ok contractor wants to cover back side with osb 6/24/2002 4:04:33 PM
|
BLD-Wall cover | 6/24/2002 | 6/24/2002 | 6/24/2002 | P | PART |
Dave Hannah
|
|
|
Scheduled by Inspector: 420 On 6/24/2002 10:34:14 AM shear nail ok to cover ext garage headers ok contractor wants to cover back side with osb 6/24/2002 4:04:33 PM
|
BLD-Wall cover | 6/24/2002 | 6/24/2002 | 6/24/2002 | P | PART |
Dave Hannah
|
|
|
Scheduled by Inspector: 420 On 6/24/2002 10:34:14 AM shear nail ok to cover ext garage headers ok contractor wants to cover back side with osb 6/24/2002 4:04:33 PM
|
BLD-Wall cover | 6/24/2002 | 6/24/2002 | 6/24/2002 | P | PART |
Dave Hannah
|
|
|
Scheduled by Inspector: 420 On 6/24/2002 10:34:14 AM shear nail ok to cover ext garage headers ok contractor wants to cover back side with osb 6/24/2002 4:04:33 PM
|
BLD-Wall cover | 6/24/2002 | 6/24/2002 | 6/24/2002 | P | PART |
Dave Hannah
|
|
|
Scheduled by Inspector: 420 On 6/24/2002 10:34:14 AM shear nail ok to cover ext garage headers ok contractor wants to cover back side with osb 6/24/2002 4:04:33 PM
|
BLD-Foundation | 4/12/2002 | 4/12/2002 | 4/12/2002 | P | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 04/12/2002 at 08:31:55. Contact: ###-####. wip 4/12/2002 2:59:34 PM
|
BLD-Footing | 4/9/2002 | 4/10/2002 | 4/10/2002 | A | PART |
Steven Webb
|
|
|
###-#### steve wip 4/10/2002 11:30:14 AM
|
BLD-Footing | 4/9/2002 | 4/9/2002 | 4/9/2002 | P | FAIL |
Steven Webb
|
|
|
###-#### Setback not per approved plans. 4/9/2002 3:26:51 PM
|
Print Pending Permit.LaserJet4 | | | 4/9/2002 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/9/2002 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/9/2002 | | DONE |
|
|
|
|
Pending Assignment by DJO | 3/26/2002 | | 4/8/2002 | | DONE |
Dan Overy
|
|
|
|
Routing - PLAN CHECK | 3/28/2002 | | 4/8/2002 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 4/8/2002 | | |
|
|
|
|
Plan Review Report | | | 4/8/2002 | | |
|
|
|
|
Plan Reviewer's activity | | | 4/8/2002 | | PEND |
|
|
|
Only one set of plans is being approved due to excessive redlining.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/8/2002 | | DONE |
|
|
|
|
Telephone call | | | 4/8/2002 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 3/28/2002 | | 3/28/2002 | | PASS |
|
|
|
|
Routing - PLANNING | 3/26/2002 | | 3/27/2002 | | PASS |
|
|
|
|
Application received | | | 3/26/2002 | | |
|
|
|
|