BLD-Final | 9/18/2002 | 9/19/2002 | 9/19/2002 | A | PASS |
Tony Young
|
|
|
###-####
|
DOC - Permit Finaled | 9/19/2002 | 9/19/2002 | 9/19/2002 | P | PASS |
Tony Young
|
|
|
Finaled by inspector at 9/19/2002 11:49:47 AM
|
Case Summary (BLD) | | | 9/19/2002 | | DONE |
|
|
|
|
BLD-Final | 9/16/2002 | 9/17/2002 | 9/17/2002 | A | FAIL |
Tony Young
|
|
|
keith; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
walk through only, need trades, insulation under floor, firecaulking, achd 9/17/2002 11:07:14 AM
|
BLD-Energy code compliance | 7/12/2002 | 7/15/2002 | 7/15/2002 | A | PASS |
Tony Young
|
|
|
KEVIN ###-####--
|
BLD-Framing/Rough-in | 7/10/2002 | 7/11/2002 | 7/11/2002 | A | PASS |
Tony Young
|
|
|
ok to insulate, c/n posted 7/11/2002 12:29:50 PM
|
BLD-Energy code compliance | 7/10/2002 | 7/11/2002 | 7/10/2002 | P | CANC |
Tony Young
|
|
|
###-#### late pm--cancel per kevin
|
BLD-Framing/Rough-in | 7/8/2002 | 7/10/2002 | 7/10/2002 | A | FAIL |
Tony Young
|
|
|
fr insp- ###-#### kevin
c/n posted 7/10/2002 12:45:46 PM
|
BLD-Framing/Rough-in | 7/10/2002 | 7/10/2002 | 7/10/2002 | P | FAIL |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 6/26/2002 | 6/27/2002 | 6/27/2002 | A | PART |
Tom Arcoraci
|
|
|
SHEER NAIL KEITH ###-#### ok to side 6/27/2002 9:56:59 AM
|
BLD-Framing/Rough-in | 6/10/2002 | 6/11/2002 | 6/11/2002 | A | PART |
Carl Dependahl
|
|
|
KEITH ###-#### FIRE WALL INSPECTION... extend gyp to front wall at jog....attic truss gypped...( on ground, need insp as installed.) 6/11/2002 11:33:17 AM
|
BLD-Framing/Rough-in | 6/6/2002 | 6/7/2002 | 6/7/2002 | A | FAIL |
Tony Young
|
|
|
fire wall -###-####- keith
need to redo to townhouse specs 6/7/2002 10:30:22 AM
|
BLD-Other | 6/7/2002 | 6/7/2002 | 6/7/2002 | P | PART |
Tony Young
|
|
|
firewall
lower firewalls ok to stand, need to verify nailing on outside of walls later, and attic front and back 6/7/2002 12:41:23 PM
|
BLD-Foundation | 5/29/2002 | 5/30/2002 | 5/30/2002 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 05/29/2002 at 18:06:31. Contact: ###-####.
wip 5/30/2002 12:19:40 PM
|
BLD-Foundation | 5/29/2002 | 5/29/2002 | 5/29/2002 | P | PART |
Tony Young
|
|
|
###-#### KEITH
|
Issue PAID IN FULL permit | | | 5/21/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/11/2002 | | DONE |
|
|
|
|
Telephone call | | | 4/11/2002 | | DONE |
|
|
|
SPOKE WITH RACHAEL GILBERT PERMIT READY AND FEE
|
Plan assigned to (DJO) | 4/5/2002 | 4/5/2002 | 4/10/2002 | | PASS |
Dan Overy
|
|
|
4/10/2002 16:24:11 DJO - activity updated through activity BLDA022 from case BLD02-00676.
|
Plan Reviewer's activity | | | 4/10/2002 | | DONE |
|
|
|
received truss engineering. parcel tag has been lifted. ok to issue
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/10/2002 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/9/2002 | | PEND |
|
|
|
|
Plan Review Report | | | 4/9/2002 | | PEND |
|
|
|
|
Plan Reviewer's activity | | | 4/5/2002 | | PEND |
|
|
|
have left message for both rachel gilbert and contractor (cornerstone builders). land division needs additional info before issuance of permit. all glu-lam beams will calculations for loads and footing sizes. carport beams and garage headers fail
|
Plans ACCEPTED BY PLAN CHECK | | | 4/5/2002 | | |
|
|
|
|
Routing - PUBLIC WORKS | 3/27/2002 | | 3/28/2002 | | PASS |
|
|
|
|
Routing - PLANNING | 3/26/2002 | | 3/27/2002 | | PASS |
|
|
|
|
Application received | | | 3/26/2002 | | |
|
|
|
|
Pending Assignment by DJO | 3/26/2002 | | | | |
Dan Overy
|
|
|
|
Routing - PLAN CHECK | 3/28/2002 | | | | |
|
|
|
|