Fee Review-notes | 7/22/2003 | 7/22/2003 | 7/22/2003 | | DONE |
|
|
|
|
Permanent Occupancy | | 12/23/2002 | 12/23/2002 | | DONE |
|
|
|
|
BLD-Final | 12/20/2002 | 12/23/2002 | 12/23/2002 | A | PASS |
Russ Owen
|
|
|
Don, ###-####Ok for a permanent oc. 12/23/2002 9:25:12 AM
|
Permanent occupancy | | | 12/23/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9490 issued 12-23-02 to Capital One.
|
FIRE-Alarm Testing | 12/19/2002 | 12/20/2002 | 12/20/2002 | P | PASS |
Troy Cobbley
|
|
|
fire life safety finaled 12/20/2002 2:23:21 PM
|
BLD-Final | 11/12/2002 | 11/12/2002 | 11/12/2002 | P | PART |
Russ Owen
|
|
|
Don Bryan, ###-####. needs fire/life safety before a perm oc. 11/12/2002 3:35:56 PM
|
FIRE-Final Inspection | 10/22/2002 | 10/23/2002 | 10/23/2002 | P | FAIL |
Troy Cobbley
|
|
|
provide a/v's in the storage turned conference rooms, relocate new duct detectors to the supply side of the duct and get the supervisory signals to the central station figured out 10/24/2002 11:07:20 AM
|
FIRE-Sprinkler Rough-in | 8/13/2002 | 8/14/2002 | 8/14/2002 | A | FAIL |
Troy Cobbley
|
|
|
This inspection was done under FIR02-00215 but I left a correction notice for the addition of duct detectors, per review notes 3 and 18, per Don the general contractors request 8/14/2002 8:51:42 AM
|
FIRE-Conference | 8/9/2002 | 8/13/2002 | 8/13/2002 | A | DONE |
Troy Cobbley
|
|
|
I went over the fire life safety notes with the contractor 8/13/2002 11:19:28 AM
|
BLD-Framing/Rough-in | 5/31/2002 | 6/3/2002 | 6/3/2002 | P | PART |
Russ Owen
|
|
|
Don, ###-####. needs electrical and braces at top walls. 6/3/2002 4:56:46 PM
|
Issue PAID IN FULL permit | | | 5/10/2002 | | |
|
|
|
|
Routing - PLAN CHECK | 4/26/2002 | | 5/6/2002 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/6/2002 | | PASS |
|
|
|
|
Print Occupancy Form | | | 5/6/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/6/2002 | | DONE |
|
|
|
|
Telephone call | | | 5/6/2002 | | DONE |
|
|
|
permit ready
|
Plan assigned to (JCB) | 3/28/2002 | | 5/6/2002 | | PASS |
Jason Blais
|
|
|
5/6/2002 09:07:31 JCB - activity updated through activity BLDA022 from case BLD02-00691.
|
Routing - FIRE | 4/23/2002 | | 4/26/2002 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 4/26/2002 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 4/23/2002 | | |
|
|
|
Plan resubmittals and response required for further review.
|
Routing - PLAN CHECK | 3/28/2002 | | 4/23/2002 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to Fire Dept. for review.
|
Routing - PUBLIC WORKS | 3/28/2002 | | 3/28/2002 | | PASS |
|
|
|
|
First Notice | 3/27/2002 | 3/27/2002 | 3/27/2002 | | DONE |
|
|
|
3 hrs after hour inspections
|
Routing - PLUMBING | 3/26/2002 | | 3/27/2002 | | PASS |
|
|
|
|
Application received | | | 3/27/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/27/2002 | | DONE |
|
|
|
|