Permit Information
Permit NumberBLD02-00720
StatusExpired
Name BOISE CITY (ANNE FRANK MEMORIAL)
Site Address 800 S 8TH ST
Project NameANNE FRANK MEMORIAL
Customer Number 
ePlanReviewNo
Description
(ANNE FRANK HUMAN RIGHTS MEMORIAL) To construct retaining walls exceeding 4 feet in height to retain earth in the landscaping of a public memorial per engineered approved plans on file. Site reviewed and approved for location in flood plain by H. Wayne Gibbs and Public Works. Zoning approval not required. Special inspection required per attached condition. Note: No other site development is under the scope of the UBC. P.C.#0199-02 (mys)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection2/26/20042/26/20042/26/2004 DONE
DetailsDave Hannah
DOC - Permit Expired2/26/20042/26/20042/26/2004APASS
DetailsDave Hannah
Expired by inspector at 2/26/2004 9:42:02 AM
BLD-Aging Inspection8/12/20038/12/20038/12/2003 FAIL
DetailsCarl Dependahl
contractor not at site... 8/12/2003 1:19:39 PM
PubWorks Occupancy Approval12/18/200212/18/200212/18/2002 DONE
Project found complete, no inspections requested. 12/18/02. M.Strasser
BLD-Conference9/10/20029/10/20029/10/2002PPASS
DetailsCarl Dependahl
w/GS...memorial need handrails, spec insp reports , etc. 9/10/2002 4:33:54 PM
Plan resubmittals received  8/1/2002 DONE
Received two sets of resubmittal sheets M1.1with calcs. Routed to Bill Vandegrift in Plumbing.
Routing - PLUMBING8/1/2002 8/1/2002 PASS
additional cross connection protection may be required, per plans submitted 8/1/02 M1.1 and attached revision from 8" to 6" sewer.
BLD-Footing7/23/20027/24/20027/24/2002APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 07/23/2002 at 17:12:43. Contact: . forming in prgess ok to cover 7/24/2002 10:01:45 AM
BLD-Foundation7/2/20027/3/20027/3/2002APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 07/02/2002 at 20:10:53. Contact: ###-####.
BLD-Footing6/25/20026/25/20026/25/2002PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 06/25/2002 at 10:03:44. Contact: ###-####. WIP STRATA DOING INSPS 6/25/2002 2:51:39 PM
BLD-Footing6/20/20026/20/20026/20/2002PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 06/20/2002 at 07:25:20. Contact: ###-####. 6/20/2002 2:34:26 PM ending stratas report 6/20/2002 2:34:52 PM
BLD-Footing6/13/20026/14/20026/13/2002ACANC
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 06/13/2002 at 11:40:14. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 06/13/2002 at 13:44:11.
BLD-Foundation6/12/20026/12/20026/12/2002PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 06/12/2002 at 07:04:01. Contact: ###-####.
BLD-Concrete6/6/20026/7/20026/7/2002APART
DetailsJim Storey
wip 6/7/2002 11:09:01 AM
BLD-Footing6/6/20026/7/20026/7/2002APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 06/06/2002 at 17:21:16. Contact: ###-####. wip 6/7/2002 11:09:10 AM
BLD-Footing6/5/20026/6/20026/6/2002APART
DetailsCarl Dependahl
darren ###-#### masonry ok pend report. 6/6/2002 3:04:22 PM
BLD-Concrete6/5/20026/6/20026/6/2002APART
DetailsCarl Dependahl
strata onsite...pend report. 6/6/2002 9:50:39 AM
BLD-Framing/Rough-in6/4/20026/5/20026/5/2002APART
DetailsCarl Dependahl
block wall- darrin ###-#### ...pend spec insp report 6/5/2002 2:28:24 PM
BLD-Concrete6/5/20026/5/20026/5/2002PPART
DetailsCarl Dependahl
strata onsite 6/5/2002 5:40:12 PM
BLD-Concrete6/3/20026/4/20026/4/2002APART
DetailsCarl Dependahl
DARREN ###-####...masonry, pending spec insp report. 6/4/2002 9:12:36 AM
BLD-Concrete6/3/20026/3/20026/3/2002PPART
DetailsCarl Dependahl
masonry, 1st lift, east side...visual insp ok...has spec. insp.
BLD-Conference6/3/20026/3/20026/3/2002PPASS
DetailsCarl Dependahl
darren...re spec insp req's; need scope -of- work statement...Strata has been onsite, left initial written report, no apparent discrepancies for 1st lift, east side of bridge 6/3/2002 3:36:15 PM
BLD-Footing5/28/20025/29/20025/29/2002PNR
DetailsCarl Dependahl
FT INSP DARREN ###-#### FTGS ONLY...OK TO USE # 6 bar in lieu of # 4 5/29/2002 5:02:15 PM
BLD-Conference5/29/20025/29/20025/29/2002PCANC
DetailsCarl Dependahl
"pre-con" resub for masonry is approved by Marlene; need spec insp for masonry( & concrete all ready placed??? approved by 425) will advise who will do insps; met w/ Mickelson Masony foreman, advised not to grout prior to insp.
BLD-Footing5/24/20025/28/20025/28/2002PNR
DetailsCarl Dependahl
ft insp -- darin- ###-####...need verts installed. 5/28/2002 4:01:37 PM
BLD-Footing5/24/20025/28/20025/28/2002PCANC
DetailsCarl Dependahl
DARREN ###-####
BLD-Footing5/23/20025/24/20025/24/2002APART
DetailsDave Hannah
###-#### ftg for area south of 9th st ok to pour 5/24/2002 9:55:56 AM
Routing - PLAN CHECK5/20/2002 5/22/2002 PASS
Changed retaining walls to solid fill masonry. Approved resubmittals, sent one copy to job site with owner and other copy to records.
Plan resubmittals received  5/20/2002 DONE
Received two copies of revised sheets S1, S2, one copy of calcs. and one copy of cover letter. Routed to Marlene.
Plan resubmittals received  5/16/2002 DONE
Received two copies of revised sheets S1 & S2. Routed to Carl D. kmm
BLD-Conference5/15/20025/15/20025/15/2002PPASS
DetailsCarl Dependahl
met w/ Les Bock & contractor....requests change to masonry ret. wall; supply calcs & soils report...& written letter with reasoning and requesting change. If all else ok, I'd allow change
(F) Reprint permit  5/10/2002  
Plan assigned to (MYS)4/1/20024/1/20024/17/2002 PASS
DetailsMarlene Southard
4/17/2002 12:44:17 MYS - activity updated through activity BLDA022 from case BLD02-00720.
Routing - PLAN CHECK4/16/2002 4/17/2002 PASS
Reviewed retaining walls only. All other items on site on not considered structures or buildings regulated by the UBC.
PLANS/APPL TAKEN TO FRONT DESK  4/17/2002 DONE
Inspection Record Card- Bld  4/17/2002 DONE
Telephone call  4/17/2002 DONE
called left v-message plans ready 4-17-02 ///dld
Issue PAID IN FULL permit  4/17/2002 DONE
Routing - PUBLIC WORKS4/12/2002 4/16/2002 PASS
Routing - PLANNING4/16/2002 4/16/2002 PASS
Mr. Gibbs as flood plain Administrator.
Plans ACCEPTED BY PLAN TECH  4/12/2002 DONE
Balance of calculations, etc. submitted.
Plan routing begun/NEW & ADDTN  4/12/2002 DONE
Plan resubmittals received  4/2/2002 DONE
Received two sets of stamped/signed plans from Architect. Original plans were swapped with signed plans. Still waiting for calculations, drainage calcs, and O&M.
Plans ACCEPTED BY PLAN TECH  4/1/2002 HOLD
Plans not signed. Contacted Les of this need. Stamped and signed plans will be fed exed 4-2-02. I also requested struct. calcs and am having Les speak with Brian Murphy about drainage plan, calcs. and O&M manuel. KMM
4/10/02 Received struct. calcs. Still waiting for drainage calcs, three extra civil. Let Les know of this need. kmm
Application received  4/1/2002  
Recd Pcfee & Taken To Pln CK  4/1/2002  
Fee Review-notes4/1/20024/1/2002