Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD02-00731
StatusFinaled
Name NYK LOGISTICS & MEGACARRIER
Site Address 101 S CAPITOL BLVD Unit: 1201
Project NameUS BANK-12TH FLR
Customer Number 
ePlanReviewNo
Description
(NYK LOGISTICS & MEGACARRIER - US BANK BLDG - 12TH FLR) This building is fire sprinklered because it is a high-rise. To expand an existing 9,527 square foot office tenant space into an adjacent 2,335 square foot area. After the expansion, this office tenant space will have a total floor area of 11,862 square feet and will occupy the entire floor. Selective nonstructural demolition is also covered under this permit. Work is to include interior nonbearing walls, suspended ceilings, and finishes all per approved drawings and plan review conditions on file. Also, the common restrooms on this floor are being modified to be accessible to the disabled. The location of fire sprinkler heads shall comply with NFPA 13-1999 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  7/2/2013 DONE
Fee Review-notes7/22/20037/22/20037/22/2003 DONE
1. Fees only charged for original Certificate of Value of $52,000. Revised Certificate of Value of $77,000 submitted on 6/3/02.
2. Additional values from subcontractors.
Permanent occupancy  8/12/2002 DONE
Perm. Occ. Cert. #9294 issued 8-12-02 to NYK Logistics & Megacarrier on the 12th floor of the U.S. Bank Bldg.
BLD-Final8/7/20028/7/20028/7/2002PPASS
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 08/07/2002 at 09:45:13. Contact: ###-####.
BLD-Final8/6/20028/6/20028/6/2002PNR
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 08/06/2002 at 10:53:31. Contact: ###-####....need plans onsite, recall 8/6/2002 5:07:54 PM
FIRE-Final Inspection8/2/20028/2/20028/2/2002PPASS
DetailsRick Jackson
Permanent Occupancy 8/2/20028/2/2002 DONE
Details
BLD-Framing/Rough-in7/11/20027/12/20027/12/2002PPART
DetailsCarl Dependahl
DAVE ###-#### wip, complete plbg, ok to use extended office area 7/12/2002 3:01:26 PM
FIRE-Alarm Testing7/3/20027/9/20027/9/2002APASS
DetailsRick Jackson
###-#### loren please call 1st alrms tested okay; need rated doors at restroom areas 7/9/2002 10:09:24 AM
BLD-Framing/Rough-in7/2/20027/3/20027/3/2002APART
DetailsTom Arcoraci
###-#### samm wip 7/3/2002 11:51:57 AM
BLD-Framing/Rough-in6/27/20026/27/20026/27/2002PFAIL
DetailsCarl Dependahl
r/i- sam- ###-#### c/n, extend 1hr assy's to deck, seal penetrations at wa 6/27/2002 4:08:48 PM lls & floors 6/27/2002 4:09:00 PM
BLD-Conference6/26/20026/26/20026/26/2002PPASS
DetailsCarl Dependahl
###-#### SAM ADA clr at rest rm.ok due to existing stand pipe ( 19" to c.l.) Awaiting archs detail re corridor walls 6/26/2002 2:33:10 PM
FIRE-Conference6/24/20026/25/20026/25/2002APART
DetailsRick Jackson
###-#### exit signs to installed as redlined on approved plans 6/25/2002 8:01:34 AM
BLD-Conference6/20/20026/21/20026/21/2002APASS
DetailsCarl Dependahl
###-#### CALL FIRST need arch's detail to maintain 1hr corridors around core 6/21/2002 2:35:46 PM
BLD-Conference6/21/20026/21/20026/21/2002PCANC
DetailsCarl Dependahl
Issue PAID IN FULL permit  6/10/2002 DONE
Inspection Record Card- Bld  6/5/2002 DONE
Print Occupancy Form  6/5/2002 DONE
Telephone call  6/5/2002 DONE
CALLED RYAN 6-5-02
(F) Reprint permit  6/5/2002 DONE
Routing - PLAN CHECK4/23/2002 6/4/2002 PASS
(4-29-02) Received a letter from the architect requesting that upgrades for accessibility not be required. (5-1-02) Request was denied by the Building Official. (6-4-02) Drawings showing the common restrooms upgraded to be accessible to the disabled were provided. The project was approved.
PLANS/APPL TAKEN TO FRONT DESK  6/4/2002 PASS
Plan assigned to (CJW)4/5/2002 6/4/2002 PASS
DetailsCarl Westfall
6/4/2002 11:19:01 CJW - activity updated through activity BLDA022 from case BLD02-00731.
Plan resubmittals received  6/3/2002 DONE
Received two copies of revised sheets A5.0 A5.1 and one copy of revised cert. of value. Routed to Carl W. kmm
Routing - FIRE4/18/2002 4/23/2002 PASS
Plan Review Completed(1st rev)  4/23/2002  
Failed first UBC review.
Routing - PLAN CHECK4/9/2002 4/18/2002  
Failed first UBC review. UBC plan review started April 17, 2002 and was finished the next day. Resubmitted drawings from the architect were required. See the conditions list. A copy of the plan review report was sent to the architect.
Routing - PUBLIC WORKS4/5/2002 4/8/2002 PASS
Plans ACCEPTED BY PLAN TECH  4/2/2002 DONE
First Notice4/1/20024/1/20024/1/2002 DONE
Application received  4/1/2002  
Recd Pcfee & Taken To Pln CK  4/1/2002 DONE