Permit NumberBLD02-00732
StatusFinaled
Name STEVE WELSH (OWN REP)
Site Address 217 S 11TH ST
Project Name 
Customer Number 
ePlanReviewNo
Description
(OLIVER RUSSELL & ASSOCIATES) This building is NOT fire sprinklered. To convert an existing automobile repair garage to an office building. The existing 5,130 square foot 1st floor and 1,400 square foot 2nd floor are being remodeled. Work is to include filling in openings in the South exterior wall, raising the parapet on the South and North exterior walls, new exterior doors, new exterior windows, roll down fire shutters to protect the window openings in the North exterior wall, 2 restrooms accessible to the disabled, a new stairway to serve the 2nd floor, interior nonbearing walls, and finishes all per approved drawings, engineering, and plan review conditions on file. A demolition permit (BLD02-00876) was issued earlier. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  5/21/2012 DONE
Fee Review-notes7/22/20037/22/20037/22/2003 DONE
Permanent Occupancy 9/23/20029/23/2002 DONE
Details
Permanent occupancy  9/23/2002 DONE
Perm. Occ. Cert. #9372 issued 9-23-02 to Oliver Ruseell & Associates.
FIRE-Final Inspection9/12/20029/12/20029/12/2002PPASS
DetailsRick Jackson
mike; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
BLD-Final9/12/20029/12/20029/12/2002PPART
DetailsTom Arcoraci
mike; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung ok for perm occ after code enf signs 9/12/2002 4:08:17 PM
BLD-Conference7/31/20028/1/20028/1/2002APART
DetailsDave Hannah
re glass block ok for 1hr rating and masonry infill on windows on west wall ok to hand grout small openning and high lift grout on large opennings 8/1/2002 3:43:01 PM
BLD-Conference7/31/20027/31/20027/31/2002PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 07/31/2002 at 11:25:55. Contact: ###-####....details for glass; will recall... 7/31/2002 4:43:48 PM
BLD-Framing/Rough-in7/25/20027/29/20027/29/2002APART
DetailsTom Arcoraci
MIKE; Phone #: ###-#### ok to cover steel int studs 7/29/2002 10:53:39 AM
BLD-Foundation6/20/20026/21/20026/21/2002APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 06/20/2002 at 11:40:48. Contact: ###-####. slab & frost wall ok to pour. 6/21/2002 9:56:40 AM
Issue PAID IN FULL permit  5/24/2002  
Plan assigned to (CJW)4/5/2002 5/20/2002 PASS
DetailsCarl Westfall
5/20/2002 08:20:26 CJW - activity updated through activity BLDA022 from case BLD02-00732.
Routing - PLAN CHECK5/20/2002 5/20/2002 PASS
PLANS/APPL TAKEN TO FRONT DESK  5/20/2002 PASS
Inspection Record Card- Bld  5/20/2002 DONE
Print Occupancy Form  5/20/2002  
Telephone call  5/20/2002 DONE
CALLED MIKE LEFT V-MESSAGE PERMIT READY 5-20-02///DLD
Routing - PLANNING5/15/2002 5/17/2002 PASS
Approve per CZC02-00047. A joint access/parking agreement with the property to the west shall be submitted to the Planning Division prior to issuance of an occupancy permit.
Routing - PLAN CHECK4/25/2002 5/15/2002 PASS
Drawings approved, with conditions, after resubmittal review.
Plan resubmittals received  5/9/2002 DONE
Received two copies of revised sheetsa1.11, a2.11, a2.12, a2.31, a3.11, a3.12, a5.11, a6.11, a6.12, two sets of structural calcs. & details. One copy of response letter. Routed to Carl W. kmm
Plan Review Completed(1st rev)  4/25/2002  
Failed first UBC review.
Routing - FIRE4/22/2002 4/25/2002 PASS
APPROVED WITHOUT WRITTEN COMMENT
Routing - PLAN CHECK4/12/2002 4/22/2002  
Failed first UBC plan review. UBC plan review started April 18, 2002 and finished April 22, 2002. Resubmitted drawings were required from the architect. See the conditions list. A copy of the plan review report was sent to the architect.
Routing - PUBLIC WORKS4/5/2002 4/12/2002 PASS
Plan resubmittals received  4/8/2002 DONE
Requested Demo Permit. Received revised Certificate of Value with seperate Certificate of Value for Demo Permit. Routed to Carl Westfall.
Plans ACCEPTED BY PLAN TECH  4/2/2002 PASS
Plans on my desk, waiting for mech plans that Rob Thornton will be bring in, along with the DR #. Requires signatures on cert. of value and involved parties sheet. KMM
4/3/02 received mech. sheets (not signed) however is for office not medical, laundry or food service. I have spoke with Carl of Erstad-Thornton about the DR# for this project. They are waiting for Tempra to get back around the 8th of April.
First Notice4/1/20024/1/20024/1/2002 DONE
Application received  4/1/2002  
Recd Pcfee & Taken To Pln CK  4/1/2002 DONE
First Notice 5/31/2012